(b) second, the respondents state that, in effect, when the council, as consent authority, and later upon its appointment as principal certifying authority for the subdivision work, issued the construction certificate and the subdivision certificate, it represented to the respondents that the road had been built in conformity with the consent and that the conditions of the consent, including condition 9, had been complied with.
13 The council cannot now assert a breach of the consent by reason of any stated failure to satisfactorily complete the road works. To the extent that it seeks to do so, it is estopped.
14 The respondents in their cross claim seek a declaration that the council had breached ss 109E(3)(e) and 109J(1)(c) of the EPAA to the extent that the subdivision was not carried out in accordance with the consent. Further, if the subdivision was not carried out in accordance with the consent as alleged, then the respondents seek an order that they not be required to submit to any relief, or comply with any order of the Court, unless and until the council pays or contributes towards the cost of it having to do so.
Proposed Amended Points of Defence and Cross Claim
15 The proposed amended pleadings by the respondents did not seek to amplify or reduce the issues raised in the currently filed pleadings in any material way. Rather, the amendments sought to respond to defects previously identified by the council. In particular, the pleaded estoppel and the asserted breaches of ss 109E(3)(e) and 109J(1)(c) of the EPAA were pleaded with greater precision.
Statutory Framework
16 As at the date which the subdivision was permitted, ss 109E(3)(e) and 109J(1)(c) of the EPAA stated as follows:
109E Principal certifying authorities
(3) A principal certifying authority for building work or subdivision work to be carried out on a site is required to be satisfied:
(e) that any preconditions required by a development consent or complying development certificate to be met for the work before the issue of an occupation certificate or subdivision certificate have been met, before the principal certifying authority issues the occupation certificate or subdivision certificate.
109J Restriction on issue of subdivision certificates
(1) A subdivision certificate must not be issued for a subdivision unless the certifying authority is satisfied of each of the following:
(c) in the case of subdivision for which a development consent has been granted, that the applicant has complied with all conditions of the consent that, by its terms, are required to be complied with before a subdivision certificate may be issued in relation to the plan of subdivision,
17 Rule 14.28(1) of the UCPR states as follows:
14.28 Circumstances in which court may strike out pleadings
(1) The court may at any stage of the proceedings order that the whole or any part of a pleading be struck out if the pleading:
(a) discloses no reasonable cause of action or defence or other case appropriate to the nature of the pleading, or
(b) has a tendency to cause prejudice, embarrassment or delay in the proceedings, or
(c) is otherwise an abuse of the process of the court.
18 Rule 14.1 of the UCPR states, "this Part applies to proceedings commenced by statement of claim and to proceedings in which a statement of claim has been filed" (emphasis added).
19 Schedule 1 of the UCPR states that proceedings in Class 4 of this Court's jurisdiction incorporate by way of practice and procedure all of the provisions of the Civil Procedure Act 2005 ("the CPA") and the UCPR. Having said this, Sch 2 of the UCPR effectively states that the local rules of this Court prevail over those enacted in the UCPR.
20 The Land and Environment Court Rules 1996 were repealed by the passage of the Land and Environment Court Rules 2007 ("the 2007 Rules"). The 2007 Rules were enacted following the enactment of the UCPR to reflect the adoption in this Court of those harmonised civil procedure rules.
21 Rule 4.1 of the 2007 Rules states "this Part applies to proceedings in Class 4 of the Court's jurisdiction."
22 The Note to this rule provides as follows:
Note : Proceedings to which this Part applies are subject to the provisions of the Civil Procedure Act 2005 and the Uniform Civil Procedure Rules 2005 . That Act and those rules refer to an applicant under these rules as a plaintiff and a respondent under these rules as a defendant. Under Part 4 of the Uniform Civil Procedure Rules 2005 , proceedings to which this Part applies are to be commenced by statement of claim or by summons.
23 The last sentence of the Note appears to suggest that proceedings to which Pt 4 of the 2007 Rules apply may be commenced only by statement of claim or by summons. However, proceedings in Class 4 of the Court's jurisdiction are commenced not by statement of claim but are initiated by points of claim, together with a summons. The significance of this will be explained below.
Defects in the Proposed Amended Pleadings
24 The council complained about four defects in the proposed amended points of defence and cross claim that sought to be filed by the respondents. Some, but not all, of these defects currently exist in the points of defence and cross claim as filed.