© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2003] NSWLEC 206
Land and Environment Court (NSW)
1993-07-01
Pain J, Bignold J, Pearlman J, Mr JJ
Original judgment source is linked above.
Introduction
Legal issues identified 5. The overarching issue relates to the obligation of the Council to collect and spend money under s 94 of the Environmental Planning and Assessment Act 1979 (the EP&A Act). There were important amendments to the EP&A Act in 1993 so that the scheme of the Act before and after those amendments must be considered as the development consents were granted before and after these amendments. There are three bases for the Applicants' claims as follows: (i) the Council has not undertaken all the work for which s 94 contributions were collected and the Applicants are entitled to recover their contributions (abandonment), (ii) each Applicant paid s 94 contributions at an incorrect, higher rate than it should have and are entitled to recover the amount overpaid (overpayment), and (iii) damages are claimed as an alternative to the part of the claim based on overpayment.
Abandonment (i) What was the basis on which the Council could levy and spend s 94 contributions before the requirement for contributions plans was implemented on 1 July 1993? (Questions 1, 2, 3 and 4) (ii) What was the basis on which the Council could levy and spend s 94 contributions after the requirements for contributions plans was implemented on 1 July 1993? (Question 5) (iii) What is the nature of the Council's obligations in holding s 94 contributions? (Questions 2, 6 and 7) (iv) Does the Court have jurisdiction to give refunds of s 94 contributions? (Question 8) (v) In order to get a refund, must a contributor be able to show his/her/its money is unspent by the Council? (Question 9)
Overpayment (i) Is the Applicants' claim for overpayment maintainable at all? (ii) Does the Court have jurisdiction to award damages for breach of the provisions of s 94 of the EP&A Act in relation to overpayments? Relevant legislation Section 94 EP&A Act as it applied 1988 (year first consent granted) to 1 July 1993 8. Section 94(1) of the EP&A Act stated in 1988 to 13 February 1992: Subject to subsection (2), where a consent authority is satisfied that a development, the subject of a development application, will or is likely to require the provision of or increase the demand for public amenities and public services within the area, the consent authority may grant consent to that application subject to a condition requiring - … (b) the payment of a monetary contribution …
Section 94 of the EP&A Act as it applied in 1993 - 1998 13. Sections 94(7) and (8) were inserted as follows: (7) When granting consent to a development application made on or after the first anniversary of the date of assent to the Environmental Planning and Assessment (Contributions Plans) Amendment Act 1991 or such earlier day as may be fixed by proclamation for the purposes of this subsection, a council may impose a condition referred to in this section only if it is of a kind allowed by, and is determined in accordance with, a contributions plan approved under section 94AB. (8) A contribution of a kind allowed by a contributions plan may be disallowed or amended by the Court on appeal because it is unreasonable, even if it was determined in accordance with the plan. 14. The requirement to have a contributions plan in place under s 94(7) was ultimately extended so as to be required from 1 July 1993. While s 94(3) became s 94(6) on 1 July 1998 the wording of that section has continued unaltered since 1992.
The Regulations 15. Amendments made to the Environmental Planning and Assessment Regulation 1980 (EP&A Regulation 1980), which commenced on 14 February 1992, inserted clauses concerning the making of contributions plans and record keeping obligations of councils in relation to s 94 contribution plan monies. Part 4A - Contribution Plans, required that a contributions plan must be drawn up and contain specific details.
Planning and contribution instruments 20. The relevant planning instruments and s 94 contributions plans, being the East Bowral Development Control Plan No 8 (the 1987 DCP), the Developer Contributions Plan - Roads and Traffic Management Facilities effective 1 July 1993 (the 1993 Contributions Plan) and the Developer Contributions Planning for East Bowral effective 4 September 1996 (the 1996 Contributions Plan), relied on by the Applicants are shown in the table below. The total amount of roadworks planned for the East Bowral area in the relevant instruments and total amount of s 94 contributions required for that work is also shown.
Instrument Total of East Bowral Roadworks Section 94 contributions required for work 1987 DCP $4,714,488 $2,276,488* (*incorrect figure should be $182,000 less) 1993 Contributions Plan $4,606,375 $3,120,513 1996 Contributions Plan $3,050,000 $2,673,500
Summary of the development consents issued to the Applicants 22. The following table sets out the eight relevant development consents and conditions relating to roads, for the consents issued before and after 1 July 1993, which the Applicants' case relied on. I note that a development consent granted to Frevcourt, No 160/89, was included in the Applicants' submissions. As no contributions were paid pursuant to this consent I have not included it as it is irrelevant. Further, a Frevcourt development consent no 448/92 is referred to in the Council's submissions only. As Frevcourt did not rely on that consent in argument I have not included it in this table either.
Applicant Development consent no Date granted Conditions of consent Before 1 July 1993 Payment to Council of contributions levied in respect of Section 94 of the EP&A Act subject of this development consent to be made prior to the endorsement and release of the final plan of subdivision, or as elsewhere specified. … This clause has been applied in accordance with Council's adopted policy.
Frevcourt 282/92 10/07/92 The contribution by the applicant of monies for the following designated purposes prior to the release of the linen plan of subdivision. The exact amount of contribution will be calculated at the rate applicable at the time of payment. The current contribution rate is noted below. … The payment of a monetary contribution towards the improvement of local roads to which the subdivision has its frontage, and having the benefit of local access thereto, it being noted that the current contribution is $114,240 [amount amended 8 Dec 1992].
Payment to Council of contributions levied in respect of Section 94 of the EP&A Act subject of this development consent to be made prior to the endorsement and release of the final plan of subdivision, or as elsewhere specified … This clause has been applied in accordance with Council's adopted policy.
