© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2003] VSC 276
Supreme Court of Victoria
2003-07-28
DODDS-STREETON J.
Original judgment source is linked above.
[2003] VSC 276
ARBITRATION - Commercial Arbitration - Award - Application for leave to appeal against award of Arbitral Tribunal - Construction of contractual terms adopted by Arbitral Tribunal alleged to constitute manifest error of law on face of award - Contractor alleged award misconstrued relevant contractual clauses - Literal construction of terms devoid of common sense, unworkable, contrary to authority - Careful exercise of judicial discretion to grant leave to appeal against construction of "one off" contractual clauses - Error must be obvious and evident, rather than merely arguable - Where arbitral tribunal's construction fairly arguable or reasonably open, or two views possible, manifest error not made out - Arbitral Tribunal's construction gives effect to interrelated literal terms in context, workable and preferred to Contractor's proposed construction - No manifest error of law on the face of award - Application dismissed.
"the Arbitrators (in paragraphs 7.10 - 7.18 of the Award) misconstrued clauses 2, 6, 7, 8 and 9 of the EPC Contract made between Fluor and the first defendant (Anaconda) on 21 August 1997 by:
* holding that in the absence of novation or assignment, clauses 2.9(1) and (d) of the EPC Contract render Fluor liable for any defect in the Facility as those terms are defined in clause 1 of the EPC Contract;
* holding that the cumulative effect of clauses 2, 6, 7, 8 and 9 of the EPC Contract is to create an obligation upon Fluor to design, construct and deliver a Facility complying with the Revised Scope Book with materials, where not otherwise specified, complying with clause 9.1(a) and/or (b), regardless of the operation of clause 2 upon Early Works Contracts;
* failing to hold that clauses 2, 6, 7, 8 and 9 of the EPC Contract have the effect that the obligations assumed by Fluor to Anaconda pursuant to the terms of the EPC Contract with respect to work performed by Early Works Contractors (as to which see paragraph 16 of the McDonald affidavit) were no greater than, and could rise no higher than, the obligations owed by the Early Works Contractors to the Owner (effectively Anaconda) pursuant to the Early Works Contracts."
"2. COMMENCEMENT 2.1 Contractor's Obligation to Commence The Contractor must immediately commence to perform the Project Works. 2.2 Owner to co-operate The Owner shall:
(a) cooperate with the Contractor during the performance of this Contract; and
(b) not materially interfere with the Contractor's agents, employees or Sub-contractors.
2.3 Contractor occupation of Site
The Owner:
(a) grants the Contractor and all persons authorised by it or by its Sub-contractors a non-exclusive, revocable, non-transferable contractual licence on and from the date of this Deed until Final Acceptance to enter, occupy and use the Site to carry out, or cause to be carried out, the Project Works;
(b) warrants that the Site is free from all Hazardous Material except any such material which may be brought on to the Site by the Contractor or those for whom it is responsible.
2.4 Owner's financing arrangement
(a) The Owner shall be responsible for obtaining sufficient financing for the Project Works.
(b) As security for meeting its obligations under this Contract, the Owners shall, within seven days, or such longer period to which the Owner and the Contractor agree, of the Award Date, provide to the Contractor an unconditional bank guarantee given by a bank reasonably approved by the Contractor for an amount of $40 million. The guarantee shall be returned to the Owner upon reasonably satisfying the Contractor that it has in place full financing to meet its payment obligations under the Contract.
2.5 Owner's Personnel
The Owner shall provide qualified, competent and, where necessary, licensed operations and maintenance personnel for testing, start-up and initial operation of the Facility. The Owner shall provide that such personnel perform the duties to which they are assigned in accordance with generally accepted practices and standards of the industry. The Owner shall supply, or cause to be supplied, sufficient small tools to facilitate on-the-job training of the operations and maintenance personnel.
2.6 Novation of Early Works Contracts
Promptly after the Award Date (or such later time as the Owner may direct), the Contractor shall execute a Deed of Novation in respect of each Early Works Contract.
2.7 Assignment of Early Works Contracts
If the Owner notifies the Contractor that a Deed of Novation cannot be executed in respect of an Early Works Contract, unless prohibited from so doing, the Owner or Anaconda Nickel NL, as the case may be (the `Assignor'), will irrevocably assign to the Contractor in accordance with this Clause the benefit of the Early Works Contract.
