© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2024] NSWLEC 28
Land and Environment Court (NSW)
2024-03-26
Pepper J, Pty Ltd J
Original judgment source is linked above.
Friends of Coila Seek Interim Injunctive Relief to Stop Subdivision Works
A Residential Subdivision is Approved, Modified and Challenged
Legislative Framework
Legal Principles Applying to the Grant of an Interim Injunction
Evidence of the Parties
Is There a Serious Question to be Tried?
There is No Serious Question to be Tried
Where Does the Balance of Convenience Lie?
The Balance of Convenience Favours Refusing Interim Relief
FoC Should Pay the Respondents' Costs of the Application
Orders
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 02 April 2024
South East Forest Rescue Incorporated INC9894030 v Forestry Corporation of New South Wales [2024] NSWLEC 7
South East Forest Rescue Incorporated v Forestry Corporation of New South Wales [2024] NSWCA 64
Tegra (NSW) Pty Ltd v Gundagai Shire Council [2007] NSWLEC 806; (2007) 160 LGERA 1
Friends of Coila Incorporated trading as Friends of Coila (Applicant)
Friends of Coila Seek Interim Injunctive Relief to Stop Subdivision Works
(a) development consent 2248/83 granted on 3 December 1984 ("the 1984 consent");
(b) a modification approval in respect of the 1984 consent granted on 1 March 2022 ("Mod 22");
(c) an Aboriginal Heritage Impact Permit granted on 7 December 2022 ("AHIP"); and
(d) a subdivision works certificate granted on 14 March 2024, issued under Mod 22 permitting McCloy to commence excavation works on the land ("swc").
A Residential Subdivision is Approved, Modified and Challenged
(a) the filling of land (condition 1d);
(b) trunk stormwater drainage works (condition 1g);
(c) Aboriginal heritage (condition 1i); and
(d) erosion and sediment control (condition 1j).
(a) the proposed development was substantially the same as that the subject of the 1984 consent;
(b) an updated environmental impact statement was required. However, because the original development consent approved the clearing of the land in its entirety, there would be no increase in the impact on biodiversity and a biodiversity development assessment was not required;
(c) while the site partially contains an endangered ecological community ("EEC"), swap oak flood plain forest, because the footprint of the proposed development was not different to the original approval, no further assessment is required;
(d) because there is a coastal wetland adjacent to the proposed development there was the inclusion of a water sensitive urban design and bio retention treatment for water quality;
(e) a number of cultural assessments have been carried out previously to assess Indigenous cultural heritage, nevertheless an AHIP was conditioned as necessary to be obtained before work commenced. This involved a separate application process and further cultural heritage assessments; and
(f) no clearing beyond what was originally approved or within public reserves would be permitted.
(a) the appointment of a project manager to oversee the actions the subject of the AHIP; and
(b) that certain objects must not be harmed, including all human remains.
(a) the original development application ("the DA");
(b) the 1984 consent; and
(c) reports provided as part of the assessment of the DA, including a flora and fauna study and Aboriginal cultural heritage assessment (see below at [33] for a more detailed description of the report).
Reasons for decision
12 The Council is the relevant consent authority.
13 The Consent had not lapsed (p 1 and Appendix B Assessment Report).
14 The Assessment Report confirms MDA0124/20 was assessed by Council under section 4.55(1A) of the EPA Act.
15 The Council was satisfied that the proposed modification was of minimal environmental impact for the following reasons (pp 5 - 6 Assessment Report):
(a) The Consent authorised the clearing of the Land. The proposed modification would not result in any additional impact on biodiversity values or waterways (pp 2 and 5 Assessment Report).
(b) The amended proposal included a water sensitive stormwater design to ensure that the development has a lessened impact on the runoff water quality and scouring of Coila Lake from that which was originally approved (p 6 Assessment Report).
(c) The amended proposal minimises the impact the proposal and its infrastructure will have on the natural environment (p 6 Assessment Report).
16 The Council was satisfied that the development to which the Consent as modified relates is substantially the same development as the development for which the Consent was originally granted for the following reasons (p 3 Assessment Report):
(a) The proposed modification would not change the footprint of the proposed subdivision - changes were proposed to the lot and road layout resulting in an increase from 61 to 72 lots.
(b) The proposed modification did not change the character of the original development.