Frevcourt 511/92 25/05/93 The contribution of the applicant of moneys for the following designated purposes prior to the release of the linen plan of subdivision. The exact amount of contribution will be calculated at the rate applicable at the time of payment. The current contribution rate is noted below. … The payment of a monetary contribution towards the improvement of providing roads of local ["within the East Bowral precinct" added 18 August 1994], it being noted that the current contribution is $83,694 [amount amended 18 August 1994]. Payment to Council of contributions level in respect of Sec 94 of the EP&A Act subject of this development consent to be made prior to the endorsement and release of the final plan of subdivision, or as elsewhere specified. … This clause has been applied in accordance with Council's adopted policy.
Kettle* 483/88 19/09/88 The contribution by the applicant of monies for the following designated purposes prior to the release of the linen plan of subdivision. The exact amount of contribution will be calculated at the rate applicable at the time of release of the linen plan of subdivision. The current contribution rate is noted below. … The payment of a monetary contribution for the improvement of Old South Road to which the subdivision has its frontage, it being noted that the current contribution is $85,860. Payment to Council of contributions levied in respect of Sec 94 of the EP&A Act subject of this development consent to be made prior to the endorsement and release of the final plan of subdivision, or as elsewhere specified. … This clause has been applied in accordance with Council's adopted policy.
Rutar 689/89 14/11/89 The contribution by the applicant of monies for the following designated purposes prior to the release of the linen plan of subdivision. The exact amount of contribution will be calculated at the rate applicable at the time of release of the linen plan of subdivision. The current contribution rate is noted below. … The payment of a monetary contribution for the improvement of Old South Road to which the subdivision has its frontage, it being noted that the current contribution is $126,000. Post July 1993 Frevcourt 338/95 04/01/96 Payment to Council of contributions levied in respect of Section 94 of the EP&A Act subject of this development consent to be made prior to the endorsement and release of the final plan of subdivision, or as elsewhere specified … This clause has been applied in accordance with Council's adopted policy. 102/96 09/05/96 Rutar 640/95 07/02/96 The contribution by the applicant of moneys for the following designated purposes prior to the release of the linen plan of subdivision. The exact amount of contribution will be calculated at the rate applicable at the time of payment and will reflect the current contribution rates which are reviewed annually. The current contribution rate is noted below. … Kettle* modified 483/88 19/07/94 The payment of a monetary contribution towards the improvement of local roads to which the subdivision has its frontage, and having the benefit of local access thereto, it being noted that the current contribution is $… [338/95 amount amended 20 May 1996, 102/96 amount amended 4 June 1996]
Legal issues - Abandonment Statutory position before 1 July 1993 Question 1 Prior to 1 July 1993, was a council in breach of the EP&A Act if it failed to hold or apply monies, collected in consequence of a valid condition of consent given prior to that date, for the purposes stipulated in a DCP containing a works schedule and a formula for fixing contributions? If so, what was the breach of which it was guilty?
Applicants' arguments 24. The Applicants argued that the Council by adopting a Development Control Plan in 1987 for contributions to be made for roadworks under s 94 created an obligation on the Council: (a) to prepare that Development Control Plan (DCP) under the EP&A Act and EP&A Regulation 1980 (b) to apply the DCP to any application for development that considered or required the contributions of monies under s 94. This obligation was said to arise because of the scheme of the EP&A Act and EP&A Regulation 1980 which provided for the making of a DCP.
Section 94(3) imposed on the Council an obligation to hold such monies collected in "trust" and only pay out those monies for the public amenities or public services identified in the DCP and to do so within a reasonable time. The mandatory obligation on a council in respect of the contributions made under s 94(3) as it applied before the 1993 amendments are as identified by Holland J in Levadetes v Hawkesbury Shire Council (1988) 67 LGRA 190 at 195: (i) to hold the money in trust for the purposes for which the payment was required; (ii) to apply the money towards providing the relevant public amenities or services (in the Applicants' submissions being those amenities identified in the plans required by the Department of Urban Affairs and Planning Guidelines or the 1987 DCP); (iii) to do so in a reasonable time; and (iv) to apply the monies in such a manner as will meet the increased demand for those public amenities or services.
The Applicants argue that there is a clear breach by the Council of requirements (ii) and (iii) in Levadetes because the Council does not intend to provide those "relevant public amenities" at all. These were specified in the 1987 DCP but many were abandoned in the 1993 and, particularly, the 1996 Contributions Plan.
The Applicants argue that the 1987 DCP defined the "purpose" for which the Council held the monies contributed under s 94 and contained lists of proposed works or expenditures relevant to the contributions collected under s 94(3). Accordingly, the Council was bound to apply the money to the works in the proposed list in the 1987 DCP and this was to be reflected in the development consents issued by the Council.
The Applicants dispute that it is only by reference to the development consent conditions imposed by the Council and the terms of s 94 that the obligation of the Council under s 94 is defined under the EP&A Act. The Applicants argue that there was a general practice that required s 94 monies to be applied in conformity with the guidelines provided by the Department of Urban Affairs and Planning. That criteria extended to the making of a plan for the provision of public amenities in instruments such as DCPs and instituting proper accounting procedures. (There were no regulations requiring accounting procedures for s 94 contributions until 1992).
Where a Council uses a DCP for the purposes of determining the amount which should be paid by way of contribution under s 94 and then charges those amounts exactly, the contents of that DCP become part of the obligation under which the monies are held on trust, that is to spend such contributions on those works set out in the DCP. This is the obligation that is created to comply with the s 94(3) obligation to "apply the money towards providing public amenities or public services or both".