2.8 Contractor as agent if no assignment
(a) If the Assignor is unable to assign the benefit of any Early Works Contract pursuant to Clause 2.7, the Assignor hereby appoints the Contractor as its agent to perform and observe the Assignor's obligations under the Early Works Contract instead of the Assignor.
(b) If paragraph (a) applies the Assignor shall, at the request of the Contractor, do everything reasonably necessary (including the execution of documents) to assist the Contractor in commencing and prosecuting proceedings against an Early Works Contractor for a breach of an Early Works Contract, and in particular, shall:
(i) permit the Contractor to bring those proceedings in the name of the Assignor; and
(ii) provide the Contractor with reasonable evidence, information and assistance in relation to those proceedings,
provided that the Contractor shall:
(iii) keep the Assignor fully informed of the progress of, and consult with the Assignor in relation to, those proceedings;
(iv) not incur or admit any liability on the part of the Assignor in those proceedings without the prior consent of the Assignor; and
(v) indemnify the Assignor against all legal and other costs, losses, damages or claims incurred or suffered by the Assignor in respect of those proceedings, except to the extent to which the cost, loss, damage or claim is attributable to the negligent act or omission of the Assignor.
(c) The Contractor shall be entitled to any moneys recovered against an Early Works Contractor pursuant to this Clause 2.8.
2.9 Responsibility for work carried out by Early Works Contractors
(a) The Contractor assumes responsibility to the Owner from the Award Date for the proper performance of all the work carried out by each Early Works Contractor under an Early Works Contract prior to and following the Award Date.
(b) The Contractor:
(i) bears the risk of any Defects in the Facility which may arise (whether directly or indirectly) as a result of any work carried out by the Early Works Contractor; and
(ii) indemnifies the Owner against any liability which the Owner may have to an Early Works Contractor where an assignment occurs pursuant to Clause 2.7 or an appointment of agent occurs under Clause 2.8,
whether this work or liability occurred or arose prior to, or after, the date of execution of a Deed of Novation, or any assignment pursuant to Clause 2.7 or an appointment of an agent under Clause 2.8.
(c) The Contractor has no entitlement to any sums in addition to the Contract Price or to any extensions of time to any Date for Mechanical Completion or otherwise to make any Claim, solely because of the assumption by the Contractor of the obligations set out in paragraphs 2.9(a) and 2.9(b) and accepts the entire risk of the work to be performed under the Early Works Contract on the basis that it forms part of the Project Works.
(d) The Contractor shall require that each Early Works Contractor complies with its obligations under its Early Works Contract, provided that nothing contained in Clauses 2.7 and 2.8 shall require the Contractor to assume any greater obligation or liability pursuant to the terms of this Contract than the Early Works Contractor assumed to the Owner. However, nothing in this paragraph lessens or otherwise modifies the Contractor's obligation to pay liquidated damages pursuant to Clause 13.7.
6. DESIGN AND DOCUMENTATION 6.1 The Contractor's Design Obligation The Contractor: (a) acknowledges and warrants that:
(i) it prepared the documents which comprise the Revised Scope Book and that those documents are fit for the purpose of enabling the Contractor to carry out the Project Works in accordance with the Contract;
(ii) it prepared, or has checked and is satisfied with, the Drawings and specifications, and that they comply with the requirements of the Contract;
(iii) the design of the Facility will comply with the requirements of the Revised Scope Book and satisfy the requirements of the Contract; and
(iv) construction in accordance with the design of the Facility will satisfy the requirements of the Contract;
(b) except as provided in Clause 2.9(d), agrees that its obligations under, and the warranties given in, this Clause 6.1 will remain unaffected and that it will bear and continue to bear full liability and responsibility in accordance with this Contract for the performance of the Project Works notwithstanding:
(i) any design work carried out by the Contractor or by others prior to the date of this Contract and incorporated in this Contract; or
(ii) any review or approval of, or comments upon, such design by the Owner, or anyone on its behalf, prior to the Award Date.
6.2 Acknowledgement of Reliance
The Contractor acknowledges that the Owner:
(a) has relied on each of the acknowledgements, warranties and agreements given in Clause 6.1 in entering into the Contract; and
(b) would not have entered into the Contract but for those acknowledgements, warranties and agreements.
