NSWNSWCATCD
Gassman v Peck
[2017] NSWCATCD 90
NCAT Consumer and Commercial|2017-02-17
View original sourceAt a glance
Source factsCourt
NCAT Consumer and Commercial
Decision date
2017-02-17
Source
Original judgment source is linked above.
Judgment (14 paragraphs)
[1]
The Application
- For ease of reference in these reasons the applicants shall be referred to as homeowners and the respondent as builder.
- On 9 May 2016, the homeowners made an application to renew proceedings HB 14/17549 in which orders had been made by consent on 11 December 2015. The orders required the builder to undertake and complete agreed works in a proper and workmanlike manner on or before 24 March 2016. The Tribunal has decided in this matter to make an order for money for rectification of the defective works.
[2]
Background
- The homeowners made application HB 14/17549 on 1 April 2014. The application related to defective works which the homeowners allege the builder was liable for. The respondent had initially been named as 'Impeckable Constructions Pty Limited' in that application. That was the name of the builder as it appeared on the contract. The respondents name has subsequently been amended to Nathan Peck. Both parties have proceeded on the basis that was the builder with whom the homeowners contracted.
- Both parties engaged experts. Mr Connor provided a report and gave evidence for the homeowners and Mr Moore appeared on behalf of the builder. The experts agreed that the works the subject of the Tribunal order on 11 December 2015 were not complete. They experts disagree in relation to quantum and to liability. The builder also denies liability for not having complied with the work order. He alleges the homeowners and/or their experts have caused the delay.