The Applicants approach is that the 1987 DCP should be compared to the 1993 Contributions plan in order to make a decision as to whether a particular item of proposed expenditure has been "abandoned". Other works can be substituted but there is no objective test proposed by the Applicants to reach a decision as to whether substitution has occurred. If an item has been abandoned, the contributions paid should be assessed and the amount of each dollar paid which may be attributed to the abandoned item should be refunded.
Council's argument 31. Section 94 was amended in 1985 and the requirement that had previously existed for a Council to identify potential future community need resulting from a development in an environmental planning instrument was deleted. There was no requirement that a Council seeking to recoup costs under s 94 do so by a DCP or any other like mechanism as the Applicants submitted. Under s 90(1)(a)(iv) a council only had to consider a DCP, it was not bound as a matter of law to apply it.
Finding on Question 1 34. I accept the Council's submission that the 1987 DCP was not, under the EP&A Act as it applied between 1988 and 1 July 1993, the basis on which the s 94 contributions collected from the Applicants had to be collected and spent. Failure to comply with the 1987 DCP in this respect is not a breach of s 94. While I understand the Applicants submitted that it was the practice, encouraged by the Department of Urban Affairs and Planning (DUAP) (as it was then known), to include programs of works in DCPs and other plans, it was not a legal requirement under s 94 of the EP&A Act as it applied at that time. I further note that observations made by Pearlman J in Toadalla Co Pty Ltd v Dumaresq Shire Council (1992) 78 LGERA 261 are to the same effect where she stated at 269: Nothing in s 94(3) requires evidence of a plan or proposal for the application of the funds, so long as they are expended within a reasonable time. Toadalla concerned a development consent granted in 1988 and her Honour was considering the same statutory scheme as applies in this part of this case.
The Applicants' submissions relied heavily on the Council's responsibility as identified in Levadetes, set out at par 25. The difficulty of this approach for the Applicants' case is that the dictum in Levadetes, which I agree with and apply as being the general obligations of the Council under s 94, does not address the particular circumstances the Applicants are arguing, namely that the money must be expended on the works listed in the DCP. Reliance on Levadetes does not satisfy the Applicants' case.
The Applicants' argument is effectively that DCPs have the same legal status as contributions plans introduced after 1 July 1993. The duty imposed by s 90(1)(a) (iv) of the EP&A Act before 1 July 1993 was to consider the contents of a DCP in assessing a development application. There was no necessity (until 1993) for a demand for contributions from developers to be supported by a contributions plan or any other like document such as a DCP.
The validity of a condition requiring payment of a contribution was to be determined upon the test set out in s 94(1) and s 94(2) and the Council's obligations once it received the money were set out in s 94(3). If these sections were complied with the imposition of the development consent condition was in accordance with the Act and the dealing by the Council with the funds was not unlawful. Provided the Council collected funds in accordance with valid conditions of development consent and spent the money towards the purposes specified in those consents within a reasonable time, then s 94(3) has been satisfied. It is not a breach of s 94 if the exact terms of the 1987 DCP were not applied by the Council in spending the money, provided s 94(3) was complied with in the spending of contributions collected.
There was no obligation on the Council under s 94 to impose a condition requiring s 94 contributions in such a way as to be consistent with the DCP nor to expend funds paid to it in the manner anticipated in the 1987 DCP. "The purpose for which the payment was required" is to be determined by reference to the provisions of the development consents granted by the Council and s 94(1) and s 94(3). In this case the relevant conditions of consent referred to payment "towards the improvement of roads of local [within the East Bowral precinct]", (511/92), "towards the improvement of local roads to which the subdivision has its frontage" (282/92), and "for the improvement of Old South Road to which the subdivision has its frontage" (689/89, 483/88).
None of these conditions of consent refer to the 1987 DCP and nor is this required. The consents do state that "Payment to Council of contributions levied in respect of s 94 of the EP&A Act the subject of this development consent to be made … This clause has been adopted in accordance with the Council's adopted policy". This provision does not assist the Applicants' case. Section 94(1) and s 94(3) did not require that the money be spent in accordance with a predetermined program provided s 94(3) was complied with i.e. the money was applied "towards providing public amenities or public services or both within a reasonable time and in such a manner as will meet the increased demand for those amenities or services".
There is one argument the Council made which I do not accept. It does not affect my finding on this question but is a significant matter in relation to the consents granted after 1 July 1993 dealt with in Question 5. The Council argued that the obligation it has in spending the money under s 94(3) is separate and disconnected from the obligation it has in charging for and holding any monetary contribution under s 94(1).
Section 94(3) before 14 February 1992 required that the consent authority hold the contribution money "in trust for the purpose for which the payment was required". As the Council pointed out the section does not specifically state that s 94 contributions must be spent on that purpose. Rather it provides that contributions must be applied towards providing public amenities or public services within a reasonable time to meet the increased demand for those amenities or services. Section 94(1) makes clear that a contribution can only be levied if a development is likely to require the provision of or increase the demand for public amenities and services within the area.
There are clear statements in Toadalla that s 94 contributions are held by the Council by way of a "statutory" trust which has a special purpose involving the provision of public amenities and services. I consider the scheme established by s 94(1), (2) and (3) requires that s 94 contribution money held for a purpose must be spent for that purpose. Before 1 July 1993 the "purpose" was not required to be precisely determined in a plan, so that the development consent conditions requiring s 94 contributions as in force before 1 July 1993 are important in determining the scope of that purpose.