(c) The proposed modification would not have a greater environmental impact but would instead improve environmental outcomes.
17 The Council notified the application in accordance with Council's Advertisement and Notification Code (p3 Assessment Report).
18 The Council considered all submissions made concerning the proposed modification in accordance with Council's Advertisement and Notification Code (pp 4; and 7 - 10 Assessment Report).
19 The Council took into consideration such of the matters referred to in section 4.15(1) as are of relevance to the development the subject of the application (p 7 Assessment Report).
20 The Council took into consideration the reasons identified in the Notice of Determination dated 3 December 1984. The Council did not otherwise give reasons for the grant of the Consent.
Native Vegetation
The existing approval is overlaid with the approved subdivision layout.
A biodiversity development assessment report is not required to be submitted if Council is satisfied that the modification will not increase the impact on biodiversity values.
A review of Council's file revealed that the assessment report and development consent whilst not expressly stating clearing is approved, in Council opinion imply that clearing has been considered for removal. The assessment report uses the term under the heading "Impact on Environment and Action proposed/required" total change - previously considered. The consent goes on to require physical works including services road construction and filling of the land implying in Council's opinion that clearing is approved.
It is Council's position that DA 2248/83 has approved the clearing of the land in its entirety. As a result, Council is of the opinion the development will not increase the impact on biodiversity values and as such Section 7.17(2)(C) of the Biodiversity Conservation Act 2016 is considered to be met. An advisory note will be placed on the consent advising the applicant of their obligations under the Environment Protection and Biodiversity Conservation Act 1999. Council also sought legal advice to clarify the position this can be seen in appendix D.
Aboriginal Heritage
There are many cultural heritage sites of significance in the Tuross area. The original archaeologist was likely to have been Henry Warner who did some site assessments in 1966. Further studies were done by Navin Officer Heritage Consultant in 2004 and Grinbergs/ Heritage Solutions in 2007-2008.
No new archaeological assessment was required for the current modification of the 1983 approval. A condition will be imposed that identifies the previous cultural heritage assessments and that an Aboriginal Heritage Impact Permit (AHIP) is required prior to works commencing.
A further application was submitted to Council in 2012 for a similar subdivision and was accompanied by a Cultural Heritage Assessment. This was undertaken by Onsite Cultural Heritage Management and a detailed assessment was provided to Council and the NSW Office of Environment and Heritage (now Heritage NSW). After further assessment by the applicant, General Terms of Approval (GTA) were issued by NSW OEH in March 2018. A requirement of the GTA's is that an AHIP is obtained.
The original consent did not addressed aboriginal heritage, with the above knowledge a condition is proposed to be placed on the consent prior to any works being undertaken an AHIP be obtained. Council also confirmed the imposition of this condition with the legal advice in appendix D.
3. A minimum of two (2) days prior to the commencement of sewer main and/or water main construction works, the contractor is to contact Council's Water and Sewer Operations Coordinator to arrange for inspection:
4. It is understood that earthworks (cut) in Stage 2 and 3 areas shall form part of Stage 1works. All disturbed areas shall be progressively re-established (topsoiled and grassed) to the satisfaction of Council Development Engineers. Disturbed areas are not to be left un-stabilised for extended periods. Sediment and erosion control measures shall be implemented progressively around all disturbed areas until they are fully established.
5. If, during the course of carrying out any earthworks on site, acid sulphate materials V are identified, no further earthworks shall take place until the consent holder has lodged an Acid Sulfate Management Plan prepared by a suitably qualified person in accordance with the NSW Acid Sulfate Soils Manual (1998) refer https://www.epa.nsw.gov.au. Earthworks can recommence once the plan has been submitted and approved by Council and all necessary remedial works have been undertaken.
(1) Proceedings for judicial review of a decision must be commenced within 3 months of the date of the decision.
(2) The court may, at any time, extend the time for commencing proceedings fixed by subrule (1).
(3) In considering whether to extend time under subrule (2), the court should take account of such factors as are relevant in the circumstances of the particular case, including the following -
(a) any particular interest of the plaintiff in challenging the decision,
(b) possible prejudice to other persons caused by the passage of time, if the relief were to be granted, including but not limited to prejudice to parties to the proceedings,
(c) the time at which the plaintiff became or, by exercising reasonable diligence, should have become aware of the decision,
(d) any relevant public interest.
