1 Appeal No 11200 of 2005 concerns a letter dated 26 August 2005 issued under s 22C of the Rivers and Foreshores Improvement Act 1948, (RFI Act), requiring the provision of a security bond in the amount of $35,000 to secure restoration of the cliff face as a precondition to the issue of a Part 3A permit to carry out works on Lot 115, DP 1111, being No 10 Fortescue Street, Chiswick, the applicant's property, that is 'protected land' as defined by the Act. A condition of the draft permit was included with the 26 August letter that requires the restoration of the cliff face in two stages.
2 Appeal No 11202 of 2006 concerns a direction dated 26 August 2005 issued by the respondent under s 22G of then RFI Act to carry out specified rehabilitation works on a collapsed cliff face at the land.
3 Appeal No 11203 of 2005 was under s 97 of the Environmental Planning and Assessment Act 1979, against the decision of the City of Canada Bay (the council) to refuse a development application to construct a seawall, swimming pool, retaining wall, access stairs, landscaping, to relocate boulders and to excavate and level the land at Lot 115, DP 1111 being No 10 Fortescue Street, Chiswick. As integrated development is involved in this appeal and a Part 3A permit is required under the RFI Act, the second respondent (the Minister) has been joined as a party.
4 The applicant did not pursue Appeal No 11201 of 2005 under s 97 of the Environmental Planning and Assessment Act 1979 that was against the decision of the council to refuse a development application to construct a jetty, ramp and pontoon on the bed of Parramatta River adjacent to the subject land.
5 I viewed the land in company with the parties from the water on the morning of the first day of proceedings. The matter was heard on two days in December 2006 and was not completed. Case management was held on 22 December 2006, 12 February 2007 and 04 April 2007 seeking to finalise the matter.
6 Following intensive negotiation between the parties many of the issues have been resolved. I am satisfied that the outstanding matter of the type and position of steps leading to the waterfront has now been properly addressed and I conclude that the applicant should succeed.
The land
7 The land is situated on the northwestern side of Fortescue Street between Riverview and Chiswick Streets and has a frontage to Parramatta River to the northwest. It has a frontage of 20.115m to Fortescue Street and an irregular depth of 62.79 and 68.275m, with an area of some 1,315m2. The land falls about 16m from Fortescue Street to the Parramatta River.
8 Development adjoining the subject land comprises residential properties. Abutting to the southwest is a two-storey dwelling house at No 12 Fortescue Street, and to the northeast are two dwelling houses in a battle-axe arrangement at Nos 8 and 8a Fortescue Street. Opposite the land to the southeast are other residential dwellings.
Relevant planning controls
Drummoyne Local Environmental Plan 1986, (DLEP)
9 Under the provisions of the DLEP the land is zoned 2(a) Residential and the proposal to construct a seawall, swimming pool, retaining wall, access stairs, landscaping among other things is permissible with consent.
Drummoyne Comprehensive Development Control Plan 1999, (DDCP)
10 Section 6.15 of the DDCP relates to the Foreshore Building Line, (FSBL).
State Environmental Planning Policy No 56 - Sydney Harbour Foreshores and Tributaries, (SEPP56)
11 SEPP56 is now repealed but was applicable when the application was lodged.
Sydney Regional Environmental Plan No 22 - Parramatta River, (SREP22)
12 SREP22 is now repealed but was applicable when the application was lodged.
Sydney Regional Environmental Plan (Sydney Harbour Catchment) 2005, (SREP2005)
13 SREP2005 applies to the land.
The proposal and its history
14 Appeal No 11203 of 2005 involves Development Application No 391/2005 that was lodged with the respondent council on 13 July 2005 to construct a seawall, swimming pool, retaining wall, access stairs, landscaping, to relocate boulders and to excavate and level the land.
15 Previous development applications include:
· Development Application No 915/02 to demolish the existing dwelling and to erect a new dwelling, was approved by the council on 6 May 2003. The construction of the dwelling has commenced has not been completed and the proposed works are part of the development of the same land.