I note that in Toadalla, the applicants sought to challenge, in 1992, the validity of development consent conditions granted in 1988, on the basis there was insufficient "nexus" between the proposed development and the contributions levied to satisfy s 94. Her Honour in that case found the consent conditions in question were invalid in part because they lacked sufficient "nexus" to the development in question. In these proceedings the Applicants are not challenging the validity of the consent conditions in question and there has been no attempt to present evidence on that basis. Given my finding that the Council's obligations are defined by the consent conditions, which are valid, and the terms of s 94(3), and that obligation is not defined by the 1987 DCP, there is no basis to argue there has been a breach of s 94 based on a failure to spend the contributions in accordance with the works specified in the 1987 DCP as the Applicants have done. (I also note that in Toadalla her Honour refused to grant the relief sought, which included a refund of s 94 contributions, on discretionary grounds, an issue which is highly relevant to these proceedings and a matter I will return to).
For the Applicants to be successful in their claim they would have to show that the roadworks on which s 94 contributions were spent by Council for the consents granted before 1 July 1993 were not spent "towards providing public amenities or public services … as will meet the increased demand …" within a reasonable time. The evidence relied on by the Applicants has focussed exclusively on a failure to apply the works schedule in the 1987 DCP. That evidence does not otherwise address the issue of whether s 94(3) has been complied with in spending s 94 contributions. There is no evidence before me that the funds spent by Council were not used to satisfy increased demand for services, or were not spent in accordance with the development consent conditions in accordance with s 94(3).
The Applicants did also raise as an alternative argument that s 94 contributions received by the Council had not been spent in a reasonable time but little emphasis was given to this argument in the Applicant's submissions. There was no evidence presented in a form that I could understand to support this claim. I am unable to consider that argument further and, given the lack of clear evidence presented by the Applicants, it is unlikely that I could reach a conclusion in any event.
In terms of the first part of Question 1, the answer is in the negative. It is therefore unnecessary to answer the second part of the question, namely "If so, what was the breach of which it was guilty?". I also note that much of the Applicants' argument concerning abandonment focussed on a comparison between the 1987 DCP and the 1993 and 1996 Contribution Plans, but that analysis is not open to support claims for abandonment given my finding on Question 1. Question 2 Was the effect of the deletion of the expression "in trust" from s 94(3) of the EP&A Act in 1991 [which commenced on 14 February 1992] such as to change in any material way the nature and extent of a council's obligations pursuant to s 94(3)? If so, what was the change?
Finding on Question 2 47. The Applicants submit that the consequence of the words "in trust" being removed from s 94(3) has made no difference to the obligation of the Council in relation to the monies held. The Council agreed with this view. I also see no reason to treat the basis on which s 94 contributions are held after 14 February 1992 as any different because the words "in trust" were deleted. In other words, even though the words "in trust" were removed in 1992, the s 94 contributions were still held in a form of statutory trust. In my view there was no change in the nature and extent of the Council's obligations pursuant to s 94(3) following the deletion of the words "in trust" in s 94(3) in 1992.
Finding on Question 3 49. The amendments to s 94 which became operative on 1 July 1993, did not affect the holding and application of monies paid pursuant to consents granted before 1 July 1993. There is no suggestion in s 94(7) that the amendments have any retrospective operation on development consents already existing pursuant to which monies have been paid. Indeed the wording of the section makes clear that the amendments apply only to development applications made on or after the date of assent of the Act introducing the requirement for contributions plans (s 94(7)). The obligations of the Council after 1 July 1993 in relation to the holding and spending of s 94 funds collected pursuant to development consents granted before 1 July 1993 continued to be the same as set out in my finding on Question 1.
Question 4 Where a council received after 1 July 1993 money by way of contributions pursuant to a consent given before 1 July 1993, did s 94 require the council to apply the money so received: (a) in accordance with any contributions plan then in force, or (b) in accordance with the terms of s 94(3) without reference to any such plan, or (c) in accordance with the terms of the condition and s 94(3) without reference to any such plan? 50. The evidence produced by the parties demonstrates that payment of s 94 contributions pursuant to consents given before 1 July 1993 took place for several years after that date.
Finding on Question 4 52. The answer is (c) in that clearly the terms of the conditions of consent are relevant within the context of s 94(3) of the EP&A Act and s 94(3) itself must be complied with. A contributions plan which was not in existence at the time the consents were granted will obviously not affect how contributions paid under those consents are applied. This answer flows logically from my findings on Question 1 - 3.
Summary of conclusions on claims for consents granted before 1 July 1993 53. Given my findings on questions 1, 2, 3 and 4, the Applicants' claims in relation to abandonment for the development consents granted before 1 July 1993 must fail (Frevcourt 282/92, 511/92; Kettle 483/88 (as unamended); Rutar 689/89). The Applicants have failed to demonstrate there was of a breach of s 94 because of abandonment by Council of work specified in the 1987 DCP. The Applicants did not base their case on a failure to spend the s 94 contributions in accordance with the conditions of consent and s 94(3). Furthermore, there has been no challenge to the validity of the development consent conditions pursuant to which payment has been made, and payments made under the consents must be presumed valid as a consequence. Statutory position after 1 July 1993 Question 5 Where monies have been paid to a council by way of s 94 contributions pursuant to a valid condition attached to a consent validly given after 1 July 1993, is the council necessarily in breach of the Act if it applies the monies otherwise than in accordance with the schedule of works contained in the contributions plan in force at the time of: (a) the consent; or (b) the application of the monies? If so, what is the breach of which it is guilty? Applicants' arguments 54. The Applicants' argue that the roadworks to be carried out with the Applicants' s 94 contributions were identified in substantial detail in the relevant Contributions Plans including the 1987 DCP and the 1993 Contributions plan. (I found in Question 1 that the 1987 DCP does not have the same legal effect as a contributions plan). The Applicants also relied on the fact that the 1996 Contributions Plan reduced the works program to that in the 1993 Contributions Plan. (The table at par 20 shows a big reduction ($1,556,375) in roadworks proposed under the 1996 Contributions Plan compared to the 1993 Contributions Plan). The obligation of the Council is to spend s 94 contributions in accordance with a contributions plan as implemented through development consent conditions and to do so in a reasonable time. The obligations of the Council continued to be the same as defined in Levadetes (see par 25). Failure to meet those obligations is a breach of s 94 of the EP&A Act. Although not made explicit in the Applicants' argument, I understand the Applicants' case to be that the contributions plan in force at the time development consent was granted must be applied (option (a) in Question 5).
