© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2002] QCA 24
Court of Appeal (Qld)
2002-02-15
de Jersey CJ, Davies JA and Ambrose JJoint reasons for judgment of de, Jersey CJ and Davies JA, separate reasons of Ambrose J, concurring as to the
Original judgment source is linked above.
Text from the judgment source.
SUPREME COURT OF QUEENSLAND
CITATION:
Hennessey Glass & Aluminium P/L v Watpac Australia P/L [2002] QCA 24
PARTIES:
HENNESSEY GLASS & ALUMINIUM PTY LTD
ACN 051 330 100
(plaintiff/respondent)
v
WATPAC AUSTRALIA PTY LTD ACN 010 462 816
(defendant/applicant/appellant)
FILE NO/S:
Appeal No 9110 of 2001
DC No 523 of 2000
DIVISION:
Court of Appeal
PROCEEDING:
Application for Leave s 118 DCA (Civil)
ORIGINATING COURT:
District Court at Brisbane
DELIVERED ON:
15 February 2002
DELIVERED AT:
Brisbane
HEARING DATE:
30 January 2002
JUDGES:
de Jersey CJ, Davies JA and Ambrose J
Joint reasons for judgment of de Jersey CJ and Davies JA; separate reasons of Ambrose J, concurring as to the orders made.
ORDER:
1.
Grant leave to appeal.
2.
Order that the answer to the question "upon the proper construction of the contract, was the supply and installation of hardware to the unframed glass doors to the corporate suites described in the Don Mathieson and Staff Glass Pty Ltd invoice number 377682 an obligation required to be performed by the plaintiff under the contract such that the performance of that obligation would not entitle the plaintiff to any adjustment of the contract sum under the contract?" be set aside in so far as it concerns the matter of supply and adjourn further consideration of the answer to that part of the question to the District Court.
3.
No order as to costs of the appeal.
CATCHWORDS:
CONTRACTS-GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION AND INTERPRETATION - CUSTOM
AND USAGE - INCORPORATION INTO CONTRACT - KNOWLEDGE OF BOTH PARTIES - appeal against decision of District Court judge - where building contract for installation of doors and windows - dispute over terms of sub-contract - whether the terms of a sub-contract had been correctly construed - construction and interpretation of the "scope of works" clause - whether subject doors were required to be framed or unframed - whether the respondent had to supply unframed glass doors pursuant to the sub-contract - whether trial judge proceeded on an erroneous factual basis that the sub-contract provided that the subject doors were to be framed.
INTERPRETATION - ADMISSIBILITY OF EXTRINSIC EVIDENCE IN RELATION TO INSTRUMENTS - WHEN EVIDENCE ADMISSIBLE TO SHOW MEANING OF TERMS - where ambiguity in contract - whether Court should resort to the use of extrinsic material to determine the true meaning of the contract and the intention of both parties
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - OTHER MATTERS
Bank of New Zealand v Simpson [1900] AC 182, applied.
Codelfa Construction Pty Ltd v State Rail Authority of NSW (1982) 149 CLR 337, applied
Turner v Bladin & Ors [1951] HCA 13; (1950-51) 82 CLR 463, cited.
COUNSEL:
JK Bond SC, with RC Schulte for the appellant
P A Keane QC, with P A Hastie for the respondent
SOLICITORS:
Dibbs Barker Gosling for the appellant
Phillips Fox for the respondent.
Hennessey Glass & Aluminium P/L
Watpac Australia P/L [2002] QCA 24
(1982) 149 CLR 337