Hornsby Shire Council v Viscardi
[2015] NSWCA 417
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2015-11-23
Before
Beazley P, Gleeson JA, Simpson JA
Source
Original judgment source is linked above.
Judgment (15 paragraphs)
Background facts
- The bitumen patch which was the subject of the restoration work had been cut using a saw, as evidenced by the straight edges of the repair work. The patch was measured by the Council's engineering expert, Mr Clark, to be 1070 mm by 1000 mm. Mr Clark measured the depth of the reinstated asphalt surfacing to be 25-30 mm. The repair work was carried out using hot mix bituminous asphalt (hot mix).
- The Council's pavement engineer, Mr Suthersan, gave evidence of the Council's system of inspection and maintenance repair and of his inspection of the car park some months before the accident, and of the accident site shortly after the respondent's fall.
- So far as is relevant to the central question on the appeal on liability, Mr Suthersan's evidence was as follows:
- The Council had a system of an annual inspection of its roads and car parks. If a problem was encountered on an inspection, it was recorded. In addition, any complaints from the public were also recorded;
- When repair work was required to be undertaken, it was carried out either by a Council maintenance crew or a contractor. The question of who carried out the repair work depended upon the nature and extent of the problem;
- The Council's maintenance crew carried out repairs to pot holes. The maintenance crew did not use saw cutting to do so;
- The maintenance crew also carried out restoration work if the work involved was undertaken on a surface area no more than approximately 1 m2. Such work could involve saw cutting;
- If the Council considered that the repair work involved more than a routine repair, for example, if the work was to be undertaken on a surface area larger than 1 m2, the work would be put on the "works program". A work order would then be issued to an outside contractor engaged by the Council to carry out such work. The contractor then invoiced the Council for the work after inspection and approval for payment by a Council inspector. Such work could involve saw cutting;