Did the builder fail to complete the works the subject of the work order?
- Both Mr Gassman (one of the homeowners) and Mr Peck (the builder) gave statements and were cross examined at the hearing. The homeowners allege that the builder failed to complete the works within the time agreed in the orders.
- In his statement dated 14 February 2017 Mr Peck stated that when he agreed to the orders on 11 December 2015, he felt the time allowed to complete the works
was not sufficient due to co-ordination of all the "experts", Xmas closures, the amount of work and client's up and coming overseas trip that was for a period of a few months.
- He lists the chronology of the works completed and times that his workers were on site. Mr Peck relevantly states that:
I would like to note, that predominately the hold ups have been from the applicant's expert's and engineer's as the emails reflect. I would like to know, they are aware of the deadline and claim they want the work carried out, why are they making it more difficult to carry out the works, and make it impossible to meet the deadline. From my point of view, it would seem that they have intentionally tried to delay works to put me in a bad light for the next hearing.
….
As this document clearly points out, I have been in no way avoiding my obligations and instead have tried my utmost to co-ordinate and carry out what was required of me and I am still willing to return and complete the works but the client has now refused access, which makes it impossible for me to do so.
- The emails referred to by Mr Peck have been provided with his statement and he was cross examined in relation to them. The email dated 28 January 2016 from Mr Stuart Bullivant refers to a change of date for site meeting with Mr Broune who was the engineer for homeowners. It refers to confirmation of the new meeting time with Mr Broune, but it does not, as Mr Peck alleges, say that Mr Broune "couldn't make 28 January 2016."
- Mr Gassman refers to the scheduled hold point meeting for 28 January 2016 in his statement of 3 March 2017 at paragraphs 65 and 66. He states that he was advised by Mr Connor his building expert that on the morning of 28 January 2016, Mr Connor received a call from Mr Bullivant that the inspection has been cancelled. Mr Connor then contacted Mr Broune to advise him of the cancellation. Mr Gassman also states that Mr Broune had advised him that Mr Connor had rung him to cancel the meeting. Before the Tribunal was also an affidavit sworn by Mr Connor dated 12 July 2016 (who was also cross examined at hearing). At paragraph 6, Mr Connor stated that it had been the respondents engineering expert Mr Kevin Mayes who had not been available for the inspection.
- In his statement dated 3 March 2017, Mr Gassman states that at the Tribunal hearing on 11 December 2015 he had advised Mr Peck that he and his wife would be going on holidays for three months at the end of March 2016. He states that on that basis he had agreed not to include rectification of the bathroom ensuite in the agreement. He states that after the engineering meeting which took place on 10 March 2016 (his statement has 2015, but the Tribunal accepts that this is a typographical error, as the builder statement also refers to the meeting as happening on 10 March 2016) he did not hear again from the builder until 30 March 2016.
- Mr Peck states that on 23 March 2016 he followed up the matter and on 30 March 2016 he contacted Mr Gassman and was informed that he would not be allowed access while the homeowners were away overseas.
- The builder also refers in submissions to the complexity of rectifying the defective windows. The work orders made 11 December 2015 allow for hold point inspections to allow the experts building consultants and engineers to further confer on resolving the defective windows. The builder makes submissions that the method of rectification agreed by the experts in relation to the windows leaking was only communicated to him on 23 March 2016, the day prior to the work orders requiring completion.
- Having considered the evidence on this point the Tribunal does not find that the hold point inspection that was schedule for 28 January 2016 was postponed due to the unavailability of the applicant's engineer. Mr Bullivants email does not state, as Mr Peck alleges that the meeting was postponed due to the unavailability of Mr Broune. It only states that new dates have to be confirmed with Mr Broune for meeting. Similarly, the subsequent emails between various parties simply reveal what is ordinary in these circumstances, correspondence to facilitate a date that is suitable for all the parties to be in attendance for the hold point inspection. It is noted for instance that in an email from Nathan Peck himself dated 26 February 2016 he states:
My only available days next week are Thursday or Friday morning
- Mr Peck consented to the Tribunal orders to finish the works by 24 March 2016. As part of agreeing to those orders Mr Peck should have considered the time it takes to facilitate multiple parties for hold inspections. The Tribunal does not find that any unreasonable delay has been caused by the homeowner's experts to attend inspections. The Tribunal does not find that prior to 23 March 2016, the homeowners themselves have done anything to delay the works proceeding or that they refused to give access. The Tribunal finds that Mr Peck has not completed the works as he has agreed. In relation to the complexity of rectifying the windows, the defect was known to Mr Peck at the time he made the agreement and he should have considered how the hold point inspections may impact on the work schedule. The Tribunal finds that the works have not been completed within time by Mr Peck because he did not properly plan for them.