The first Deed remained entirely unperformed
57 I agree with Simos J that even the default provisions of the first Deed were entirely unperformed by the commencement of proceedings. There was a total failure of consideration, or agreed return, under the relevant contractual arrangement.
58 The parties are agreed that it is necessary to examine the first Deed to see what it was that the respondent had bargained for in return for his $100,000 (see David Securities Pty Ltd v Commonwealth Bank of Australia (1992) 175 CLR 353 at 382, Baltic at 351). The receipt of benefits referable to matters other than performance of the relevant contractual arrangement will not preclude a plaintiff from recovering payments as on a "total failure of consideration" (see Rover International Ltd v Cannon Film Sales Ltd (No 3) [1989] 3 All ER 423 at 432-4).
59 The secondary obligation of the appellants to the respondent had two aspects:
• transfer (ie vesting) of 20% of Heckenberg Holdings' interest in the quarry; and
• transfer (ie vesting) of 20% of the shares in Port Macquarie Concrete.
60 Neither event occurred.
61 Nor was there partial performance of either obligation, for the reasons which follow.
62 The transfer of 20% of Heckenberg Holdings' unregistered leasehold interest in the quarry was capable of performance by deed. None was executed. The 1991 arrangement that resulted in $12,288.28 being paid to the respondent was not performance of the default provision concerning the assignment of a share in the quarry lease, notwithstanding that (for a time) it produced an equivalence of the benefits that might have come from performance of the default obligation. The 1991 arrangement represented the conferral by Heckenberg Holdings on Wilson River Sand and Gravel of some interest in the lease. The evidence does not disclose whether this was by way of assignment, sublease or licence. Whatever was involved, it was not a performance of the default obligation. The very fact that it was negotiated in 1991 and stemmed from a separate agreement to which Mr Fleming and Wilson Sand and Gravel were parties further confirms this. Indeed, the 1991 arrangement was incompatible with performance of the default provision, because it was based upon Heckenberg Holdings retaining the totality of its leasehold interest, albeit that this enabled it to provide the respondent with an equivalent benefit for the (limited) time of its duration. The letter of 21 December 1993 shows Heckenberg Holdings still regarding itself as the owner of the total leasehold interest. This interpretation differs from that of Simos J in some respects (cf RB 156-8) but is open in relation to the unchallenged primary facts.
63 It does not assist the appellants that the 1991 arrangement entailed express recognition of the respondent's entitlement to a 20% share in the lease "in accordance with our earlier agreement" (ie the first Deed). Performance of a contract requires more than recognition of its continued existence.
64 The submission that it was for the respondent to tender the appropriate assurance before he would put the appellants in breach must be rejected for several reasons. I respectfully adopt those given by Simos J and would add the following.
65 No question of possible performance according to the default provision could have arisen until March 1991 when Heckenberg Holdings eventually prised its interest in the lease back from Quizrock. The parties then moved to the new arrangement involving Wilson River Sand and Gravel which (as indicated) was not itself a performance of the first Deed. Nor was there any performance during the time when Heckenberg Holdings chose to operate the lease itself (albeit unprofitably). The suggestion that the respondent was obliged to take the first step and to tender a draft deed of assignment before putting the appellants into breach of the default obligation strikes me as fanciful in these circumstances.
66 More importantly, this abstruse and unpleaded conveyancing point (which was not raised below until after the close of evidence and which was not supported by evidence) is irrelevant. That is because there was still total non-performance on the appellants' part up to the time that the respondent brought the shutters down by commencing the proceedings in late 1993. The reality appears to be that the whole project was either abandoned by mutual agreement in 1992-1993 or (at the very least) performance of it was left in all parties' "too hard" baskets. It is unnecessary to decide which was the situation, because the important thing is that the contract was held to have been brought to an end by commencement of the proceedings in 1993. Either way, there was "total failure of consideration" regardless who may have had the next obligation with regard to what I shall assume was a wholly incomplete "conveyancing" transaction.
67 To say that the appellants may not have been entitled to make secret profits out of the quarry lease while the agreement with the respondent remained extant is not the same as saying that the appellants had taken steps in performance that prevented a claim based upon "total failure of consideration" once the contractual arrangement had been brought to an end.
68 As regards the default obligation to vest a 20% shareholding in the respondent, this obligation was wholly unperformed. In light of the matters summarised in pars 8-11, I do not accept that Simos J erred in holding that he was not satisfied that the necessary board resolution concerning the allotment ever occurred, a fortiori that the appellants caused the respondent to become a member of Port Macquarie Concrete.
69 The appellants' failure to answer the respondent's letter of 1 April 1991 (par 14, above) in which he enquired about receiving a share certificate is proof sufficient that performance of this obligation was called for and did not occur.
70 It is unnecessary to decide whether the allotment (if it occurred and if it were perfected) would have constituted performance of the first Deed. It is hardly self evident, in circumstances where four-fifths of the shares were held by the appellants and where the intent of the arrangements effectuated by the first Deed was that there would be partners additional to the appellants and the respondents.
71 The appeal should be dismissed with costs.
72 MEAGHER JA: At all material times a company called Port Macquarie Concrete Pty Ltd owned certain assets situate at Port Macquarie, and another company called Heckenberg Holdings Pty Limited owned certain other assets, including a quarry. The appellants, Mr and Mrs Heckenberg, were the only directors of, and shareholders in, both companies.