6.3 Review of Documentation
The Contractor and Owner acknowledge and agree that:
(a) the Contractor shall provide the Project Manager with copies of all Design Documents as they are produced. The Project Manager may review such documents. If the Project Manager concludes that any of the Design Documents does not comply with the requirements of the Contract, he may reject such documents. Upon such rejection the Contractor shall rectify the defect;
(b) the receipt and review by the Project Manager of any Design Documents submitted by the Contractor is solely for the purposes of administration of this Contract and monitoring the performance of the Contractor;
(c) the Project Manager does not accept any responsibility, or assume any duty of care, to the Contractor to review, or in reviewing, the Design Documents submitted by the Contractor for errors, omissions or compliance with the requirements of the Contract; and
(d) no comment upon, review or rejection of the use of, or any failure to review or comment upon, the Design Documents or any other Direction by the Project Manager about the Design Documents will:
(i) affect the Contractor's warranties in Clause 6.1 or otherwise relieve the Contractor from, or alter or affect the Contractor's liabilities or responsibilities under, the Contract or otherwise according to Law; or
(ii) prejudice the Owner's rights against the Contractor, whether under the Contract or otherwise according to Law.
6.4 Ownership of Design Documents
(a) The Owner owns, and the Contractor assigns to the Owner copyright, and all other intellectual property in:
(i) the Revised Scope Book; and
(ii) the Design Documents when each Design Document comes into existence,
provided that the Owner may only use the Design Documents for the operation and maintenance of the Facility and any other use shall be at the Owner's sole risk and without liability or legal exposure to the Contractor and the Owner shall indemnify and hold harmless the Contractor from all claims, losses, costs, damages and expenses (including attorney's fees on a solicitor client basis) arising out of or resulting therefrom.
(b) The Contractor has an irrevocable licence to use the Design Documents for:
(i) completion of the Project Works and performance of its obligations under the Contract; and
(ii) (omitting any specific project reference (including relevant title blocks)) any other project undertaken (either alone or in joint venture with another person).
6.5 Resolution of Ambiguities in Contract
If there is any ambiguity, discrepancy or inconsistency in the documents which make up the Contract or between the Contract and any Design Document which the Contractor is entitled to use for construction purposes under Clause 6.4:
(a) the order of precedence in the Contract Particulars will apply;
(b) where the ambiguity, discrepancy or inconsistency is between the Revised Scope Book and the Design Documents, the higher standard, quality or quantum will prevail but if this does not resolve it the Revised Scope Book will prevail;
(c) if the matter is not resolved by paragraphs (a) or (b) the true intent of the Revised Scope Book as determined by reference to the Revised Scope Book as a whole will be used to determine the requirements under the Contract;
(d) if it is discovered by the Contractor or the Project Manager, then the party discovering it must give notice to the other; and
(e) the Project Manager must instruct the Contractor as to the course it must adopt within 2 days of the notice under paragraph (d).
6.6 Intellectual Property Rights
The Contractor must ensure that the Project Works do not infringe any patent, registered design, trade mark or name, copyright or other protected right and the Owner must ensure that in respect of any process or part thereof, which the Owner provides, such process or part thereof does not infringe any patent, registered design, trade mark or name, copyright or other protected right.
The Contractor acknowledges that prior to the Award Date it has:
(a) ascertained the nature extent of the risks relating to the Project Works;
(b) visited and examined the Site and its surroundings and informed itself as to the Site conditions which may affect its performance of the Contract;
(c) informed itself as to the nature of the work and materials necessary for the execution of the Project Works and the means of access to and facilities at the Site and transport facilities for deliveries to or from the Site;
(d) informed itself of all requirements of the authorities in relation to the Project Works generally and, without limitation, in relation to measures necessary to protect the environment from any adverse effect or damage arising from execution of the Project Works; and
(e) reviewed and checked the Information Documents to the extent reasonably appropriate to agree the Contract Price and perform the works done to date and it is expressly agreed that such review and checking does not include a check or review of the test work carried out by Sherritt International Consultants Inc., and the resulting preliminary flow sheets process data and preliminary P&IDs.