(4) This rule does not apply to proceedings in which there is a statutory limitation period for commencing the proceedings.
(5) This rule does not apply to any proceedings in which the setting aside of a decision is not required.
(1) Matters for consideration - general In determining a development application, a consent authority is to take into consideration such of the following matters as are of relevance to the development the subject of the development application -
(i) any environmental planning instrument, and
(ii) any proposed instrument that is or has been the subject of public consultation under this Act and that has been notified to the consent authority (unless the Planning Secretary has notified the consent authority that the making of the proposed instrument has been deferred indefinitely or has not been approved), and
(iii) any development control plan, and
(iiia) any planning agreement that has been entered into under section 7.4, or any draft planning agreement that a developer has offered to enter into under section 7.4, and
(iv) the regulations (to the extent that they prescribe matters for the purposes of this paragraph),
(v) (Repealed)
that apply to the land to which the development application relates,
(b) the likely impacts of that development, including environmental impacts on both the natural and built environments, and social and economic impacts in the locality,
(c) the suitability of the site for the development,
(d) any submissions made in accordance with this Act or the regulations,
(e) the public interest.
...
(6) Definitions In this section -
(a) reference to development extends to include a reference to the building, work, use or land proposed to be erected, carried out, undertaken or subdivided, respectively, pursuant to the grant of consent to a development application, and
(b) non-discretionary development standards means development standards that are identified in an environmental planning instrument or a regulation as non-discretionary development standards.
5.5 Duty to consider environmental impact
(1) For the purpose of attaining the objects of this Act relating to the protection and enhancement of the environment, a determining authority in its consideration of an activity shall, notwithstanding any other provisions of this Act or the provisions of any other Act or of any instrument made under this or any other Act, examine and take into account to the fullest extent possible all matters affecting or likely to affect the environment by reason of that activity.
activity means -
(a) the use of land, and
(b) the subdivision of land, and
(c) the erection of a building, and
(d) the carrying out of a work, and
(e) the demolition of a building or work, and
(f) any other act, matter or thing referred to in section 3.14 that is prescribed by the regulations for the purposes of this definition,
_but does not include - _
(g) any act, matter or thing for which development consent under Part 4 is required or has been obtained,...
4.2 Proceedings brought in the public interest
(1) The Court may decide not to make an order for the payment of costs against an unsuccessful applicant in any proceedings if it is satisfied that the proceedings have been brought in the public interest.
(2) The Court may decide not to make an order requiring an applicant in any proceedings to give security for the respondent's costs if it is satisfied that the proceedings have been brought in the public interest.
(3) In any proceedings on an application for an interlocutory injunction or interlocutory order, the Court may decide not to require the applicant to give any undertaking as to damages in relation to -
(a) the injunction or order sought by the applicant, or
(b) an undertaking offered by the respondent in response to the application,
if it is satisfied that the proceedings have been brought in the public interest.
Legal Principles Applying to the Grant of an Interim Injunction
162 In Tegra (NSW) Pty Ltd v Gundagai Shire Council (Tegra), Preston CJ of LEC identified the following factors as relevant to the balance of convenience:
(1) whether irreparable injury will be caused (at [18]);
(2) whether damages are an adequate remedy (at [26]);
(3) whether undertaking as to damages are offered (at [29] to [31]);
(4) where the status quo lies (at [35]);
(5) the nature of interlocutory relief sought (at [37] to [38]);
(6) the relative strength of each party's case (at [41]);
(7) equitable considerations (at [43]);
(8) prejudice to third parties (at [51]);
(9) the public interest (at [54] to [56]); and
(10) the time period before a final hearing (at [58]).
