(i) it prepared the documents which comprise the Revised Scope Book and that those documents are fit for the purpose of enabling the Contractor to carry out the Project Works in accordance with the Contract;
(ii) it prepared, or has checked and is satisfied with, the Drawings and specifications, and that they comply with the requirements of the Contract;
(iii) the design of the Facility will comply with the requirements of the Revised Scope Book and satisfy the requirements of the Contract; and
(iv) construction in accordance with the design of the Facility will satisfy the requirements of the Contract;
(b) except as provided in Clause 2.9(d), agrees that its obligations under, and the warranties given in, this Clause 6.1 will remain unaffected and that it will bear and continue to bear full liability and responsibility in accordance with this Contract for the performance of the Project Works notwithstanding:
(i) any design work carried out by the Contractor or by others prior to the date of this Contract and incorporated in this Contract; or
(ii) any review or approval of, or comments upon, such design by the Owner, or anyone on its behalf, prior to the Award Date.
6.2 Acknowledgement of Reliance
The Contractor acknowledges that the Owner:
(a) has relied on each of the acknowledgements, warranties and agreements given in Clause 6.1 in entering into the Contract; and
(b) would not have entered into the Contract but for those acknowledgements, warranties and agreements.
6.3 Review of Documentation
The Contractor and Owner acknowledge and agree that:
(a) the Contractor shall provide the Project Manager with copies of all Design Documents as they are produced. The Project Manager may review such documents. If the Project Manager concludes that any of the Design Documents does not comply with the requirements of the Contract, he may reject such documents. Upon such rejection the Contractor shall rectify the defect;
(b) the receipt and review by the Project Manager of any Design Documents submitted by the Contractor is solely for the purposes of administration of this Contract and monitoring the performance of the Contractor;
(c) the Project Manager does not accept any responsibility, or assume any duty of care, to the Contractor to review, or in reviewing, the Design Documents submitted by the Contractor for errors, omissions or compliance with the requirements of the Contract; and
(d) no comment upon, review or rejection of the use of, or any failure to review or comment upon, the Design Documents or any other Direction by the Project Manager about the Design Documents will:
(i) affect the Contractor's warranties in Clause 6.1 or otherwise relieve the Contractor from, or alter or affect the Contractor's liabilities or responsibilities under, the Contract or otherwise according to Law; or
(ii) prejudice the Owner's rights against the Contractor, whether under the Contract or otherwise according to Law.
6.4 Ownership of Design Documents
(a) The Owner owns, and the Contractor assigns to the Owner copyright, and all other intellectual property in:
(i) the Revised Scope Book; and
(ii) the Design Documents when each Design Document comes into existence,
provided that the Owner may only use the Design Documents for the operation and maintenance of the Facility and any other use shall be at the Owner's sole risk and without liability or legal exposure to the Contractor and the Owner shall indemnify and hold harmless the Contractor from all claims, losses, costs, damages and expenses (including attorney's fees on a solicitor client basis) arising out of or resulting therefrom.
(b) The Contractor has an irrevocable licence to use the Design Documents for:
(i) completion of the Project Works and performance of its obligations under the Contract; and
(ii) (omitting any specific project reference (including relevant title blocks)) any other project undertaken (either alone or in joint venture with another person).
6.5 Resolution of Ambiguities in Contract
If there is any ambiguity, discrepancy or inconsistency in the documents which make up the Contract or between the Contract and any Design Document which the Contractor is entitled to use for construction purposes under Clause 6.4:
(a) the order of precedence in the Contract Particulars will apply;
(b) where the ambiguity, discrepancy or inconsistency is between the Revised Scope Book and the Design Documents, the higher standard, quality or quantum will prevail but if this does not resolve it the Revised Scope Book will prevail;
(c) if the matter is not resolved by paragraphs (a) or (b) the true intent of the Revised Scope Book as determined by reference to the Revised Scope Book as a whole will be used to determine the requirements under the Contract;
(d) if it is discovered by the Contractor or the Project Manager, then the party discovering it must give notice to the other; and
(e) the Project Manager must instruct the Contractor as to the course it must adopt within 2 days of the notice under paragraph (d).
6.6 Intellectual Property Rights
The Contractor must ensure that the Project Works do not infringe any patent, registered design, trade mark or name, copyright or other protected right and the Owner must ensure that in respect of any process or part thereof, which the Owner provides, such process or part thereof does not infringe any patent, registered design, trade mark or name, copyright or other protected right.