Appendix A to the Decision of the Tribunal in HB 17/08049 and HB 17 19441
WARNING
FOR THE PURPOSE OF THE HOME BUILDING ACT 1989
The Contract Sum or the amount to be paid by the Owner is not known as at the date of contract
The amount of money payable to the Builder by the Owner is dependent upon the costs incurred by or payable by the Builder in carrying out work under the Contract.
(Owner to Initial)
Any figure nominated or stated below is only an estimate and is provided specifically subject to the terms of Clause 30.
(Owner to Initial)
$443,179.00……
Estimated Cost of Works and Fees (incl of GST) pursuant to Schedule 1 Parts A and B
The amount to be paid by the Owner is and will be determined by reference to the contract and the work done by the Builder. This will be influenced by and subject to adjustment by reason of such things as:
Discrepancy in Drawings and Specification; Refer to Clause 4.
Availability of Materials, Refer to Clause 9.
Delays and Extensions of time; Refer to Schedule 1 Part B (a)(iii) and Clause 11.
Compliance with Requirements of Local and Other Authorities; Refer to Clause 12.
Site Investigations, Refer to Clause 13.
Variations to the works; Refer to Clause 14.
Insurance responsibilities, Refer to Clause 16.
Interest on Late Payments, Refer to Clauses 17(g) and 21(c).
Impact of GST, Refer to Schedule 1, Part C and Clause 18.
Suspension of works; Refer to Clause 19.
Costs of the works as set out in the Contract; Refer to Schedule 1.
Payment of Costs and/or Fees payable to the Builder; Refer to Schedule 1 and Clause 17.
The work actually done being different to the work contemplated at the time of signing the contract. For example cost differences arising from details provided or choices made after the contract is signed.
Correction of Defects to work, other than new work undertaken wholly by the Builder. The Builder is to correct defects to its work at its own cost. Refer to Clauses 20 and 22.
This is page 1 of the contract, it specifically forms part of the contract document.
Owner ………..………..Builder……………...
IT IS AGREED THAT:
Please note that this part is to be manually completed by hand when contract is printed
(1) The Builder will subject to the contract terms and conditions, for the cost of the works (see Schedule 1, Part A) plus the fees payable under the contract (see Schedule 1, Part B), properly treated for GST complete the works shown upon the Drawings and described in the Specification. The works may be adjusted under the contract.
(2) The Owner will pay to the Builder the cost of the works plus the fee payable under the contract and the GST consequences of the work, at the times and in the manner required by the contract.
(3) (i) The Owner acknowledges and understands that the total cost of the works, including the fee payable to the Builder and the GST payable on the works is not known or ascertainable as at the date of this contract.
(ii) The Owner acknowledges and understands that the work done and completed and the materials used directly affect the question of costs payable by the Owner.
(iii) The Owner has read and understood the warning as to Cost Plus Contracts, which appears at the front of this document.
(iv) The Owner is liable to pay for the proper consequences of the tax commonly known as the GST referable to the work carried out by the Builder under this contract.
The parties sign below, this twenty fourth day of March 2016 to confirm their acceptance of this agreement.
SIGNED BY THE OWNER(S):…………………(sgn)
SIGNED BY THE BUILDER:…………………...(sgn)
SCHEDULE 1
[refer Clause 17 of the Contract]
PART A - Cost of Works which are Payable by the Owner or at the direction of the Builder
The Cost of Works which are payable by the Owner include:
(a) Wages and other entitlements payable to the Builder's employees or payable by reason of such employment relevant to the works. For example - wage, superannuation (Builder's workers compensation insurance, long service leave, redundancy and any other statutory or industrial entitlement,. See Schedule 2 Item (a) for specific agree rates for some employees.
(b) Costs for the individual Builder or Builder's director (or that of site supervisor) carrying out work , including administrative work, under the contract at the rate specified, being $80.00 per hour. If no rate is specified the rate to be relied upon will be that detailed in the most current Master Builder Association of NSW charge out schedule for the classification of carpenter unless otherwise agreed.
(c) The cost of having a service provided or a task done in order to have the works carried out, monitored, reviewed, certified and or approved. For example - surveyor's fees, engineer's fees, council fees, insurance cost or any other cost, fee expense paid or payable because of the work.
(d) The cost of all work carried out by trade contractors engaged by the Builder to carry out work at the work site or in relation to the works. This cost is conclusively evidenced by an invoice or statement of costs from the trade contractor.
(e) Cost of all goods and materials ordered and/or paid for by the Builder necessary to carry out the works.
(f) The cost of hiring equipment necessary to enable the Builder to carry out the works.
(g) The cost as nominated at Schedule 2(b), for the use of the plant and equipment which is already owned by the Builder or which is acquired by the Builder to carry out work.
