Green v Modern Roof Restorations
[2021] NSWCATCD 101
At a glance
Source factsCourt
NCAT Consumer and Commercial
Decision date
2021-08-18
Source
Original judgment source is linked above.
Judgment (9 paragraphs)
REASONS FOR DECISION
- This is a claim a home building claim by the applicant that the work was not completed with due care and skill pursuant to Section 18B of the Home Building Act 1989 (NSW). The applicant seeks the amount of $26,821.96 in compensation for damaged and inadequate gutters and to replace the damaged and irreparable roof, removal and return of the solar panels to accommodate a new roof.
Evidence of the applicant
- The applicant contracted with the respondent on 31 August 2020. The work commenced on 8 September 2020 and was to take a maximum of 2 days, however, the work was not completed satisfactorily by a sub-contractor of the respondent, Scott Fagerlund, the issues with the gutters were being addressed when work commenced on the roof restoration.
- The applicant claim to the Tribunal are that the gutters are inadequate, all need to be replaced by another contractor, the gutters are not functional as they have been over-sprayed with roof restoration paint.
- On 13 October 2020 work commenced on the roof, including replacement of broken tiles, and repointing cleaning, and preparation prior to painting, however, the sub-contractor delayed the completion due to personal reasons. On 23 October 2020 the applicant was advised by Chris Rowe, that the work was completed and that the final payment was due. The applicant felt pressure my Mr Rowe to pay the final instalment however, she did not believe that all the coats of paint would be dry by this time. On 29 October 2020 after her return from Grafton she went to an elevated area of her backyard and could see that not all the work had been completed. She could see many broken tiles. She contacted the respondent received a scathing response from Mr Rowe, the applicant declined to pay the remaining payment as she did not believe that the work had been completed. It was suggested to pay the final instalment and use the warranty to rectify the issues.