7.2 Risk of Accuracy of Information and Site Conditions
Other than to the extent set out in Clause 7.3 the Contractor:
(a) is responsible for, and assumes the risk of, all increased costs and any damage, losses, expenses and liability it suffers or incurs arising out of, or in connection with, the Site conditions actually encountered at the Site during the execution of the Project Works or the accuracy of the information and design in the Information Documents;
(b) acknowledges and agrees that the Contract Price includes an amount to compensate the Contractor for all risk associated with the Site conditions or the information and design in all the Information Documents; and
(c) is not entitled to any extension of time to any Date for Mechanical Completion or any adjustment to the Contract Price or to make any other Claim against the Owner arising out of, or in connection with, any Site conditions or any inaccuracy in the information and design contained in the Information Documents.
(a) If the Contractor considers it has encountered or found a Latent Condition, it must immediately give the Project Manager notice in writing.
After receipt of a notice from the Contractor the Project Manager must:
(i) determine whether a Latent Condition has been encountered or found; and
(ii) within 3 days make a determination, and notify the parties of its determination.
(b) If a Latent Condition has been encountered, the Contractor will be entitled to:
(i) claim an extension of time to the Date for Mechanical Completion where it is entitled to do so under Clause 10.5; and
(ii) be paid by the Owner any extra costs incurred by the Contractor after the giving of a notice under this Clause arising from the Latent Condition, which will be determined by the Project Manager and added to the Contract Price.
The Contractor's entitlement under paragraph (b) will be its only right to payment of money arising from the Latent Condition.
(a) the only liability which the Owner may have for any information or design in the Information Documents is that which may arise pursuant to Clause 7.3(b);
(b) the Owner does not warrant, guarantee, make any representation or assume any duty of care in respect of the accuracy or adequacy of any information or data made available to the Contractor (including the Information Documents) prior to the Award Date;
(c) the Contractor acknowledges that such information or data (including the Information Documents) does not form part of the Contract and that Clause 18.8 applies to the information and data (including the Information Documents);
(d) to the extent permitted by Law, the Owner will not be liable upon any Claim by the Contractor arising out of or in connection with:
(i) the provision of, or the purported reliance upon, or use of, that information or data (including the Information Documents) by the Contractor or any other person to whom the information or data (including the Information Documents) is disclosed; or
(ii) a failure to provide any other information or data to the Contractor; and
(e) apart from any liability which may arise pursuant to Clause 7.3(b), the Contractor releases the Owner from any Claim for any costs, losses or damages suffered or incurred by the Contractor;
(iii) the provision of, or the purported reliance upon, or use of, the information or data (including the Information Documents) by the Contractor or any other person to whom the information or data (including the Information Documents) is disclosed.
(a) will, to the extent reasonably practical, provide the Contractor with sole, uninterrupted or continuous possession or access to the Site;
(b) may engage or allow Special Contractors and Other Contractors to work upon or in the vicinity of the Site or the Facility at the same time as the Contractor is performing the Project Works at the Facility; and
(c) will notify the Contractor in writing of the identity of the Other Contractors and details of the work they are to perform.
7.6 Contractor's to allow Owner Right of Access to the Site
(a) at all reasonable times give the Project Manager, the Owner and any person authorised by either the Project Manager or the Owner access to the Facility, the Site or any areas off-Site where Project Works are being performed; and
(b) provide the Owner and the Project Manager with every reasonable facility necessary for the supervision, examination and testing of the Project Works.
"7.10 Fluor invokes two substantive defences which apply potentially to all elements of the Facility currently under consideration. First, Fluor contends that the satisfactory operation of the Facility was conditional upon Fluor's being provided with a blended ore substantially the same as composite sample OC3. This contention is evaluated further below. Secondly, Fluor contends that Clause 2 of the EPC Contract had the effect of restricting Fluor's liability in respect of Early Works Contractors (`EWCs') and that the obligations created by Clauses 6, 7, 8 and 9 did not apply to work which was the subject of Early Works Contracts. These contentions will be dealt with immediately."
"7.11 By Clause 2.6 of the EPC Contract (set out in Section 4 above) the Contractor (Fluor) is required to execute a Deed of Novation in respect of each EWC. If the Owner notifies the Contractor that a Deed of Novation cannot be executed in respect of an EWC, the benefit of the Early Works Contract is to be irrecoverably assigned to the Contractor (Clause 2.7). If the benefit cannot be assigned, the Contractor is appointed as agent to perform the obligations of the Owner (Clause 2.8). Clause 2.9 then provides that:
(a) the Contractor assumes responsibility to the Owner for the proper performance of work carried out by each EWC;
(b) the Contractor bears the risk of any defects which may arise as a result of work carried out by the EWC;
(c) the Contractor accepts the entire risk of the work to be performed under the Early Works Contract on the basis that it forms part of the project works;
(d) the Contractor is to require each EWC to comply with its obligations.