(h) The cost of correcting, modifying or changing work already completed, which is changed by reason of a variation by the Owner, or which is defective for reasons other than due to materials provided by the Builder or the workmanship of the Builder.
(i) The cost of complying with any site specific issues as to safety, pollution and or water disposal, as directed by a relevant Authority or the Owner or the Owner's agents.
(j) Any other cost or expense which the Builder is liable for and/or incurs by reason of the Builder carrying out work pursuant to this contract including but not limited to, insurance costs and materials owned by the Builder.
PART B - Fees
[Choose the appropriate alternative for sub paragraph (a)]
(a) COST OF WORKS PLUS PERCENTAGE BASIS - (Alternative 1)
The Owner will pay to the Builder the Cost of Works as determined pursuant to Schedule 1 Part A, together with an additional fee equal to 10% of the Cost of Works and those items referred to in Sub-Clause 17(c)(ii). This fee is to be applied to a sum covering the Cost of Works which is determined on a GST exclusive basis. See also Clause 14(a) which may become applicable.
………………
PART D - Budget Report to be Provided
Pursuant to Clause 1(e) and (f) of the Contract the Builder is to provide a budget report. The budget report should be provided on the:
(i) 1 day of the calendar month; or
(ii) when requested by the Owner but not more than once per fortnight / month.
Please refer to Clause 1(e) and (f) of the contract.
Note: this is to make the parties aware of the impact that:
(i) the work done;
(ii) choices made; and
(iii) things discovered or addressed during the construction works
have on the amount to be paid by the Owner.
See also Clause 2A which requires the parties to meet when a conflict between the cost of the work (being the work done plus the work still to be done) and the capacity to pay arises or becomes apparent.
Conditions of Contract
1. Responsibilities of Builder and Results of Construction
(a) the Builder will, subject to these Conditions and the contract work details in Schedule 3, execute and complete the works required by the contract.
(b) Statutory Warranties for Residential Building Work Pursuant to s18B of the Home Building Act 1989 (the "Act") the Builder warrants that:-
Plans and Specifications
(c) (i) All plans and specifications for work to be done under this Contract, including
any variations to those plans and specifications, are taken to form part of this Contract.
(ii) Any agreement to vary this Contract, or to vary the plans and specifications for work to be done under this Contract, must be in writing signed by or on behalf of each party to this Contract.
(iii) This clause only applies to a contract to which section 7AA (Consumer Information) of the Home Building Act 1989 applies.
Budget Reports to be Provided
(e) The Builder will regularly provide to the Owner a written report on the cost of the works. This will be known as the budget report. If no specific period is agreed by the parties then a budget report will be done once per calendar month. See Schedule 1 Part D where a date for providing the Budget report can be agreed. The budget report is to be provided no later than five (5) days after this date.
(f) The budget report will include:
(i) details of the work done, costs known and moneys paid or payable as at the date identified in the budget report
(ii) a summary of work being performed and still to be performed;
(iii) details of work about which the Owner needs to provide instructions in order to allow the works to proceed; and
(iv) a revised estimated total cost of works.
The estimate above will be based on the Builder's knowledge at the time the budget report is done. The Builder is to use reasonable care in preparing the budget report. However the revised estimated total cost of works provided in the budget report is not a lump sum or guaranteed amount and is subject to the impact of the costs and the fees payable or incurred under the contract. Refer to Clause 30 also.
2. Owner's Responsibilities Concerning the Works - Pre Construction & During Construction
The Owner must …
(c) make payment as required by the contract within the period required by the contract. This includes directing any lending Authority to make payment direct to the Builder.
(d) provide written instructions to the Builder, where required, in a timely and proper manner so as to avoid delay to the works. This specifically relates to variations, directions and instructions in relation to work under the contract.
Owner's Duty to provide full terms of approval to Builder
(g)
(i) ensure that the Builder receives all terms and conditions of any approval by an Authority which affects or is relevant to the works. This should be done prior to signing the contract. If not it may cause the amount money to be paid by the Owner to change.
(ii) if the Drawings and Specification are lodged by the Builder this duty will bemet only if the Builder collects the approval documents from the Authority.
2A. Joint Responsibilities of the Builder and Owner
The Parties acknowledge the fact that:
(i) the amount payable by the Owner under this contract is not as at the date of the contract known.
(ii) the total amount payable under the contract will not necessarily be ascertainable during the course of the contract; and
(iii) the amount to be paid by the Owner is the result of the costs incurred by the Builder, the Builder's fee or return and the impact of the GST on the work done.
The parties agree in order to manage this situation that:
(a) they will conduct regular meetings in order to:
(i) review the work done and costs incurred;
(ii) review the work to be done and the costs thought to be payable for such work; and
(iii) make decisions and choices regarding work under the contract so that the work to be paid for by the Owner is consistent with the Owner's capacity to pay.
