© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2021] NSWSC 1052
Supreme Court of NSW
2021-08-19
Williams J
Original judgment source is linked above.
Introduction
Nature of the proceedings
Strike out and amendment motions
Paragraph 45 is an allegation of fraud
Fraud must be alleged with specificity
The fraud allegation is not stated with sufficient specificity and particulars
Timing of the strike out application
Other matters
Conclusion and orders
ANNEXURE 45 The Representations and the Further Representations were: (a) false; or (b) knowingly false; or [Not used] (c) made wilfully, in that they were made with: (i) reckless disregard ; (ii) further or in the alternative, reckless indifference, as to whether they were true or false, in that unbeknown to the Company: (i) the First Cross-Defendant (which was the entity within the joint venture with responsibility for construction at the Mt Pleasant mine site) was in April 2018 insolvent, or near insolvent, and likely to be placed in administration; Particulars Notes 18 and 26.1 to the financial statements and reports of fourth Cross-Defendant for the financial year ended 31 December 2018 lodged with the Australian Securities and Investments Commission, document number 7EAK85978. Letter dated 19 November 2018, from DRA (Carvelas) to MACH Energy (Purnamasidi) [MAC.0010.0017.03135] at p.4 Unincorporated Joint Venture Agreement between the First Cross-Defendant and the Second Cross-Defendant dated on about 2 November 2016, schedule 4 [MAC.1004.0001.53595] (ii) the Contractor had significantly under-stated the time and cost to complete the Works under the Contract resulting in the Second Cross-Defendant making a provision in its accounts of approximately $52 million for additional costs expected to be incurred to complete the Contract over and above the costs originally budgeted for. Particulars Notes 18 and 26.1 to the financial statements and reports of fourth Cross-Defendant for the financial year ended 31 December 2018 lodged with the Australian Securities and Investments Commission, document number 7EAK85978
(iii) from at least April 2018, First Cross-Defendant was more focussed on its own commercial outcomes within the joint venture between the First Cross-Defendant and the Second-Cross Defendant than it was on delivering the best for the project outcomes for all parties, which outcomes included achieving the Dates for Practical Completion; Particulars Letter from Mr Carvelas of the Second Cross-Defendant to Mr Purnamasidi of the First Cross-Claimant dated 19 November 2018 [MAC.0010.0017.03135] (iv) the delivery of the best for project outcomes for all parties necessitated at least wholesale changes to, or control of, the First Cross-Defendant's site management staff by the Second Cross-Defendant (because construction of the Project was the responsibility of the First Cross-Defendant as between the First Cross-Defendant and the Second Cross-Defendant); Particulars Letter from Mr Carvelas of the Second Cross-Defendant to Mr Purnamasidi of the First Cross-Claimant dated 19 November 2018 [MAC.0010.0017.03135] (v) the Second Cross-Defendant could not make wholesale changes to. or take control of. the First Cross-Defendant's site management staff. or take any other steps to deliver best for project outcomes, until it took control of the First Cross-Defendant; Particulars Letter from Mr Carvelas of the Second Cross-Defendant to Mr Purnamasidi of the First Cross-Claimant dated 19 November 2018 [MAC.0010.0017.03135] (vi) any negotiation between the First Cross-Defendant and the Second Cross-Defendant as at April 2018 for the control of the First Cross-Defendant would take weeks, if not months, to be concluded; Particulars This fact is inferred from the following (which were also not known by the Company as at the date of the SVA or the receipt by it of notice of the satisfaction of the conditions precedent to the SVA operation): (A) the First Cross-Defendant and the Second Cross-Defendant had been in negotiation for the control of the First Cross-Defendant since at least 10 March 2018; see the affidavit of Mr Michael Crowe dated 17 May 2021 (Crowe Affidavit) at [65]; (B) The Second Cross-Defendant had been, and was, reluctantly negotiating with the First Cross-Defendant for its acquisition; see letter dated 19 November 2018, from DRA (Carvelas) to MACH Energy (Purnamasidi) [MAC.0010.0017.03135] at p.4; (C) The Second Cross-Defendant's parent, DRA Global Ltd, finally acquired the First Cross-Defendant in August 2018: see the Crowe Affidavit at [14]; (vii) further and in the alternative to (i) to (vi) above: (A) as at 23 March 2018 and at all