(2) Alternatively, the Applicants submitted that the discretion allowed to Councils in disbursing s 94 monies, as recognised in Rodmac, no longer applies after 1 July 1993. The Council does retain a discretion to vary the amenities/services s 94 contributions are spent on if the ability to provide a "specific amenity" is no longer available and the next contributions plan substitutes a viable and proper alternative. The discretion is determined by the terms of the contributions plan.
Council's submissions 58. The Council argues that the EP&A Act, whilst requiring the imposition of conditions of consent pursuant to s 94 only in accordance with a Contributions Plan, does not contain a provision requiring that moneys paid pursuant to such a condition be expended in accordance with the Contributions Plan. Rather, s 94(3) provides that the money collected by a Council by way of contributions paid pursuant to s 94(1) must be held for that purpose but requires only that it be applied "towards providing public amenities or public services … in such a manner as will meet the increased demand". The Council suggests it can collect money for roadworks specified in a contributions plan and apply it for other related roadworks, provided that s 94(3) is complied with.
The provisions in the regulations do not require strict adherence to a Contributions Plan, insofar as it identifies specific proposals for expenditure. The Council argues the EP&A accounting regulation requires that monies expended will have been spent "on the various kinds of public amenities or services" for which the contributions have been received (EP&A Regulation 2000). I note that the EP&A Regulation 1980 cl 41L which applied at the relevant time, later the EP&A Regulation 1994 cl 34, used the word "categories" rather than "kinds".
The words "towards providing" in s 94(3) suggest that Parliament intended that monies be applied in accordance with the section, and not in accordance with any other criteria: Rodmac at 9.
The Council argues that the purpose of a contributions plan is to ensure that there is a logical and comprehensive approach to the assessment of the nature and quantum of the s 94 contribution demanded, and to demonstrate that the relevant nexus between the levy and development is present. It does not require a Council to conduct its financial affairs in relation to the provision of public amenities and services according to a fixed scheme from which it is not free to depart if circumstances warrant. There is discretion in the manner in which the money is applied. The obligation of a council is to see that the public purpose which underlies the contributions scheme can be implemented in a workable and manageable way (see Rodmac and Toadolla).
Contributions plans are made upon the basis of the best information available about future needs and demands. That information is prognosticatory and may sometimes be wrong. A council should not be held to every element of its plans and the EP&A Act does not attempt to do so. It recognises by its silence that the purpose of the contributions plan is served by its making, not by its implementation. The method of assessment of the contributions, which provides the test of the validity of the condition, is ultimately, when it comes to paying for the amenity or services, subjugated to the practicalities of affording and paying for what is required.
There is discretion available to the Council in how s 94 monies are spent provided this conforms with s 94(3). The discretion must be exercised to ensure that the demand created by new development is met, insofar as and to the full extent that is workable and manageable: Rodmac. The Council relies on Rodmac to assert that the Council has some discretion to substitute one facility for another provided s 94(3) is complied with.
Finding on Question 5 64. In order to answer the question posed, it is necessary to review the Council's obligation to hold and apply s 94 contributions after 1 July 1993. Is the Council obliged to spend s 94 contributions on the same basis for which these are collected? 65. The terms of s 94(3) have not materially altered since the introduction of contributions plans, given my finding in Question 2 that the removal of the words "in trust" in 1992 did not affect the basis on which money is held under s 94(3). Section 94(3) is essentially the same as I considered in Question 1 in relation to development consents granted before 1 July 1993. The obligation under s 94(3) is still that expenditure must be applied towards providing public amenities or public services and in such a manner as will meet increased demand for public amenities and services within a reasonable time. The way the section is drafted does not expressly require that the money held for the purpose for which it is required under s 94(1) and s 94(3) be spent for that purpose, as I noted at par 42 in Question 1. The only basis, however, on which a condition seeking monetary contribution under s 94 can be levied is on the basis of a contributions plan under s 94(7) of the EP&A Act.
(1) Contributions exhausted 69. I agree with the Council's argument that it is open on the wording of s 94(3) that not all of the amenities identified in a contributions plan must be built if, due to cost increases between collection and later application of s 94 contributions, it is no longer possible to build the same number or extent of facilities from the amount of s 94 contributions collected. Section 94(3) recognises the need to apply the s 94 contributions "towards providing public amenities or services or both … and in such a manner as will meet the increased demand for those amenities or services or both." Under this scenario all the s 94 contributions would nevertheless be spent on amenities and services specified in the contributions plan but on a reduced basis. This circumstance would not be a breach of s 94(3) in my view.
(2) Less demand for services 70. If there has been an unforeseen reduction in the actual level of increased demand compared to that anticipated in a contributions plan for a greenfields site so that facilities and services are not proceeded with to the same extent as originally envisaged is that a breach of the EP&A Act? Arguably not in that the collection of monies pursuant to a s 94 contribution plan is proper at the time of collection and it may well be (as the Council argued here) that there has been expenditure towards the provision of these facilities and services in accordance with s 94(3), just not to the extent envisaged in the contributions plan. It does not automatically follow that in these circumstances there will be "excess" money. Whether there is "abandonment" and excess funds under this scenario will depend on the evidence.