The latter obligation is subject to the following proviso: `Provided that nothing contained in Clauses 2.7 (assignment of early works contract) and 2.8 ((contractor as agent if no assignment) shall require the contractor to assume any greater obligation or liability pursuant to the terms of this Contract than the Early Works Contractor assumed to the owner ... "
7.12 It is common ground between the Parties that none of the Early Works Contracts relevant to Areas 3100 and 3200 were novated; further, none of the remaining Early Works Contracts was assigned. The contentions raised by Fluor, therefore, apply to the whole of the issues currently under review. Anaconda submits that Clauses 2.6 to 2.9 were intended to ensure that Fluor becomes liable for the due performance of EWCs in the same way as sub-contractors appointed after the execution of the EPC Contract. Fluor retorts that, despite the clumsy drafting, the intention of the proviso to Clause 2.9(d) is that the Contractor is not to assume any greater obligation pursuant to the terms of the EPC Contract than the EWC assumes to the Owner. Accordingly, exclusion and limitation provisions in Early Works Contracts take effect to exclude or limit Fluor's liability under the EPC.
7.13 Fluor moreover argues that the warranties contained in Clause 6.1 of the EPC Contract relate only to the design work itself, and not the performance or capacity of the Facility; and that the warranties relate only to the facility designed and constructed by Fluor, not to the work of EWCs or to the design as modified by Anaconda. Fluor contends that by Clause 7.1(e), the Parties acknowledged that the limited review/check undertaken by Fluor did not include test work carried out by Sherrett, nor the Sherrett process package: Accordingly, Fluor did not warrant or assume responsibility for the Sherrett process or for performance of the Facility or of equipment, which was dependent upon the efficacy of the metallurgical process. Fluor contends that Clause 8 applies only to that part of the Facility which Fluor (as opposed to EWCs) was obliged to construct; and that the obligations placed on "the Contractor" by Clause 9 are not intended to include EWCs.
7.14 In its final submissions, Anaconda disputes all the foregoing contentions. In particular, Anaconda argues that:
(i) Clause 2.9(d) clearly applies only to Clauses 2.7 and 2.8 absent any plea for rectification of the contract;
(ii) the warranty contained in Clause 6.1(a) as qualified by Clause 6.1(b) expressly covers design work by others prior to the date of the contract;
(iii) Clause 7 is consistent with Fluor's design obligations, which cover the whole design, including the process design, subject to Clauses 7.1(e) and 7.3;
(iv) the language of Clause 8.1 is clear in creating an express obligation to construct the Facility in accordance, inter alia, with the Revised Scope Book;
(v) Clause 9.1 imposes an express obligation to perform the Project Works, including work performed under Early Works Contracts;
(vi) Clauses 8 and 9 expressly apply to the Project Works. Fluor's obligations under the EPC are not limited to those set out in Early Works Contract;
(vii) in any event, Anaconda's contentions are not concerned with performance under the Early Works Contracts but with Fluor's design obligations under the EPC Contract. .It is irrelevant that EWCs might not be liable for design under their Early Works Contracts.
7.15 Addressing first the arguments raised in relation to Clause 2 of the EPC Contract, the Arbitral Tribunal accepts that, in the absence of novation or assignment, Clause 2.9(a) and (d) renders the Contractor liable for any Defect in the Facility as those terms are defined in Clause 1 of the EPC Contract. The Arbitral Tribunal further accepts that the cumulative effect of Clauses 2, 6 and 8 of the EPC Contract is to require the Contractor to take on responsibility for delivery of the whole Facility, subject to the terms of the EPC Contract, irrespective of the existence of EWCs, and irrespective of any novation or assignment. The Arbitral Tribunal is unable to accept that Clause 2.9(d) limits the obligations of the Contractor to those contained in an EWC. The sub-clause must be construed as it stands. It is not otiose; it can be given effect in relation to Clauses 2.7 and 2.8, although these have no bearing on the present issues.