(b) they will, in the event that there is a conflict between the costs of the work as set out in the budget report and the Owner capacity to pay, adjust the work to be done so that the conflict is eliminated and as such the work to be done is worn for which the Owner has the capacity to pay.
The adjustment to the work is to be recorded in writing and signed by both parties and treated as a variation under Clause 14.
(c) they will act co-operatively and in a manner which progresses the works.
(d) either party may require a meeting to be held within five (5) days of a written request for a meeting. Both parties must attend such a meeting. The party calling the meeting will identify issues to be covered at the meeting.
The Builder will provide a report on the matters raised at the meeting within a reasonable time but no later than ten (10) business days after the meeting.
(e) for the purpose of improved certainty the scope of work to be completed by the Builder is limited to that work for which the (b)Schedule 3 requires that the party responsible for having the drawings and or specification prepared be identified. If that detail is left blank it will be concluded that the Owner has made or can make and does make payment. Consequently any work which is not able to be paid for by the Owner will be eliminated from the work to be carried out by the Builder.
3. Contract Documentation
(a) the party that provides the drawings and/or specification warrants their accuracy and correctness including compliance with Clause 1(c) as applicable. As of the date of the contract, the documents detailing the work to be carried out by the Builder are listed in Schedule 3.
Contract Represents Entire Agreement.
(d) Apart from any terms implied by Statute, the whole of the terms, conditions and warranties of this Contract are set out in the Contract, drawings and specification (as set out in Schedule 3) and will not and are not in any way varied or affected by reference to any prior negotiations, stipulations or agreement, whether written or verbal.
4. Discrepancies and Ambiguities
(a) Should there be any discrepancy or ambiguity in the contract documents the following order of precedence is to be employed to resolve the same:
(i) this Agreement and Conditions including any Special Conditions;
(ii) drawings to a larger scale;
(iii) other drawings;
(iv) the specification
(b) The Builder must notify the Owner in writing of any discrepancy or ambiguity in the contract documents and request instructions on how to proceed. This should be done as soon as practicable to allow the Owner to respond.
(c) The Owner must give written instructions within five (5) days of receiving the above notice. If the Owner does not then the Builder may proceed with the work on the basis of the interpretation in accordance with Sub-Clause (a) above.
11. Delays and Extensions of Time
(a) Should the progress of the works be delayed by any of the following causes or conditions resulting from them:
(i) variations;
(ii) suspension of the works under Clause 19;
….
(v) any act, default or omission on the part of the Owner including, but not limited to, providing instructions, making payment or doing a thing necessary to allow the works to proceed including signing instructions concerning variations;
…..
(vii) an instruction by the Owner to stop the works;
…..
(x) inclement weather or the affect of weather on site access or site safety;
…..
then in any such case the builder must receive a fair and reasonable extension of time to the Construction Period.
(b) (i) the Builder must notify the Owner in writing od the matters which cause delay within a reasonable time of becoming aware
…..
(d) delay in notifying or failure to notify to Owner of delay …..will not of itself prohibit an extension of time….provided the cause is shown to cause delay to the work
…..
(f) If delay results from clause 11(a) (i), (ii), (iv) or (vii) then the Cost of Works is ….adjusted to include an amount calculated to cover the cost or expense of delay .amount
13. The Site is Presumed Suitable for and able to Support the Works
(a) The Owner warrants that the site and or any existing structure will support and allow the works to be carried out. This is the basis upon which the Builder has agreed to do the work.
14. Variations - Changes to Scope of Works Post Contract Date
(a) The works as initially understood at the time of contracting may be varied by:
(i) the execution of additional work;
(ii) changes in the character or quality of any material or work;
(iii) change in the levels, lines, positions or dimensions of any part of the works.
(iv) deletions or omission from the works.
For the sake of clarity a variation is established by:
written instructions from the Owner or the Owner's representative; and or
the supply to the Builder of post contract details such as drawings; and or
the discovery of an otherwise unknown or latent condition,
which alters the work done, the work to be done or requires adjustments to an existing situation or the work which was otherwise expected to be done.
Accordingly a variation may for example result from such things as a request from the Owner, a choice made by the Owner, dealing with latent conditions and complying with the requirements of an Authority.
(b) The Builder is not obliged to vary the Contract or carry out any extra work unless he consents, which consent is not to be unreasonably withheld.
(c) (i) If the Builder agrees to undertake a variation by the Owner, the variation isto be detailed in writing and signed by the Owner (or the Owner's agent) and the Builder. Documents detailing the variation, including as appropriate, amended drawings or specifications, become contract documents.
(ii) The Builder may require, prior to the execution of any variation, that the Owner produce evidence, satisfactory to the Builder, of the Owner's capacity to pay for the variation.