· Development Application No 56/04 for an in ground swimming pool, terrace and landscaping was refused by the council on 2 July 2004 on the grounds that a Part 3A permit was refused by NSW Waterways. This was on the grounds of inadequate information being submitted with the application and the alterations to the dwelling were indicated on the submitted plans but not applied for in the application.
· Development Application No 847/03 for the erection of a seawall, removal of a rock shelf and construction of access stairs was refused by the council on 17 February 2004 on the grounds that the application did not comply with the objectives and controls contained in SREP22 and the DCP for Sydney Harbour and Parramatta, a Part 3a permit was refused by NSW Waterways and there were said to be adverse impacts on the natural environment.
· Development Application No 423/03 for the erection of a seawall at the property was refused by the council on 22 September 2003 on the grounds that the application did not comply with the objectives and controls contained in SREP22 and the DCP for Sydney Harbour and Parramatta, and a Part 3a permit was refused by NSW Waterways.
Notification
16 Development Application No 391/2005 the subject of Appeal No 11203 of 2005, to construct a seawall, swimming pool, retaining wall, access stairs, landscaping was notified to nearby owners and occupants from 21 July 2005 to 8 August 2005 and the council received one submission.
17 An integrated development referral was made to the NSW Maritime Authority on 15 July 2005. The council received a response dated 23 August 2005 advising that a Part 3a permit would not be issued, and that land owner consent from NSW Maritime is required and that concern is raised to the merits of the proposed development.
The council's decision
18 By notice dated 2 September 2005 the council refused Development Application No 391/2005 for the following reasons:
- Pursuant to Clause 49 of the Environmental Planning and Assessment Regulation 2000, the applicant has failed to obtain consent from the owner of the land 'NSW Maritime' to land, which the development consent relates.
- Pursuant to Section 91A(4) of the Environmental Planning and Assessment Act 1979, the approval body (NSW Maritime) has not granted approval to the issuing of a Part 3A permit which is required in order for the development to be lawfully carried out, and therefore the consent authority must refuse consent to the application.
- Pursuant to Clause 7(g) of State Environmental Planning Policy No 56 - Sydney Harbour Foreshores and Tributaries, the application does not protect or improve unique visual qualities of the Harbour, its foreshores and tributaries.
- Pursuant to Clause 7 of the Sydney Regional Environmental Planning Policy No 22, the Foreshores and Waterways Planning and Development Advisory Committee has recommended refusal of the application on the following grounds:
a) the proposal involves a radical alteration of the subject foreshore and will result in a highly modified foreshore environment dominated by man-made features such as the retaining wall, seawall and access stairs,
b) the proposal would irreversibly destroy the remaining natural features of the subject land. In the Committee's view the large boulders in the Parramatta River remain a natural feature of the locality,
c) the proposal is contrary to the performance criteria for landscape character type 14 under the Development Control Plan for Parramatta River which states that:
(i) remaining natural elements along the foreshore are preserved and,
(ii) visual continuity of elements is not broken by development example cliff features,
d) the proposal is contrary to clause 4.17 of the DCP which states that where the foreshore is in its natural state seawalls generally will be discouraged. In the Committee's view, the foreshore at the water's edge has not been irreversibly damaged by previous excavation works and should be restored to its natural state,
e) the proposal will have an adverse visual impact on the scenic quality of the subject foreshore when viewed from the Parramatta River,
f) the proposal is inconsistent with the aims of Sydney Regional Environmental Plan No 22 and the guiding principles of State Environmental Planning Policy No 56 relating to protection of scenic quality, and
g) the proposal is inconsistent with clauses 17(b), (d) and (e) of the exhibited Draft Sydney Regional Environmental Plan (Sydney Harbour Catchment) 2004 relating to the protection, reinstatement and restoration of terrestrial ecological communities, natural inter tidal foreshore areas and riparian land.
- Pursuant to Clause 2(2)(e)(i) of the Sydney Regional Environmental Planning Policy No 22, the application does not protect and enhance the landscape and scenic qualities of Parramatta River.
- Pursuant to Clause 2(2)(e)(iii) of the Sydney Regional Environmental Planning Policy No 22, the application does not preserve the natural foreshores of the Parramatta River and detracts from their natural character.