Graham Evans Pty Ltd v Stencraft Pty Ltd
[1999] FCA 1670
At a glance
Source factsCourt
Federal Court of Australia
Decision date
1999-11-30
Before
Dowsett J, French J, Whitlam J, Dowsett JJ
Source
Original judgment source is linked above.
Judgment (70 paragraphs)
THE APPEAL 3 This is an appeal from a judgment dismissing a claim for damages for breach of contract. Other relief was claimed, but that is not presently relevant. The appellant is a building company. The respondent is a property developer. The appellant claims that the parties entered into a contract for the construction by the appellant of a block of home units on land owned by the respondent.
BACKGROUND 4 In the early part of 1994 the appellant was completing work on a building project described as "Goodwin Towers" which was in close proximity to land on the Brisbane river upon which the respondent proposed to erect a building unit complex described as "Dockside Stage III" or "Stradbroke Tower and Villas". The appellant believed that the performance by its key personnel on the Goodwin Towers project had acquired for it a particular reputation for competence in the eyes of potential customers. The appellant and its witnesses regularly referred to them as the "A Team". The respondent apparently also shared this view to some extent. At an early stage, Stephen Nicholas Girdis, a director of the respondent, made it clear that he wanted "your A Team" to build Dockside Stage III. At about the same time as the respondent was looking for an appropriate builder for that development, another developer (Seymour) was looking for a builder for a project known as "Admiralty Towers". Girdis knew that tenders for the Admiralty Towers project closed on 13 May (AB 131 ll 17-20). Presumably, the appellant also knew this. The appellant claims that because it reached a binding agreement with the respondent on 12 May, it submitted an uncompetitive tender for Admiralty Towers and did not win that project.