(a) an affidavit of Nicole Parsons, an elder of the Walbunja Wawarrawarri people, affirmed on 22 March 2024. She deposed to the physical and spiritual harm to country caused by the development the subject of the 1984 consent, Mod 22 and the swc. Email communication exhibited to her affidavit dated 24 January 2023 to McCloy, requested that the development cease to avoid damage to the land;
(b) an affidavit of Sam Tierney, the solicitor for FoC, affirmed 22 March 2024. In that affidavit, Tierney stated that the mission of FoC, which was incorporated on 18 October 2022, is "to advocate on behalf of the natural environment of Coila Lake, its catchment and surrounds". All of its Committee members are volunteers, are not legally trained, and do not own any real property bordering the land. Moreover, he has learned from various members of FoC that the land has important cultural significance to the First Nations people, namely, the Walbunja and Brinja-Yuin, who use it to conduct their business. Finally, he deposed that it was not until 15 March 2024, that residents whose properties adjoined the land were notified that works the subject of the swc would commence on 18 March 2023;
(c) an Aboriginal Cultural Heritage Assessment & Aboriginal Heritage Impact Permit application in respect of the subdivision prepared by OnSite in May 2015 ("OnSite Report"). The Report noted a moderate potential for burials to occur within the land; that in consultation with Registered Aboriginal Parties a number of strategies to mitigate loss of Aboriginal heritage values were endorsed, including the salvage of the many artefacts located on and in the land; and that the subdivision would have a "substantial impact" on the identified values of the land; and
(d) a Flora and Fauna Study Proposed Subdivision report prepared by PMA on 8 November 2002 ("the PMA Report"), that concluded that "the proposed subdivision upon the study area will be able to commence without having a 'significant effect' on any threatened species, populations or ecological communities or their habitats."
(a) an affidavit of Danielle Le Breton, solicitor for McCloy, sworn on 11 December 2023, annexing a schedule of works to take place on the land, including the works programmed for the weeks commencing 4, 11 and 18 December 2023, and the estimated cost of those works, including that "approximately $400K has been spent to date this year undertaking cultural heritage work that is required as part of our DA." A list of this work was annexed to her affidavit, together with a statement that McCloy has spent over $1.1million as at 10 December 2023 in preparation to undertake the works required to deliver the development; and
(b) three affidavits of Louise McAndrew, a solicitor employed by the solicitor on the record for McCloy, affirmed on 15, 20 and 26 March 2024. McAndrew deposed to the history of the proceedings, including an abandoned attempt at seeking interim interlocutory relief by FoC on 11 December 2023 before Duggan J because it was not ready to proceed. Importantly, she also gave evidence that should works cease, the standdown costs would be approximately $19,800 per day, in addition to demobilisation costs of $19,000 and remobilisation costs of $19,000.
(a) "the environment, being the native flora and fauna on or surrounding the land";
(b) the cultural significance of the land to First Nations people;
(c) the matters referred to in s 4.15(1) of the EPAA;
(d) "intergenerational and intragenerational equity, and the conservation of biological diversity and ecological integrity as being relevant to the objects embodied in the EPAA";
(e) the PMA Report, the OnSite Report, the letter from the Council dated 7 March 2022, and the 99 submissions made to the Council in respect of the proposed development; and
(f) the public interest in relation to preserving Indigenous cultural heritage.
(a) the First Nations people have expressed opposition to the development on the basis that it would cause harm to the environment, which was a fact known to the Council, as the Parsons's evidence demonstrates;
(b) the only credible and reliable evidence about the impact of the development on the Walbunja People can come from an Indigenous elder, such as Parsons; and
(c) an inference is available that the Council failed to take into account the concerns of relevant Indigenous peoples, such as Parsons, because no conditions were attached to Mod 22 or swc in order to avoid or mitigate the impact of the proposed development on the Walbunja People.
