Conclusion and findings
22In determination of the Allen matter, the issue of whether the proposed development was compatible with the character of the local area arose as a result of the provisions of clause 54A(3) of SEPPARH. Consideration of that matter was made against the existing and future character of the area, see [65]. The DFC for the Elanora Heights locality is described at [23] of that judgment. At the time of assessing that application, the four large street trees adjacent to the site were to be retained. That factor was considered an important element of the application where, at [69] I state:
The development will sit at a height below the tree canopy and has been designed to minimise the bulk and scale when viewed from a public place, however, by its nature ad as anticipated by SEPPARH, will be larger than other dwellings in the local area however, smaller in scale to those buildings within the neighbourhood centre. Existing and new native vegetation, including canopy trees will be integrated with the development and the building is of contemporary design. With the changes made to the façade by the applicant and those further changes required by condition C13 together with the colour palette proposed (Exhibit F), I am satisfied the built form will be consistent with that espoused in the character statement and will be visually compatible with its context.
23At [66] I determined the character of the area is defined by the extent of landscaping, large allotments and buildings in a landscaped setting.
24The condition the subject of the appeal was a disputed condition in Allen. At [74] of that judgment I state:
I also consider that the requirement to underground the electricity and communication lines at the frontage of the site is reasonable given the importance of the street tree planting and plantings within the site necessary to maintain the character of the area. All services to the site should also be underground to ensure that there is no need to prune trees within or adjacent to the site. For that reason, it is appropriate to impose all of the conditions proposed by the council.
25The applicant now seeks deletion of the requirement to underground the wires and relies on the variation provisions of clause C1.20. For that consideration to apply, the preamble to the clause states:
Based on technical practicalities and advice from the energy supplier the merit for not proceeding with undergrounding of utility services will be considered for the following circumstances subject to achieving the outcomes of the control.
26Firstly, I am satisfied that the clause applies to the development as, the provisions of SEPPARH as applied in Allen provide for consent to be granted for the purposes of a residential flat building. Whilst some of the units within the building are required to be used for the purposes of affordable housing the building is a residential flat building and the provisions of clause C1.20 apply to the application.
27I have no evidence that there are any technical practicalities that prevent the undergrounding works. To the contrary, the evidence of the electrical experts is that the works are a "doable day to day project". There is no advice from the energy supplier that objects to the works, says it is impractical or would not be approved. Accordingly, I do not consider that it is appropriate to evoke the variation clause.
28The evidence of the electrical experts is that the works can be achieved by utilising the existing poles and therefore, no additional poles would be required. The perceived visual impact from any additional poles as described by Mr Boston would not arise. The benefits of undergrounding the wires would provide for the planting of tree species within the road reserve that grow to heights similar to that of the trees opposite the site. The experts agree that street tree planting must occur for the completion of the development, it is the form that planting is to take that is in dispute. I consider that it is desirable and important to replace those trees lost arising from the footpath construction with trees that will achieve a height considerably greater than 3.5m. Such planting would also form an important transition from the neighbourhood centre to the adjacent residential area and compliment the plantings on the opposite side of St Andrews Gate and the character identified in the description of DFC for the Elanora Heights locality contained in the DCP. The fact that the planting may not continue the entire length of the street is not an important consideration.
29Finally, I must consider whether it is reasonable in the circumstances of the case to require works beyond the immediate property boundary. The council does not oppose the retention of those wires that cross St Andrews gate from the existing light pole however submits that the costs associated with undergrounding of that section of wires that extend beyond the prolongation of the site boundary to the western pole should be the responsibility of the developer. Firstly, I am satisfied that the works are required under the DCP and are for the planning purpose of improving the amenity of the area. Secondly, I am satisfied that the requirement to underground the wires reasonably and fairly relates to the development. From the evidence available, the only way that Ausgrid would approve the works is to connect to the existing power poles and not add additional poles.
30Having regard to my determination of the importance of street tree plantings to heights in excess of 3.5m, the planning purpose of undergrounding the wires can only be achieved if the works are extended beyond the immediate site frontage. To achieve the objectives of the DCP, that work must, on evidence available to the Court, extend beyond that frontage.
31Ms Irish, for the council, submits that the works are not confined to that section of the roadway that extends from the immediate prolongation of the side boundaries and can extend beyond that point. She cites the Macquarie Dictionary definition of adjacent as being "lying near, close, or contiguous; adjoining; neighbouring". In Botany Bay City Council v Saab Corp Pty Ltd [2011] NSWCA 308, Basten JA at [19-20] considered similar provisions and states:
19 It is apparent that the obligation imposed on the developer is to place underground "all service cables" in the street (or, in the language of the condition, road reserve - nothing was suggested as turning on this variation in language) "adjacent to" the site and thus not in the part of the street which is not so adjacent. There is no reason to limit the obligation to cables providing services to the development itself. First, the condition is not in terms so restricted. Secondly, it must cover cabling that predates the development. Thirdly, it is clear from the authorities, that no such constraint should be implied as a limitation on power. As explained by Gibbs CJ in Cardwell Shire Council (referred to at [15] above) at 388, a condition requiring the upgrading of a road and bridge away from the development site (and not exclusively used by residents of the development) could properly be the subject of a condition attaching to the development approval.
20 Improvement to the amenity of the area immediately adjacent to the development is a proper subject of an approval; it is not advanced by restricting the obligation to cables providing services to the development itself. The condition requires that if the cables are in that part of the street adjacent to the site, they must go underground at the developer's expense.
32I consider that the location of the works as agreed by the electrical experts, whilst extending beyond the immediate boundary of the site, are works within the adjacent road verge and by necessity, are to be relocated underground across the total frontage of the development and, in the circumstances of the case beyond that frontage. I do not consider that this is unreasonable in the circumstances of the case and on the basis of the evidence before me, including the cost of that additional work as a proportion to the whole cost.
33For the reasons detailed above condition B6 should be retained however, as agreed by the council, it is appropriate to clarify the extent of that works to exclude the undergrounding of that cable that crosses the roadway to the dwelling opposite the site to that detailed by the electrical experts on the plans attached to their expert report.
34The Orders of the Court are:
(1)The appeal is upheld in part.
(2)Development consent N0749/10 is modified by amending condition B6 to read as follows:
B6 Matters to be incorporated into the development and maintained over the life of the development:
(i)All utility services including overhead power supply and communication cables located in the adjacent road verge, excluding the overhead wires that cross St Andrews Gate from the existing pole that supports the street light to the dwelling on the southern side of the roadway, are to be placed and/or relocated underground at the full cost of the developer. The extent of works shall be that detailed on Sheet 1 of1 Revision A dated 13 December 2013 drawn by G Beaton.
(ii)The adjustment of all public utilities and services is to be at the full cost of the developer.
(iii)Street lighting facilities to the development street frontage of the site in the existing Public Road reserve are to be provided at the full cost of the developer and in accordance with the requirements of Energy Australia.
(3)The exhibits, other than exhibits 3 and 6, can be returned.
Sue Morris
Commissioner of the Court