(3) Extent of discretion to substitute works for those in a contributions plan 71. The extent to which works can be substituted for those in a contributions plan was raised in argument. Since 1 July 1993 contributions plans have been required as the basis upon which s 94 monies are collected by councils and I have held contributions must be spent for purposes defined in a contributions plan as implemented by the imposition of consent conditions imposed in accordance with the contributions plan. Councils have less flexibility than before 1 July 1993 in exercising their discretion in how s 94 money ought be spent. I do not consider that councils have as wide a discretion in the use of s 94 funds outside a contributions plan as the Council has argued.
While I can agree there is some flexibility in how s 94 contributions are spent, as recognised by the Applicants in their first argument (see par 56), the extent of the discretion available to the Council depends in large part on the wording of the relevant contributions plans and the facilities or services in question. The Council gave an example of collecting s 94 funds to pay for six netball courts but then using the funds to pay for a basketball court which is more expensive to build than a netball court. That may well be acceptable. In the case of roadworks, however, there may be far less scope to enable substitution which is still in conformity with the contributions plan. The terms of the contributions plans will define the scope of the Council's discretion. To what extent the Rodmac "workable and manageable" approach (see par 55) can be applied will depend on those terms and the nature of the facilities and services to be provided.
I do not accept the alternative argument (argument (2)) put by the Applicants (par 56) that there can only be substitution of facilities on the basis of a subsequent contributions plan.
The actual wording of the development consent conditions are also relevant in considering what the Council's obligations are in each case. Nelson and Rodmac demonstrate how the development consent conditions can allow more or less flexibility to councils in carrying out works using s 94 contributions. The Applicants relied on Nelson v Ballina Shire Council (1993) 80 LGERA 271 in support of their argument. In Nelson the council had required a s 94 contribution for a specific public amenity - the sealing and draining of a portion of road - as a condition of the development consent. The council had not carried out the works and requested the applicant to pay more money before it would carry out the work. The applicant sought a declaration and a mandatory injunction to compel the council to carry out that work. Bignold J found that the council was in breach of its obligation under s 94(3) and so declared.
The key factual difference between Rodmac and Nelson related to the general nature of the development consent conditions in Rodmac in contrast to the specific development consent conditions in Nelson which the council was obliged to apply. The decisions in Rodmac and Nelson concerned the statutory position before 1993 but are useful to refer to as demonstrating the importance of development consent conditions.
For the development consents granted after 1 July 1993 in this case, the relevant conditions provide for the payment "towards the improvement of local roads to which the subdivision has its frontage, and having the benefit of local access thereto …". These consent conditions, underpinned by a contributions plan in this case, are quite general in nature. Such conditions arguably provide broader scope to the Council in its application of s 94 contributions pursuant to a contributions plan than if the consent conditions specified particular facilities and services by name.
The answer to Question 5 is that s 94 contributions must be applied to the schedule of works in the contributions plan in force at the time development consent is granted, not a works schedule in a later contributions plan. There are circumstances outlined above where failing to precisely carry out that schedule of works will not be a breach of s 94. Have the Applicants satisfied the onus of proving that there is a breach of s 94(3)? 78. The Applicants claim for abandonment can only be considered in relation to the four development consents granted after 1 July 1993. The Applicants may only have a claim in relation to works "abandoned" in the 1993 Contributions Plan as evidenced by their absence from the 1996 Contributions Plan. The Applicants bear the evidentiary onus of proving there is a breach of s 94 on this basis. Much of the Applicants' case relied on the Council's alleged failure to carry out any roadworks specified in the 1987 DCP. I have already held there is no breach of s 94 resulting from that alleged failure.
Applicants' argument 83. The Applicants argued that s 94 contributions are held on the basis of a statutory trust as described in Toadalla. Unlike the Council however, the Applicants maintained that in circumstances where the Council did not spend the s 94 contributions as it was required to do, it would be in accordance with the terms of the trust that the unspent contributions be returned to the contributor of those funds. This would not be a breach of the statutory trust in which the money was held, it not being a charitable trust where payment could only be made for charitable purposes defined by the trust which precluded payment to a person who was not a "beneficiary" under that trust. There is no claim made by the Applicants that there has been a breach of any "trust" which entitles the Applicants to specific relief. Reliance is placed once again on Levadetes, see par 25.
Council's arguments 88. The Council relies on Toadolla as authority for the proposition that, due to the nature of the obligation under s 94, the Council must administer the trust in the interests of the "public as a whole" (and not the contributors) in providing the public amenities and services. The public as a whole becomes the beneficiary of the trust. Accordingly, provided the Council can show that it has complied with s 94 in the collection and disbursement of money it cannot be liable to the contributors of that money. Bathurst City Council v PWC Properties Pty Ltd (1998) 100 LGERA 383 means that little or no weight should be placed on earlier cases such as Levadetes, Idameneo (No 9) Pty Ltd v Great Lakes Shire Council (1990) 70 LGRA 27 and Denham. In circumstances where a breach of s 94 is found the appropriate beneficiaries to whom payment could be made are arguably the current owners of the subdivided land, not the Applicants. Alternatively, it could be retained by the Council and applied for the benefit of the community.
Finding on Question 6 91. Section 94 contributions are held on statutory trust by the Council. Question 6 asks whether that "trust" gives primacy to the Council's duty to administer the funds for statutory purposes in the interests, and for the benefit, of the public. It is clear from Toadalla and PWC that the application of the "trust" by a council must be on this basis, but that does not mean the Council's duty in administering the trust is clear in all situations.
(iii) If the Court were satisfied that a council had not applied monies "within a reasonable time", would any other remedy be available?