73 On 24 May 1989 the two appellants entered into a deed with the respondent Mr Delaforce. That deed provided that Port Macquarie Concrete Pty Ltd would transfer all its assets to a company not yet formed, and that Heckenberg Holdings Pty Ltd would transfer its interest in its quarry to that new company. It also provided that Mr Delaforce would acquire a 20% holding in the new company, in return for a payment by him to the appellants of the sum of $100,000.00. It acknowledged that that payment had been made.
74 It then provided, in what I might call a "default provision,"
"If for any reason the vendors are unable to transfer to the proposed new Company the assets of Port Macquarie Concrete Pty Ltd and its right title and interest in the quarry presently the property of Heckenberg Holdings Pty Ltd, then the vendor will transfer to the said ERIC DELAFORCE twenty percent (20%) of its interest in the quarry the property of Heckenberg Holdings Pty Ltd and twenty percent (20%) of the shares in the said Port Macquarie Concrete Pty Ltd."
75 Performance of the covenants in the deed of 24 May did not proceed, and a second deed was entered into between the same parties on 18 July 1989. That deed recorded another joint venture agreement between the parties. It also recited:
"The parties hereto have agreed to terminate the said Deed" ( scil the May 1989 deed)
76 It contained two covenants setting out the terms of the new agreement, and then in clause 3 provided as follows:
"3. Payment pursuant to Clause 1 and 2 hereof is strictly subject to and conditional upon PORT MAQUARIE CONCRETE PTY LIMITED and HECKENBERG HOLDINGS PTY LIMITED completing the sale of their property and gravel lease respectfully to PLASMILL PTY LIMITED"
Almost needless to say neither of the two companies completed their sale to Plasmill Pty Limited.
77 In these circumstances Simos J held that Mr Delaforce was entitled to a substantial verdict against the appellants, who now appeal against his decision.
78 Two other aspects of this case deserve mention. One is that, the first deed having been expressly repealed of the second deed, and the second deed never having taken effect, what regulated the relationship between the parties? The answer which appealed to his Honour, and which was embraced by both parties, both at first instance and on appeal, was that the "default provisions" of the first deed applied. In my view we should approach the appeal on that basis.
79 The second is that the quarry has been operating since the date of the second deed, continuously it would seem since 1991, under licence to another company called Wilson River Sand and Gravel Pty Ltd, and has been producing profits. One fifth of any profit has been paid by the appellants to the respondent. The amounts received by the respondent total $12,288.28.
80 Simos J, as I have said, found against the appellants. He found that there had been a breach of the "default provisions" of the first agreement, which resulted in a total failure of consideration as far as the respondent was concerned. I have difficulty in accepting his Honour's conclusions, and my difficulty stems mainly from the initial assumption (and assumption it was more than finding) that there was a breach by the appellants of the promises contained in the "default provisions"
81 The first promise was to convey to the respondent "20% of its (sic) interest in the quarry the property of Heckenberg Holdings Pty Limited." That is a promise to convey 20% of the property, whatever it was. It is not a promise to convey any legal estate. The owner of the property on which the quarry is situated is a company called Madwood Pty Ltd, which had given a 20-year lease of the quarry to Heckenberg Holdings Pty Ltd. That lease was unregistered and unregisterable. This was decided by Hodgson J in Madwood Pty Limited v Heckenberg Holdings Pty Limited (NSW S.C. (Eq), 9 Nov, 1988, unreported). So, then, Heckenberg Holdings had a merely equitable interest, of which it was contractually obliged to assign 20% to the respondent. Presumably, in normal circumstances, the way to do that would be by deed, a deed of the simplest form sufficing: such would be required by S.23C(1) of the Conveyancy Act 1919. In the present case, it is arguable that not even that would have been necessary, since Mr Delaforce had furnished full consideration, thereby obtaining a 20%interest by way of resulting trust, in which case S.23 C (2) would dispense with the formalities of S.23C(1). This would be bolstered both by the maxim that equity looks on as done what ought to be done, and of the doctrine enunciated by Lord Westbury LC in Holroyd v Marshall (1862) 10 HLC 191 that any agreement for consideration (even executory consideration) effects an immediate assignment of the totality of the vendors interest.
82 Further, one must address the question what if any rights Mr Delaforce would be entitled to even if he had received a one-sentence deed of conveyance. Not , assuredly, any right of possesion of the land leased. It would only be a right to 20% of the profits from the lease. This he received. He thus has obtained all which, in practical terms, he would ever have been entitled to obtain.
83 On this analysis, it is hard to see any breach of a promise to "transfer" a 20% interest in the quarry.
84 But there is more to it than that. The cases do make it plain that it is the assignee's duty to draft the assurance and tender it to the assignor, upon whom the duty to execute it then arises. This is not, as his Honour seemed to think, a mere conveyancing practice. It is a fundamental principle of conveyancing law, affirmed in England ( Poole v Hill (1840) 6 M&W 835, in Victoria (Pam v Barbour) (1870) 1 VR (L) 136, in New South Wales (Layard v Allen (1881) Tarl; and in South Australia ( E.Brown Pty Limited v Florence [1967] SASR 214). In this case it was not disputed that Mr Delaforce never drafted or tendered any draft conveyance.
85 Moreover, the appellants were forever protesting their willingness to convey the appropriate interest to Mr Delaforce. For example, on 21 December 1993 their solicitor wrote to Mr Delaforce's solicitors:
"If their is some further document that your client wishes executed evidencing his share in the quarry interest, please submit this document for our client's consideration. On our instructions, Mr Delaforce has never suggested that he required any transfer documents and our client has been kept fully informed as to the operations of the quarry."