7.16 The primary obligations placed upon the Contractor as to the design and performance of the Facility are those contained in Clauses 6 and 8. Both Clauses 6.1 and 8.1 are somewhat repetitive and circular in their references to "the requirements of the contract." Both provisions, however, contain clear obligations, both as regards design and construction, to comply with the requirements of the Revised Scope Book. This must be taken to include, within the limits already discussed, the Process Design Criteria and the Mass Balance Rev. O. The obligations of the Contractor are, however, not unqualified. Clause 8.1(b) requires the Contractor to Construct the Facility in accordance with "any Design Documents which comply with the requirements of the Contract." Clause 6.3 provides for review of such documents by the Project Manager without relieving the Contractor of liabilities under the Contract. Clause 6.1(b) further provides (subject to Clause 2.9(d)) that the Contractor's obligations in relation to design will remain unaffected notwithstanding:
`(i) Any design work carried out by the Contractor or by others prior to the date of this Contract and incorporated in this Contract; or
(ii) Any review or approval of, or comments upon, such design by the Owner, or anyone on its behalf, prior to the Award Date.'
The words emphasised above show that the Contractor's responsibility for design of the Facility is to remain notwithstanding design work carried out prior to the EPC Contract by persons other than the Contractor. Further, any review or approval by the Owner or anyone on its behalf does not affect the Contractor's responsibility. What is not covered by these provisions is design by the Owner. The Contract is not to be construed, absent very clear words, as requiring the Contractor to take responsibility for design decisions insisted upon by the Owner itself.
7.17 As regards Clause 7 of the EPC Contract, the Arbitral Tribunal accepts that the Contractor's review and checking of Sherrett test work, data and drawings was subject to the limitation of Clause 7.1(e). Subject to this, the Arbitral Tribunal is satisfied that the design obligation undertaken by Fluor embraces the whole of the Facility, including the Process Design. The Arbitral Tribunal is, moreover, unable to construe the obligations as to quality set out in Clause 9 of the EPC Contract as excluding work carried out by EWCs. The cumulative effect of Clauses 2, 6, 7, 8 and 9 is to create an obligation upon the Contractor to design, construct and deliver a Facility complying with the Revised Scope Book with materials, where not otherwise specified, complying with Clause 9.1(a) and/or (b).
7.18 In sum, the Arbitral Tribunal does not accept Fluor's argument to the effect that its liability, if established, can be affected by the fact that relevant components of the work were undertaken by EWCs.
"Unless it is apparent to the judge, on a mere perusal of the reasoned award itself without the benefit of adversarial argument, that the meaning ascribed to the clause by the arbitrator is obviously wrong."[5]
"No doubt the arbitrator gave additional reasons in support of the conclusion at which he arrived, but he definitely decided that the notice to omit was not within the provisions of clause 13 of the contract because on a consideration of all the terms of the contract and the nature and extent of the work to be done under it he thought that the words of the clause should be read as excluding omissions the extent of which would render the remaining part of the work a fundamentally different undertaking from that originally covered by the contract. If this can be described as a principle of construction, it is not, in our opinion, erroneous as a rule to be applied, though its application in a particular case may be erroneous."[11]
"Addressing first the arguments raised in relation to Clause 2 of the EPC Contract, the Arbitral Tribunal accepts that in the absence of novation or assignment, Clause 2.9(a) and (d) renders the Contractor liable for any Defect in the Facility as those terms are defined in Clause 1 of the EPC Contract."
[9] Leighton Contractors Pty Ltd v Kilpatrick Green Pty Ltd [1992] VicRp 83; [1992] 2 VR 505; Qantas Airways Ltd v Joseland & Gilling [1986] 6 NSWLR 327; Pinaca Pty Ltd v Trinity Projects Pty Ltd (No. 2) (SC Tasmania, 19 December 1988, Underwood J).
[12] Qantas Airways Ltd v Joseland & Gilling) [1986] 6 NSWLR 327; Re Tiki Village International Ltd [1994] 2 Qd R 674.
[16] BC 900808, Supreme Court of South Australia, 11 November 1994, Debelle J, at 7.
[17] BC 9402554, Supreme Court of New South Wales, CA, 26 May 1994.
[19] Leighton Contractors Pty Ltd v South Australian Superannuation Trust Fund Investment Trust, supra, at 21.
Fluor Australia Pty Ltd
Anaconda Operations Pty Ltd [2003] VSC 276
(1956) 95 CLR 420
(1985) 60 ALJR 1
(1927) 39 CLR 570
(1968) 41 ALJR 307