(a) the impact of the proposed development on native vegetation and Aboriginal heritage, noting in particular, the cultural significance of the area and that a new archaeological assessment was required as part of the modification application approval process, including the need to obtain an AHIP. The AHIP contains protections against the desecration of burial sites and certain artefacts. While respecting the evidence of Parsons, it cannot be said that the Council did not have regard to the cultural significance of the land to First Nations people. It plainly did;
(b) the 99 submissions received, of which there were 84 objections. The document also noted that two petitions were received which, (it may be inferred, were against the proposed development). It was not necessary for the Council in its Statement of Reasons or Assessment Report to set out an analysis of each submission, as FoC seemed to suggest;
(c) express reference was made to s 4.15 of the EPAA in the Statement of Reasons and the Assessment Report. The factors contained in s 4.15 of the EPAA were considered at length, especially when the Assessment Report is read as a whole;
(d) the environmental impact of the development was discussed in the Statement of Reasons and the Assessment Report and the conclusion was reached that the proposed modification would not result in any additional impact to biodiversity values or waterways to that already approved by the 1984 consent. In this context, it must be remembered that no challenge is made to the 1984 consent;
(e) while there is no express reference to intergenerational or intragenerational equity (to the extent that this is part of the object of facilitating ecological sustainable development referred to in s 1.3 of the EPAA) in the Statement of Reasons or the Assessment Report, assuming for present purposes that it is a discrete mandatory relevant consideration, it may be inferred, in the absence of any evidence to the contrary, that this was considered by the Council in its assessment of the impact of the proposed modification on the environment and the Indigenous cultural heritage of the land;
(f) the Council took into account the reasons identified in the Notice of Determination of the 1984 consent. Although this instrument was not before the Court, the PMA Report and the OnSite Report were before the Council when it determined the 1984 consent and regard to the 1984 consent was had by the Council in granting Mod 22;
(g) the letter dated 7 March 2022 was the Council's letter. It is difficult to understand how it therefore did not consider the matters referred to therein. The content of this letter again demonstrates that the mandatory relevant matters about which FoC complain were taken into account by the Council in determining to grant approval to the modification application; and
(h) the public interest as articulated by FoC was extensively considered and discussed (see the reasoning above).
(a) if FoC succeeds in challenging the validity of Mod 2022 and the swc, without injunctive relief the judgment of the Court is likely to be rendered ineffectual;
(b) there is no appreciable prejudice that would be suffered by McCloy if the restraint is imposed. By contrast, there is a real likelihood that if the works are allowed to continue, that First Nations people will lose their spiritual connection to the land, in addition to the potential for destruction of culturally significant items;
(c) FoC's interests are consonant with the public interest, whereas McCloy's interest are private in nature. The private interests of McCloy must yield to the public interest of preserving Indigenous cultural heritage where there is evidence of the irreparable harm caused to that heritage by the proposed development;
(d) because the motion has been brought in the public interest, there is no need to proffer an undertaking as to damages by FoC; and
(e) there was no delay in bringing the application for injunctive relief because the Statement of Reasons was only provided on 27 February 2024 and the swc was only issued on 14 March 2024.
The Balance of Convenience Favours Refusing Interim Relief
(a) application to modify the 1984 consent was granted on 1 March 2022;
(b) FoC was aware of Mod 22 at the time that it was made and was engaged in discussion with the Council concerning its merits;
(c) on 7 December 2023 FoC commenced these proceedings and brought an application for urgent interlocutory relief seeking to restrain McCloy from carrying out work on the land;
(d) on 11 December 2023, in response to the application for urgent interlocutory relief, McCloy filed and served the Le Breton affidavit, which informed FoC in manifestly clear terms that preliminary works had commenced on 27 November 2023; that tree removal (with cultural heritage supervision) would commence in the week commencing 11 December 2023; and that construction work would begin in January 2024 when the swc was expected to be issued;
(e) despite being aware that works had commenced, FoC did not press its application for urgent interlocutory relief when it was listed for hearing before Duggan J on 11 December 2023 because, amongst other things, it was not ready (T4:01-12);
(f) the only identifiable basis of challenge in the original summons was that the 1984 consent had lapsed; that basis was abandoned in correspondence over January 2024 by FoC;
(g) on 7 February 2024 McCloy invited FoC to withdraw the interlocutory application (which it had not sought to reagitate since 11 December 2023) and also queried why the proceedings should not be dismissed given the absence of any grounds of review in the summons;
(h) FoC did not respond to the letter of 7 February 2024, nor did it seek leave to amend its summons to plead grounds of review despite its counsel admitting before the Court at a directions hearing on 16 February 2024, that it needed to do so; and
(i) on 14 March 2024 FoC gave notice that it would be seeking to amend its summons by notice of motion returnable on 3 May 2024. No notice was given to McCloy or the Council that it would continue to press the interlocutory application.
33 ... there are, however, sound reasons why interlocutory injunctive relief should not be granted. The primary reason is that I consider that the applicant's unexplained delay in commencing the proceedings in the LEC is a sufficient basis for refusing such relief. As the Full Court of the Federal Court observed in Carlton and United Breweries (NSW) Pty Ltd v Bond Brewing New South Wales Ltd [1987] FCA 412; (1987) 76 ALR 633 at 638:
The grant of injunctive relief, interim or final, is, of course, discretionary. Delay by an applicant in instituting or in prosecuting a claim for an injunction may be a ground for refusing relief, even at a final hearing. Where an interim injunction is sought on the basis that the applicant need show only a "serious" question of fact or of law, delay in seeking that relief is an important discretionary consideration...