Applicants' submissions 100. The Applicants' submissions address this argument only on the basis that there is a breach of the EP&A Act in this case. Section 124 of the EP&A Act provides: (1) Where the Court is satisfied that a breach of this Act has been committed or that a breach of this Act will, unless restrained by order of the Court, be committed, it may make such order as it thinks fit to remedy or restrain the breach. The Applicants are seeking a substantial refund of monies paid to the Council on the basis that the Court has a wide discretion under s 124 to remedy any breach of the EP&A Act and can so order.
Council's argument 102. The relief available under s 124 of the EP&A Act while not limited as to type is limited by the Court's jurisdiction in class 4 proceedings as defined by s 20(2) of the Court Act. The Applicants must establish that an order to refund money will be within jurisdiction because it will "enforce a duty or obligation" under the EP&A Act or correspond with a "command to exercise a function" under the EP&A Act and further, that to order such a refund will "remedy a breach of the Act".
Finding on Question 8 105. I make the following findings in relation to the three questions posed: (i) The cases relied on by the Applicants clearly suggest that the Court does have power to order a refund, assuming jurisdiction can be established on the facts in a particular case. I agree with and adopt the Council's submissions that the Court does not have jurisdiction under s 124 of the EP&A Act in the absence of a breach of that Act. The Applicants' arguments are based exclusively on the assumption there is a breach of s 94(3) of the EP&A Act in this case. However, it is far from clear on the facts presented to the Court in relation to roadworks that any breach of s 94 has occurred as a result of the Council's actions. (ii) It is unnecessary to answer (ii), and its meaning is unclear in any event.
(iii)Assuming there is a breach of the EP&A Act because the Court was satisfied that a Council had not applied monies "within a reasonable time", the case law makes clear that the Court can make orders such as requiring that work for which monies have been collected be carried out by the Council. I also stated in answer to questions 6 and 7 that while a refund cannot be ruled out, the Court will first look to other remedies such as whether contributions can be spent in conformity with the trust on public facilities and services required to meet the demand from the development. The only relief sought by the Applicants here is that of a refund and if I had found there was a breach of s 94 I would have provided an opportunity to the Council to address me on what other remedies are available to the Court. 106. I also note that in Hannan Street CJ thought that a right that can be enforced in any ordinary court will not necessarily be enforced by this Court; this Court in exercising its power under s 124 must have regard to the objects of the EP&A Act (at 313). His Honour noted (at 313) that: This involves, in appropriate cases, the evaluation of matters extending beyond the mere determination of the rights and matters in dispute between the immediate parties. It involves due weight being given to the public interest and the interests of other affected persons in the overall context of the pursuit of the objects broadly set out in s 5 . These comments have particular application in a case of this nature where a statutory trust to be administered for the public benefit is concerned.
Question 9 Assuming that the Court has power or jurisdiction to make an order that a council "refund" monies to a former contributor, is the contributor entitled to such an order where the contributor cannot prove that the actual funds contributed by him/her/it have not been spent in accordance with s 94(3). That is, is the contributor entitled to an order whether or not the funds contributed by him/her/it (as opposed to funds paid by others) are unspent?
Applicants' arguments 107. The Applicants submitted that Denham showed that in an appropriate case a refund can be made by a Council provided that sufficient money remained in the s 94 account. On the Applicants' expert evidence of Mr Price there are monies left in the account. According to Mr Price excess funds remain in the amount of $871,767. (This amount is disputed by the Council).
Council's arguments 108. The accounts show that all the s 94 contributions paid by the Applicants have been spent. The Council submits that for the two Frevcourt post-1993 consents (338/95 and 102/96) total payments of $41,846 were received during 1997. For the one Rutar post-1993 consent $46,170 was received in 1997. (As set out earlier at par 51 the amounts paid for consents granted before 1 July 1993 totalled $462,912).
Finding on Question 9 111. This question as drafted assumes that the Court does have power to order a refund to a contributor, but it should be noted that in this case I have made no finding that there is a breach of s 94, which is necessary to found the Court's jurisdiction to do so. The Applicants must show, applying Denham, that the s 94 contributions claimed by them for the four post 1 July 1993 consents, totalling at least $88,016, have not been spent. They have failed to discharge the evidentiary burden on them to do so. The findings of Talbot J in Denham (at 115) are directly applicable to this case and are worth repeating here: The applicant has not proved by tracing or any other accounting procedure that the contribution paid in the sum of $173,915.20 remains in the fund. It cannot do so by showing that the balance in the account at any relevant time appears to have exceeded that amount. The Council expended an amount significantly in excess of $173,915.20 out of the fund in the period between payment in and the demand for a refund. The only reason money remained in the account was that further contributions were being received on a regular basis. The surplus funds were not there as a consequence of a failure by Council to incur expenditure. … In the absence of a capacity to isolate any unspent part of the applicant's contribution from the balance in the fund at the relevant date, no refund can be made. … There being no means of distinguishing any part of the fund as being the applicant's contribution, the claim must fail. This may be an unjust result in the eyes of the applicant but it flows from the nature of the scheme established by s 94.
Conclusion on abandonment claim 115. I do not think there is any claim available to the Applicants for contributions concerning "abandonment" of roadworks in relation to the development consents issued to the Applicants before 1 July 1993. Nor, on the evidence presented, is it clear that there is any breach of s 94 in the way the Council has disbursed s 94 contributions paid pursuant to development consents granted after 1 July 1993. The Applicants have failed in their claim in relation to abandonment and in proving that any of the Applicants' funds actually remain to be refunded in the event a breach of s 94(3) was able to be established. Legal issues - Overpayment and damages (i) Is the Applicants' claim for overpayment maintainable? 116. The Applicants' claim for overpayments relies upon the principle that a Council is only entitled to collect a s 94 contribution based upon a s 94 Plan which was operative at the time the consent was granted: see Stockland (Constructors) Pty Ltd v Baulkham Hills Shire Council (Pearlman J, NSWLEC, 10 July 1996, unreported) and Mirvac.
