10 The Association takes issue with some elements of this. It says that the amount due under the contract for work performed is $222,113, compared with $225,571.50 (or $230,406.50 including variations) in D S Flora's calculation. The slightly smaller figure comes from a report by Mr Fransen, an expert witness. The Association says that the amount of progress payments made is $75,000, not $75,500.
11 In final submissions, both the Association and D S Flora accepted a figure of $222,113 less $75,000 already paid (that is, net $147,113) as the appropriate basis on which to calculate the sum unpaid under the contract.
12 As to the remaining element, I accept the submissions made on behalf of D S Flora that his invoiced amounts for expenses after cessation of work should be taken into account in the assessment of damages, those amounts not having been challenged as to their accuracy. The aggregate of those amounts is $40,700.60 to which should be added $30.00 for cheque dishonour fees, making $46,730.60.
13 The damages sum is accordingly $187,843.60, disregarding interest.
14 In relation to interest, allowance should be made for interest on $147,113.00 at the clause 6(c) rate since 30 April 2005; and there should be interest on the $40,700.60 component at court rates from the mid-point mentioned in D S Flora's submissions (1 September 2005).
15 It will be necessary for precise calculations to be made and embodied in short minutes.
16 It remains to deal Budget's claim against D S Flora. There is no dispute in relation to that. D S Flora accepts liability quantified as follows in submissions: