Hadgkiss v Construction, Forestry, Mining and Energy Union
[2007] FCA 87
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2007-02-09
Before
Graham J
Source
Original judgment source is linked above.
Judgment (87 paragraphs)
Introduction 1 These proceedings concern alleged contraventions of certain provisions of the Workplace Relations Act 1996 (Cth) ('the Act') said to have been committed in the Illawarra region of New South Wales on Monday 19 January 2004, Tuesday 17 February 2004 and Wednesday 18 February 2004. Most of the contraventions are said to have occurred at a building site located in Woodhill Street, Fairy Meadow ('the Fairy Meadow site'). The others are said to have occurred in the first and/or second respondents' Wollongong office ('the CFMEU office'). 2 To understand the circumstances surrounding the alleged contraventions it is also necessary to have regard to another building site located at the corner of Bank and Harbour Streets in Wollongong ('the Wollongong site') 3 The principal in respect of the Fairy Meadow site was Ousley Pty Limited ABN 41 073 191 992 which was represented on site by Mr Les Dowse. The head contractor at that site was Lanskey Constructions Pty Limited ABN 66 010 636 512 ('Lanskey'). Mr David Rowland, who served as site manager for Lanskey, was Lanskey's senior representative on the site. His general foreman or '2IC' was a Mr Chris Taylor (referred to in some diary notes as 'C.T.') The building being constructed at the Fairy Meadow site was known as the 'Northgate Apartments' building. It consisted of four separate blocks - A, B, C and D. All four blocks shared a common car parking area at ground floor level. Blocks A and D had five upper floors including a loft or penthouse level. Blocks B and C were similar, but they had six upper floors including a loft or penthouse level. Approximately ten units per floor were being constructed on the upper floors of each block with approximately eight units on each loft or penthouse level. The total value of the construction was approximately $23 million. The relevant work for present purposes was gyprock plastering work in blocks A and D. 4 The head contractor in respect of the Wollongong site was Hansen Yuncken Pty Limited ABN 38 063 384 056 ('Hansen Yuncken'). The building under construction on that site was known as 'The Pavilions, City Beach Apartments - Stage 2'. It was a 52 unit development of about ten storeys in height. By February 2004 the main concrete structure at the Wollongong site was substantially complete and the façade with windows etc was being added to the lower floors. Once again the relevant work was gyprock plastering. 5 In the course of both building projects the contractors had dealings with Pro Finish Interiors Pty Limited ABN 16 096 811 059 ('Pro Finish Interiors'), which in March 2005 became known as AAA Interiors Pty Limited. In January/February 2004 it traded as 'Pro Finish Interiors'. Its principal director was Mr Spiro Repas. Its site foreman at the time was Mr Glenn Suter. 6 Lanskey also had dealings with Innovation Interiors Pty Limited ABN 89 104 518 989 ('Innovation Interiors'). That company entered into external administration on 24 February 2005. In January/February 2004 its principal director was Mr Nenad (also known as 'Ned') Djukic. Its site foreman at the Fairy Meadow site was its leading hand, Mr Graham Boyd. 7 In turn, Innovation Interiors also had dealings with some of Pro Finish Interiors' workers in respect of work at the Fairy Meadow site. 8 Innovation Interiors had a contract to carry out plastering work in respect of Blocks A, B, C and D at the Fairy Meadow site. As it was running behind with its work it had part of the work on Block A taken off it and, at the same time, all of the plastering work in respect of Block C. The work that was taken off Innovation Interiors in respect of Block A was plastering work in respect of the loft or penthouse level of that block. Thereupon, the builder retained a company known as Fast Track to attend to the plastering work in respect of the loft or penthouse level of Block A and another company was retained to carry out the plastering work in respect of Block C. 9 After about four to six weeks on the site, commencing before Christmas 2003, Fast Track left the site with some of the work on the loft or penthouse level of Block A unfinished. All the sheeting had been done. The majority of the outstanding work was to finish the setting of the sheeting - putting a coating over the gyprock - and to attend to defects. Both Innovation Interiors and Pro Finish Interiors submitted prices for the completion of Fast Track's work but the job was awarded to Pro Finish Interiors. An order, signed by Ian Herd, a Lanskey foreman, was formally placed by Lanskey on 'Pro Finnish (sic) Interiors' on Monday 19 January 2004 to 'Finnish (sic) works to block A' - 'A block level 4'. A day rate of $55 per hour was specified. The relevant work commenced on that day and was substantially completed on Friday 30 January 2004. Lanskey's site foreman for Blocks A and B, Mr Andrew Green, recorded in his site diary for 30 January 2004 that Pro Finish Interiors had 5 men on site who 'Completed A4 + Hall'. On that day Pro Finish Interiors issued a tax invoice to Lanskey for the work carried out in the period 24 January 2004 to 30 January 2004 describing the work the subject of that invoice as: 'For the supply of tradesmen labour and materials required to carry out plasterboard defect repair works to PROJECT*** Northgate Apartments Block A Level 4 Fairy Meadow' The invoice proceeded to list the names of the tradesmen who had performed work together with the number of hours worked with extensions, calculated by reference to the charge out rate of $55 per hour, to which GST was added. No charge was imposed for the work of Pro Finish Interiors' site foreman, Glenn Suter. In respect of the other workers charges were imposed for the work of Barry Sindel - 24 hours, Norm Philipp - 30 hours, Norman Philipp [Mr Norm Philipp's son] - 32 hours, Paul Philipp [Mr Norm Philipp's brother, Reinhard Philipp also known as 'Paul'] - 30 hours, Anthony Summer (sic) [Anthony Summers] - 30 hours and Jimmy Gontas [Dimitrios Gontas] - 16 hours. Each of the men, whose time was charged out by Pro Finish Interiors at $55 per hour plus GST, charged Pro Finish Interiors $35 per hour plus GST for their services. 10 Notwithstanding the apparent completion of Pro Finish Interiors' work on 30 January 2004, Mr Anthony Summers returned to carry out further work for Pro Finish Interiors at the Fairy Meadow site on Thursday 5 February 2004 and Friday 6 February 2004. 11 After Pro Finish Interiors finally completed its plastering work on the Northgate Apartments building, it left the Fairy Meadow site. However, a number of its men returned on Wednesday 18 February 2004 to carry out work on Block D after Innovation Interiors, which had the contract for that Block, sought to engage extra gyprock plasterers to enable the work on that Block to be carried out more expeditiously. 12 In relation to the Wollongong site Pro Finish Interiors was awarded the job of carrying out the plastering work for Hansen Yuncken subject to certain matters being resolved (which, in the result, were never satisfactorily resolved). On 5 February 2004 Pro Finish Interiors had submitted a quotation to Hansen Yuncken for 'Plasterboard Fit-out works to be carried out to the above-mentioned project [THE PAVILIONS, CITY BEACH STAGE 2- WOLLONGONG]. As per plans & specifications supplied'. Under the heading 'Lump Sum Tender Price' the quotation recorded a 'TOTAL PRICE' of $1,031,236.50 which with GST produced a 'TOTAL PRICE INCLUDING GST' of $1,134,360.15. Part of the price was allocated to 'Linings and Partition Works' and the balance to 'Ceilings and Partition Works'. The quotation was accompanied by a priced bill of quantities for the works. 13 On Monday 9 February 2004 Mr Repas of Pro Finish Interiors met with Mr Michael McEwan, Hansen Yuncken's Project Manager for the Pavilions project to consider Pro Finish Interiors' quotation. Mr McEwan produced a 12 page set of minutes on a standard Hansen Yuncken form headed 'Trade Contractor Pre-Award/Induction Meeting'. Those minutes included the words 'THESE MINUTES HAVE BEEN PREPARED IN CONSULTATION AND ARE AGREED AND ACCEPTED FOR IMPLEMENTATION BY BOTH PARTIES'. The minutes were signed for the 'Trade Contractor' [Pro Finish Interiors] by Mr Repas and for Hansen Yuncken by Mr McEwan. Mr McEwan's evidence, which I accept in this regard, was as follows: 'Q Was any arrangement come to between yourself and Mr Repas in that meeting? A At the end of that meeting we did agree to a contract value conditional upon a few requirements being met. Q What was the contract value? A It was $1 million. Q What were the conditional requirements that you discussed? A Fundamentally the quotation was referencing a bill of quantities which we don't particularly like. It represents a risk to the builder so I asked for him to confirm his price based on the drawings only and that the bill of quantities was issued for information only. That was the first condition and the others were that safe work method statements and safety plans were forwarded and also certificates of currency for public liability and workers' compensation.'