(ii) Does the Court have power or jurisdiction to award "damages" for breach of the provisions of s 94 in relation to overpayment? 121. The Applicants are arguing, as an alternative to the claim for a refund of overpayments, that there has been a breach of the EP&A Act and the Applicants are entitled to damages. For the reason stated in par 119 I have found the Applicants cannot maintain their claim for overpayment. Their claim for damages in relation to overpayment must also fail as the Applicants did not put forward any argument to demonstrate that the Court has jurisdiction in circumstances where their primary argument has been dismissed, because it has not been shown there has been a breach of s 94 of the EP&A Act.
Discretion to apply s 124 of the EP&A Act 125. It is worthwhile given the length and complexity of these proceedings to provide my preliminary view on whether, had I found that a "refund" ought to be made by the Council to the Applicants in relation to roadworks, I would have awarded a refund on discretionary grounds.
Orders 129. I will make no formal orders at this stage. The Applicants should consider this judgment for a set period and then advise the Court of whether or not they wish to pursue the matter any further. If the matter is to proceed further the first issue about which I will require argument is in relation to the exercise of the Court's discretion. The issue of costs in relation to this part of the proceedings will also need to be dealt with in due course.
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Frevcourt Pty Ltd & Ors
Wingecarribee Shire Council
CITATION : Frevcourt Pty Ltd & Ors v Wingecarribee Shire Council [2003] NSWLEC 206 APPLICANTS Frevcourt Pty Ltd & Ors PARTIES : RESPONDENT Wingecarribee Shire Council FILE NUMBER(S) : 40176 of 2000 CORAM: Pain J Construction and Interpretation :- alleged breach of s 94 of the Environmental Planning and Assessment Act 1979 - Applicants claim Council has "abandoned" roadworks proposed in DCP and Contributions Plans for which s 94 contributions were collected - Applicants as contributors of s 94 contributions claim to be entitled to refund of contributions for "abandoned" roadworks - obligations of Council in holding and spending contributions received under s 94 - whether prior to 1 July 1993 Council was required to hold and spend s 94 contributions in accordance with a works schedule in a DCP - effect of removal of words "in trust" from s 94 - whether introduction of amendments on 1 July 1993 requiring a contributions plan effected holding and application of moneys in relation to consents granted before 1 July 1993 - in relation to consents granted after 1 July 1993 whether Council had to hold and spend s 94 contributions in accordance with the works detailed in a Contributions Plan - discretion of Council in spending s 94 contribution monies - whether Applicant's have proved a breach of s 94 - whether a refund to a contributor of s 94 contributions is consistent with the trust under which s 94 contributions are held - nature of s 94 contributions trust - alleged overpayment of s 94 contributions - whether Applicants are entitled to a refund of overpaid amounts based on alleged breach of s 94 - whether Applicants entitled to damages in the alternative to a refund for overpayment
Jurisdiction : - whether Court has jurisdiction to order a refund to a contributor of monies in the s 94 fund - whether the Court can order a refund where the contributor cannot prove their money remains unspent Environmental Planning and Assessment Act 1979 s 94, s 124 Environmental Planning and Assessment (Contributions Plans) Amendment Act 1991 Environmental Planning and Assessment Regulation 1980 cl 41F, cl 41L LEGISLATION CITED: Environmental Planning and Assessment Regulation 1994 cl 34 Environmental Planning and Assessment Regulation 2000 Land and Environment Court Act 1979 s 20 Local Government Act 1919 s 111, s 333 Local Government Act 1993 Sch 7 cl 6(2)(b) Bathurst City Council v PWC Properties Pty Ltd (1998) 100 LGERA 383; Denham Pty Ltd v Manly Council (1995) 89 LGERA 108; F Hannan Pty Ltd v Electricity Commission of New South Wales [No 3] (1985) 66 LGRA 306; Frevcourt Pty Ltd v Wingecarribee Shire Council (1992) 80 LGERA 75; Idameneo (No 9) Pty Ltd v Great Lakes Shire Council (1990) 70 LGRA 27; Levadetes v Hawkesbury Shire Council (1988) 67 LGRA 190; Mirvac Homes (NSW) Pty Ltd v Baulkham Hills Shire Council (2000) 110 LGERA 100; CASES CITED: N & S Oliveri Pty Ltd v Fairfield City Council [2002] NSWLEC 35; Nelson v Ballina Shire Council (1993) 80 LGERA 271; Progress & Securities Pty Ltd v North Sydney Municipal Council (1988) 66 LGRA 236; Rodmac Investments Pty Ltd v Great Lakes Shire Council (Bignold J, NSWLEC, 2 August 1991, unreported); Scharer v State of New South Wales (2001) 116 LGERA 217; Stockland (Constructors) Pty Ltd v Baulkham Hills Shire Council (Pearlman J, NSWLEC, 10 July 1996, unreported); Toadalla Co Pty Ltd v Dumaresq Shire Council (1992) 78 LGERA 261; Warringah Shire Council v Sedevcic (1987) 10 NSWLR 335 DATES OF HEARING: 25-27/03/2002, 9 -11/12/2002, 13/02/2003 (written submissions),04/03/2003 (written submissions), 31/03/2003 (written submissions), 03/04/2003, 04/04/2003 (written submissions), 11/04/2003 (written submissions) DATE OF JUDGMENT: 09/16/2003
(1998) 100 LGERA 383
(1995) 89 LGERA 108
(1992) 80 LGERA 75
(2000) 110 LGERA 100
(1993) 80 LGERA 271
(2001) 116 LGERA 217
(1992) 78 LGERA 261
(1987) 10 NSWLR 335