THURSDAY 4 JUNE 2009
GREAT WALL RESOURCES PTY LTD v O'SULLIVAN & ANOR
Judgment
1 GILES JA: I agree with Macfarlan JA.
2 IPP JA: I agree with Macfarlan JA.
3 MACFARLAN JA: By a contract of sale dated 13 June 2003, the appellant agreed to sell to the respondents certain land situated at Yallah on the South Coast of New South Wales. The land was part of a larger parcel of land being subdivided by the appellant. By the contract, the appellant warranted that a right of way affecting the land would be extinguished.
4 In proceedings between the appellant and the owners of the land entitled to the benefit of the right of way, Young CJ in Eq made orders on 21 November 2005 which included the following:
"1. That immediately upon the Defendant/Cross Claimant Registering an easement, in favour of the Plaintiff/Cross Defendant, in the form annexed and marked 'A' to the Third Further Amended Cross Claim, over the "Property" (being Lot 10 in Deposited Plan 262279) then the easement presently recorded as a notification on the title of the Property (by reason of dealing number A769744) be extinguished.
…
6. Should the easement referred to in order 1 herein not be registered by the Defendant in favour of the Plaintiff by 24 December, 2005 then either party may apply to this Court to vary these orders forthwith."
5 In the events which occurred, 29 December 2005 became the contractually agreed date for settlement. After the appellant's failure to complete the contract of sale on that day, the respondents commenced the present proceedings.
6 On 24 November 2006, Palmer J made an order in the proceedings that the contract be specifically performed and made a declaration that in failing to extinguish the right of way referred to above, the appellant had breached the contract and was liable to pay damages in respect of that breach to the respondents. He also made the following orders:
"4. An order that an inquiry be held as to the amount of damages which the Plaintiffs have sustained by reason of the Defendant's refusal to perform the said contract.
…
6. An order that an inquiry be held as to the amount of damages which the Plaintiffs have sustained by reason of the Defendant's said breach of the said contract."
7 There is no evidence to suggest that by the time of the hearing before Palmer J (or indeed until recently) the appellant took any steps to extinguish the right of way in the manner contemplated by the orders of Young CJ in Eq. The appellant's position in fact appears to have been that it was unable, or at least unwilling, to remove the right of way because by letter of 24 March 2006 written on its behalf it asserted that title subject to the right of way was the only title it was "ready, willing and able" to transfer to the respondents. The proceedings before Palmer J appeared to proceed upon the basis that this continued to be the appellant's position.
8 In pursuance of the orders made by Palmer J, McLaughlin AsJ delivered a judgment on 19 May 2008 assessing the damages to which the respondents were entitled. The principal amount was $89,487.54 which became, when interest was added, $101,914.74. The present appeal is brought from that judgment. However, not all of the principal amount is the subject of challenge. The items challenged are $45,000, as to a difference in value of the subject land, and $37,730, as to additional building costs. Even with interest added, the amount in issue on the appeal is less than $100,000. As a result, leave to appeal is required under s 101(2)(r) Supreme Court Act 1970.
9 As leave has not been obtained, the purported appeal is incompetent and should be struck out. I add that the Notice of Appeal and Amended Notice of Appeal which were filed challenged the judgment of McLaughlin AsJ in general terms. The lack of specificity rendered those documents not in conformity with the Rules. The limited nature of the appellant's challenges became evident upon the filing of its written submissions.
10 The appellant did not seek leave to appeal until the appeal came on for hearing, despite the fact that the respondents filed a Notice of Motion on 8 September 2008 seeking to strike out the appeal as incompetent for want of leave.
11 The Court nevertheless heard full argument on the application for leave to appeal, on the appeal and on a Notice of Motion that was filed in the Appeal on 6 May 2009 by the appellant for leave to adduce fresh evidence.
12 It is convenient first to refer to the appellant's challenge in relation to the award of $37,330 plus interest in respect of additional building costs. After an initial assertion that there had been an arithmetical error was withdrawn, the complaint came down to one that the award was not supported by the two building quotations upon which it was based. One was dated 18 November 2006 and the other dated 19 April 2007. The contract was completed on 19 December 2006. It was submitted that the increase in costs could not be regarded as a loss suffered by the respondents resulting from the appellant failing to complete the contract.
13 I do not accept this submission. The delay in settlement was approximately 12 months (29 December 2005 to 19 December 2006). It was not unreasonable to take April 2007 as a date when the respondents would first have been in a position to build upon the land, being a few months after completion. Until completion, they could not have been certain of their control of the land. The most appropriate date to take for a comparison with April 2007 building costs would probably have been about April 2006, being about the same period after the date upon which the contract should have been settled. The fact that the respondents' evidence was instead directed to November 2006 may well have understated their loss but nevertheless was sufficient to show that there was an amount ($37,750) by which their building costs had risen as between a point of time at which they would have been able to proceed to build if the appellant had not been in breach and the point of time at which they were reasonably able to proceed to build after completion of the contract.
14 I turn then to the other challenge made to the award of damages. This item of $45,000 plus interest represented the difference between the value of the land if there had been no right of way on the title and the value of the land with the right of way.
15 At the hearing before McLaughlin AsJ, the appellant sought to read the affidavit of Adrian Daley of 30 April 2008. This referred to the orders of Young CJ in Eq and the fact (as it was thought to be) that the consent of a Mr and Mrs Le Serve was required in order to have the Land Titles Office effect the extinguishment of the right of way. The affidavit annexed a letter to the solicitors of Mr and Mrs Le Serve (who happened to be solicitors who also acted for the respondents) dated 15 April 2008, that is, a year earlier seeking the consent of Mr and Mrs Le Serve. The affidavit said that that consent to date "has not been forthcoming". It did not contain any information as to the likelihood of consent being forthcoming in the future. His Honour rejected the material parts of the affidavit saying:
"I don't consider that this matter is relevant to the present inquiry that has been committed to me".
16 Counsel for the appellant then sought an adjournment to enable the appellant to take steps to register the extinguishment. A letter was handed to his Honour in the course of the application and subsequently returned by his Honour to the parties. As the parties were not able on the appeal to identify the letter with any certainty, the contents of the letter are not known to the Court. His Honour refused the application for adjournment. No reasons are recorded. The application apparently mirrored an application to vacate the hearing date made the previous week to Young CJ in Eq. The application had been refused by his Honour. We were not informed of his reasons.
17 In the course of the cross-examination of the land valuer called by the respondents, the following exchange occurred:
"Q. In determining the valuation of the land affected by the easement, did you assume the easement would operate in future indefinitely? Was that one of your considerations?
A. Yes.
Q. I don't want you to answer this question if there is an objection and I don't wish to be discourteous in asking this question. If you had known that there had been an order of the Supreme Court in 2003 which ordered that in certain circumstances this easement affected lot 110 could be extinguished, would that be a relevant consideration in the carrying out of your valuation?
OBJECTION. REJECTED."