13 On 18 March 2009, Evewall's solicitors wrote to Golden Oceans' solicitors demanding payment of the balance of the contractual deposit of $174,000, the agreed consideration for the extension of the Notice to Complete in December of $44,000, and interest under the contract from 28 November to 27 February of $88,000 - a total of approximately $306,000 - and foreshadowing the commencement of proceedings if not paid.
14 Golden Oceans lodged a caveat in respect of the land, number AE571103Y, on 27 March 2009, claiming an interest as purchaser under the contract. A Lapsing Notice in respect of that caveat was served on 3 April 2009. On 24 April, the last day on which it could do so, Golden Oceans applied to the Court for an order extending the operation of that caveat. White J declined to make that order, but granted leave to Golden Oceans to lodge a further caveat in identical terms, upon an undertaking to withdraw it forthwith after 30 April unless the Court extended that period. Today Golden Oceans applies, in effect, for an extension of that period in order to permit the new caveat AE632239K to remain on title.
15 On an application of this kind the issues are whether there is a seriously arguable claim to a caveatable interest and, if so, where the balance of convenience and prejudice lies.
16 The present application really turns on whether there was (arguably) an agreement to extend the time for compliance with the Notice to Complete. That, in turn, depends on the conversations said to have taken place on 21 February 2009. While it appears - from the letter from Michael Flaherty of 25 February 2009 - that this conversation is likely to be in dispute, at this stage there is Mr Carroll's sworn evidence of it, and his evidence of a further conversation on 7 March which goes some way to explaining the otherwise apparent inconsistency of Mr Wallace's position, at least in the context of Mr Carroll's version. If that evidence were accepted and it cannot be said at this stage that it is impossible that it would be then that would prima facie establish an agreement to extend the time allowed by the Notice to Complete, and it would be contrary to that agreement for Evewall to have terminated on 27 February 2009.
17 It was argued that, even if accepted, the evidence could not establish such an agreement for want of consideration. That depends on the construction of the proposal to "increase the purchase price by $100,000 being interest plus a gratis payment to the total of $100,000". It is at least arguable that the "gratis payment" was additional to the $40,000 agreed to be paid in December. That being arguable, it remains sufficiently arguable for present purposes that there was an agreement for valuable consideration to extend time for compliance with the Notice to Complete. In circumstances where, if that view were ultimately to prevail, Evewall would then have wrongly purported to terminate on 27 February, questions pertaining to Golden Oceans' ability to complete on 10 April, or the circumstance that it did not tender payment on 10 April, would not detract from the existence of a sufficiently arguable case.