(a) the cost of standing down equipment and workers is nearly $20,000 per day;
(b) the demobilisation and remobilisation costs are also significant; and
(c) any significant stoppage will impact on the construction programme, with unknown consequences.
(i) the stripping of topsoil is currently underway under the supervision of a heritage consultant and members of the local Indigenous groups in accordance with a Cultural Heritage Management Plan; and
(ii) substantive earthworks are due to commence on 4 April 2024.
(a) development can still occur under the 1984 consent;
(b) the AHIP (not challenged) permits damage to Aboriginal artefacts in any event. It is, however, conditioned to mitigate and avoid damage to Indigenous cultural heritage; and
(c) McCloy will consent to an expedited final hearing if sought by FoC.
(a) merely because the members of FoC are voluntary, are not legally trained, and that its mission statement states that its aim is to advocate on behalf of the natural environment of Coila Lake, does not, without "something more", render the proceedings as having been brought in public interest for the Court to exercise its discretion under r 4.2(3) of the LEC Rules (Caroona Coal Action Group Inc v Coal Mines Australia Pty Limited and Minister for Mineral Resources (No 3) [2010] NSWLEC 59; (2010) 173 LGERA 280 at [13-[17] and [60]-[61] and Seek Justice at [75]). FoC have not identified anything "more"; and
(b) absent significant irreversible environmental harm, an injunction is not normally granted without an undertaking as to damages (Seek Justice at [76]). Again, FoC has not demonstrated to any degree that such harm will occur. The evidence of Parsons is not, in my view, sufficient. In any event, the harm complained of can still occur pursuant to the 1984 consent and the AHIP.
FoC Should Pay the Respondents' Costs of the Application
(1) Subject to rules of court and to this or any other Act -
(a) costs are in the discretion of the court, and
(b) the court has full power to determine by whom, to whom and to what extent costs are to be paid, and
(c) the court may order that costs are to be awarded on the ordinary basis or on an indemnity basis.
(2) Subject to rules of court and to this or any other Act, a party to proceedings may not recover costs from any other party otherwise than pursuant to an order of the court.
(3) An order as to costs may be made by the court at any stage of the proceedings or after the conclusion of the proceedings.
42.1 General rule that costs follow the event
Subject to this Part, if the court makes any order as to costs, the court is to order that the costs follow the event unless it appears to the court that some other order should be made as to the whole or any part of the costs.
42.7 Interlocutory applications and reserved costs
(1) Unless the court orders otherwise, the costs of any application or other step in any proceedings, including -
(a) costs that are reserved, and
(b) costs in respect of any such application or step in respect of which no order as to costs is made,
are to be paid and otherwise dealt with in the same way as the general costs of the proceedings.
58 The sense in r 42.7 is perhaps illustrated by this application for a different costs order. To consider the application, the Court has had to canvass a detailed and complicated procedural history in not one, but two hard fought proceedings and the detailed submissions made in support of and against the costs orders. Rule 42.7 appears to be directed to discouraging parties from expending further resources on such costs disputes and to focus on the substantive proceedings. If I might use an imperfect sporting analogy: if litigation is compared to a sporting match, then r 42.7 indicates that the normal result after an interlocutory application is that the parties should "play on" until the final hearing.
(1) with the exception of order 7, the applicant's amended notice of motion filed on 25 March 2024 is dismissed;
(2) the applicant is to pay the respondents' costs of the application; and
(3) the exhibits are to be returned.
Friends of Coila Incorporated t/as Friends of Coila
Eurobodalla Shire Council
(2006) 227 CLR 57
(1968) 118 CLR 818
(2010) 173 LGERA 280
(1987) 8 NSWLR 533
(1990) 170 CLR 534
(1998) 193 CLR 72
(2007) 160 LGERA 1
(1987) 76 ALR 633
[1968] HCA 1
[1986] HCA 58
[1998] HCA 11
[2006] HCA 46
[1990] HCA 59