(d) the cost of all work arising from any such variation is a cost of the works payable by the Owner and is to be valued and paid for as such.
17. Payment
(a) The Owner must pay to the Builder the Cost of Works as set out in Schedule 1 Part A; and
(i) the fee set out in Schedule 1 Part B;
(ii) the percentage referred to in Schedule 1 Part B based on:
(1) the Cost of Works as set out in Schedule 1 Part A;
(2) the cost of any goods and/or materials purchased by the Owner if those goods and/or materials are to be installed by the Builder; and
(3) the cost of any subcontractor engaged by the Owner if the Builder is requested and/or agrees to supervise that subcontractor.
For the purposes of (2) and (3) above, the Owner is to supply the Builder with copies of all invoices for that subcontractor and/or supplier.
(iii) GST, Refer to Clause 18.
(b) The above amounts must be paid to the Builder in accordance with the timetable set out in Schedule 1 Part B.
(c) A claim for payment by the Builder is to identify -
(i) the period during which work was carried out and the work for which payment is required;
(ii) the Cost of Works for works performed in this period;
(iii) a brief description of any variations relative to the initial scope of work under the contract;
(iv) the fees payable under Schedule 1 Part B; and
(v) GST.
The Cost of Works determined by the above is to be a figure initially exclusive of any GST component. The amount determined by the above processes will be subject to GST pursuant to Clause 18. (This is to avoid compounding the GST or to ensure the GST is only charged once on the aspects or components used to establish the cost of the work and the Builder's fee).
(d) All claims for payment of Costs of Works should be evidenced as far as possible by supporting copies of documents such as clean copies of invoices, receipts and account documents.
(e) Payment is to be made within the period stated in Schedule 1 Part B point (c). If no period is stated, then the payment must be made within five (5) days of the date the claim was submitted to the Owner.
(f) Should the Builder not receive from the Owner payment of or any part of a payment by the due date, the Builder will be entitled to interest on the overdue amount at the rate specified at Schedule 2 point (e). The Builder may also suspend further work pursuant to Clause 19, if the Owner fails to pay for work under this contract.
19. Suspension of Work
(a) Should the Owner:-
i) fail to pay or cause to be paid any payment or any part thereof including an amount for GST within the time required by Schedule 1 Part B point (c);
ii) fail to confirm in writing instructions regarding an Owner requested variation or a required variation to the works;
iii) fail to provide written instructions in a manner and time so as to reasonably avoid delay to the progress of works;
iv) fail to comply with the requirements of Clause 2 (b);
v) cause independent sub-contractors to attend the site address without the Builder's consent;
THEN the Builder may, without prejudice to its right to determine this Contract, suspend the works.
Suspension pursuant to this clause will act as a bar to any claim for damages, compensation or offset by the Owner against the Builder which relates to the period of suspension or consequence of such suspension.
(b) The Builder is to give notice in writing of any suspension under this clause to the Owner.
(c) Should the Owner direct the Builder to not proceed with the works then, without prejudice to the Builder's right to terminate this Contract tor to claim delay costs pursuant to Clause 11(a), the Contract is automatically suspended.
26. Termination by the Owner
(a) The Builder is in default of this Contract if the Builder:
(i) commits an act of insolvency; or
(ii) fails to proceed with the works with due diligence or in a competent manner with regard to the circumstances of the contract works;
(iii) without reasonable cause he wrongfully suspends the carrying out of the works before Practical Completion; or
(iv) refused or persistently neglects -
(a) to comply with the requirements of Clause 12 of these conditions; or
(b) to remove or remedy defective work or improper materials, so that by the refusal or persistent neglect the works are materially affected; or
(v) states that is unable or unwilling to complete the works or abandons the Contract;
AND if,
In the case of any default that is capable of remedy, the default continues for twenty five (25) days after notice in writing has been given to the Builder specifying the default and stating the Owner's intention of terminating this Contract, THEN the Owner may, without prejudice to any other rights or remedies, by notice served as allowed by Clause 29 terminate this Contract.
(b) The Owner may terminate this Contract in the circumstances provided by the general law however this does not prevent the Owner and Builder from agreeing to additional circumstances in which the contract may be terminated.
(c) In the event that the Owner terminates this Contract in accordance with Sub-Clause 26(a) of this clause, the Owner may engage another Builder to carry out the works.
30. Estimate for Owner
If an estimation of the total amount that will become payable by the Owner under this Contract is or has been made either before or after the date of the Contract THEN such estimation will be or will have been made on the basis of the information, as to the detailed and complete nature and extent of the works, then available to the Builder. However the estimation will not be of any contractual significance whatever between the parties or deemed to be a representation innocent or otherwise as to the amount or approximate amount that will become payable by the Owner. This clause also applies to the budget report referred to in Clause 1(e).
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
Registrar
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated: 05 September 2018