material times thereafter: 1. the First Cross-Defendant and (or) Second Cross-Defendant knew (but did not communicate to the Company) that they could not estimate or measure, alternatively, had not or could not fully estimate or measure. the amount of re-work (being defect repair or works to correctly dimension. cut or size the Second Cross Defendant-sourced structural steel and other elements for installation or erection at the site), and for those reasons estimate the time that would be required to undertake such rework, which work would need to be performed by the First Cross-Defendant, the Second Cross-Defendant or either of them, in order for the Cross-Defendants to achieve Practical Completion of SP1, SP2 and SP3 (or any of them); 2. the First Cross-Defendant and (or) Second Cross-Defendant knew (but did not communicate to the Company) that the said completion dates then being proposed by them for Practical Completion of SP1. SP2 and SP3 (being SP1 - 7 September 2018, SP2 - 9 October 2018 and SP3 - 20 December 2018) (or any of them) were not based on any tested, or known, or verifiable assumptions regarding the amount of and duration of re-work activities that would need to be performed by the First Cross-Defendant, the Second Cross-Defendant or either of them to achieve Practical Completion of SP1, SP2 and SP3 (or any of them); 3. the First Cross-Defendant and (or) Second Cross-Defendant knew (but did not communicate to the Company) that the said completion dates then being proposed by them for Practical Completion of SP1, SP2 and SP3 (as above) would not be met if an allowance was made in the program of the amount of and duration of re-work activities that would need to be performed by the First Cross-Defendant, the Second Cross-Defendant or either of them to achieve Practical Completion of SP1, SP2 and SP3 (or any of them); Particulars (i) Particulars of the dates then being proposed by the First Cross-Defendant. the Second Cross-Defendant (or either of them) are contained in an internal email by Mr Grinsell forwarded to Mr Crowe (for the First Cross-Defendant and the Second Cross-Defendant) dated 22 March 2018 [CDJ.017.011.6797] and [CDJ.017.011.6798]: see the Crowe Affidavit at [77[ and [78]; (ii) Particulars of the programming assumptions being made by the by the First Cross-Defendant, the Second Cross-Defendant (or either of them), and the effects of those programming assumptions are contained in an internal email between Mr Grinsell, Mr Crowe and Mr Kennedy (or the First Cross-Defendant and the Second Cross-Defendant) dated 23 March 2018 [CDJ.017.001.4735]; see the Crowe Affidavit at [82]; (B) as at 5 April 2018 and at all material times thereafter, the First Cross-Defendant and (or) the Second Cross-Defendant knew (but did not communicate to the Company) that the Dates for Practical Completion of SP1 and SP2 (being about 22 August 2018 in respect of SP1 and 9 October 2018 in respect of SP2) could not be met, alternatively, would not be met, or alternatively were at risk of not being met; Particulars This fact is inferred from the following facts (or any of them): (i) the facts referred to in particular (viii)(A) above; (ii) by his email dated 5 April 2018, Mr Crowe advised Mr MacDonald, Mr Smith, Mr Massey and Mr Allen (of the First Cross-Defendant and the Second Cross-Defendant) that, during negotiations with Mr Winter, Mr Crowe had got "the removal of the incentive from SP1 & 2 into areas where" the First Cross-Defendant and the Second Cross-Defendant "will recover the incentive based on the site teams advice". By this sentence Mr Crowe conveyed the fact that, based on the site teams advice, the Dates for Practical Completion then being proposed for SP1 and SP2 would not be achieved (such that no incentive would be recoverable by the First Cross-Defendant and the Second Cross-Defendant if attached to those proposed dates). See the Crowe Affidavit at [88], [CDJ.028.005.0612]; (iii) by his email dated 14 April 2018, Mr Crowe advised Mr Humphrey. Mr Kennedy, Ms Janson, Mr Grinsell and Mr Collins (of the First Cross-Defendant and the Second Cross-Defendant) that the Date for Practical Completion of SP1 would not be achieved by the date then being proposed (22 August 2018) and that there was some risk that the Date for Practical Completion of SP2 would not be achieved by the date then being proposed (9 October 2018). See the Crowe Affidavit at [95] [CDJ.017.001.5834].
Amendments 23 August 2021 - Corrected typographical error within coversheet DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 23 August 2021
G&S Engineering Services Pty Ltd
MACH Energy Australia Pty Ltd