Graham Evans Pty Ltd v Stencraft Pty Ltd
[1999] FCA 290
At a glance
Source factsCourt
Federal Court of Australia
Decision date
1999-03-25
Before
Lockhart J, Spender J
Source
Original judgment source is linked above.
Judgment (101 paragraphs)
REASONS FOR JUDGMENT 1 This is an application filed on 6 February 1995 by Graham Evans Pty Limited ('GE') against the respondent, Stencraft Pty Limited ('Stencraft') claiming, pursuant to s 82 of the Trade Practices Act 1974, damages, interest and costs. On 24 March 1995, Lockhart J ordered by consent that the proceedings be transferred to the Queensland Division of the Federal Court. 2 The central question on the application is whether there was a contract entered into by GE and Stencraft for GE to build a major residential construction project in Brisbane known as the "Dockside Stage III" project and if so, what was its content. GE by its statement of claim filed 6 February 1995 and amended statement of claim filed 17 June 1996 alleges that a concluded agreement was reached on 12 May 1994 that GE was to build the Dockside project for Stencraft at a contract price of $28.261 million. By its defence filed 23 June 1995, Stencraft denies that any concluded agreement was reached and alleges that its acceptance of GE's contract price was subject to the acceptance by GE of the form of contract and deed of assumption. 3 If there was a contract as alleged by GE, a further question is what damages ought be awarded for its repudiation by Stencraft. 4 As will be seen, much ultimately turns in these proceedings on issues of fact and the proper inferences to be drawn from the facts as found. It has been necessary to have close regard to the context in which the parties have conducted themselves at the relative times and to the chronology of certain critical events. Background and Facts 5 Negotiations between the parties leading to the tender by GE for the Dockside project began on 25 March 1994 between Mr Ian Harrington, General Manager, Queensland of GE, Mr Murray Osbaldiston, GE's Estimating Manager, Mr Steve Girdis, a director of Stencraft and Mr Fred Brands, the General Manager of F A Pidgeon and Son Pty Ltd ('Pidgeon'), a shareholder of Stencraft. GE was at this time nearing completion of construction of a project known as "Goodwin Towers". This had been a successful project, and had involved particular staff of GE referred to by the parties in these proceedings as the "A" team. Following that meeting and on the same day, Mr Brands for Stencraft forwarded a letter to Mr Osbaldiston enclosing documents relating to the construction of the Dockside project and inviting GE to tender for the project, such tender to be submitted by 12 noon, Friday, 22 April 1994. There then followed a period of approximately one month from late March to early May 1994 in which the parties exchanged extensive correspondence relating to the technical details of the Dockside project, including specification details, finishes schedules and architects' drawings of the project. 6 As a result of the detailed information provided by Stencraft, GE delivered its first tender in the sum of $29,196,873 by letter to Stencraft dated 22 April 1994. 7 Mr Harrington, Mr Osbaldiston, Mr Girdis and Mr Brands met at the offices of Pidgeon on 26 April 1994 to discuss technical matters and the scope of work, and the form of the contract to be signed should GE ultimately be successful in their tender. In particular, Mr Harrington for GE deposes in his affidavit sworn 9 November 1995 to a conversation that took place between himself and Mr Brands of Stencraft. He says that Mr Brands indicated that he was not familiar with the "JCCB" form of contract nominated in GE's tender and preferred to use "AS2124" (Australian Standard 2124) in substitution, to which Mr Harrington replied "We don't have a problem with that - we want to sort out the terms of payment and retention." Mr Brands in his affidavit sworn 12 March 1996 deposes to discussing a large number of matters relating to scope, including: "- formwork - waterproofing the basement - reinforcing - concrete - piling - joinery - carpet - tiles - kitchen benchtops - vanity benchtops - kitchen splashbacks - kitchen cupboards - art glass - entry decoration - granite in lobbies - skirtings - tiling in firestairs, anteroom and refuse room - ceiling in firestairs, refuse room and anteroom - cornices - tiling to firehose reel cupboards - access panels - skirting in laundry - laundry cupboards - tiling to balconies - Stair to car park - angle corner guards - grates to spoon drains - louvres - bin rooms to the villas - escape stairs - waterproofing system - kitchen entry doors - curtain pelmets - insulation - windows - handrails and balustrades - glass strength - landscaping - contract period - hoarding - boardwalk - hydraulics - lifts - electrics - fire services - security 8 Further correspondence, drawings and sketches followed the meeting on 26 April 1994. 9 By letter dated 29 April 1994 GE submitted a re-tender in the sum of $28,344,000.00. Their letter said: "Our tender is subject to the conditions and attachments of our original tender together with the attached Post-Tender Amendments." 10 On 6 May 1994 a further Re-Tender 2 for the Dockside Stage 3 project was sent by Mr Harrington to Mr Girdis. This was for a price of $28,434,439. The letter said: "Our tender is subject to the attached Post Tender Amendments No. 2 and the following Conditions and Attachments of our previous tender submissions.