4.47 Development that is integrated development
(1) This section applies to the determination of a development application for development that is integrated development.
(2) Before granting development consent to an application for consent to carry out the development, the consent authority must, in accordance with the regulations, obtain from each relevant approval body the general terms of any approval proposed to be granted by the approval body in relation to the development. Nothing in this section requires the consent authority to obtain the general terms of any such approval if the consent authority determines to refuse to grant development consent.
(3) A consent granted by the consent authority must be consistent with the general terms of any approval proposed to be granted by the approval body in relation to the development and of which the consent authority is informed. For the purposes of this Part, the consent authority is taken to have power under this Act to impose any condition that the approval body could impose as a condition of its approval.
(4) If the approval body informs the consent authority that it will not grant an approval that is required in order for the development to be lawfully carried out, the consent authority must refuse consent to the application.
...
4.50 Granting and modification of approval by approval body
(1) Despite any other Act or law, an approval body must, in respect of integrated development for which development consent has been granted following the provision by the approval body of the general terms of the approval proposed to be granted by the approval body in relation to the development, grant approval to any application for approval that is made within 3 years after the date on which the development consent is granted if, within that 3-year period, the development consent has not lapsed or been revoked.
(2) The approval may be granted subject to conditions that are not inconsistent with the development consent. Neither the provisions of section 4.17(6)-(10) nor the imposition of conditions as to security by the consent authority prevent an approval body from imposing conditions, or additional conditions, as to security.
(3) Subsection (1) does not apply to or limit the granting of approval to an application for renewal of an approval.
(4) An approval body cannot vary the terms of an approval granted for integrated development for which development consent has been granted before the expiration, lapsing or first renewal of the approval, whichever first occurs, other than to make variations that are not inconsistent with the development consent.
…
Division 8.3 Appeals - development consents
…
8.14 Powers of Court on appeals
…
(4) If an appeal under this Division relates to integrated development -
(a) the Court may determine the appeal whether or not the consent authority has obtained general terms of approval from each relevant approval body, and
(b) the Court is not bound to refuse an application for development consent because a relevant approval body has decided that general terms of approval will not be determined or has decided not to grant a relevant approval, and
(c) the Court may determine an appeal even though a development consent granted as a result of the appeal is inconsistent with the general terms of approval of a relevant approval body.
8.15 Miscellaneous provisions relating to appeals under this Division
…
(2) On an appeal under this Division, the Court may, at any time on the application of a person or of its own motion, order the joinder of a person as a party to the appeal if the Court is of the opinion -
(a) that the person is able to raise an issue that should be considered in relation to the appeal but would not be likely to be sufficiently addressed if the person were not joined as a party, or
(b) that -
(i) it is in the interests of justice, or
(ii) it is in the public interest,
that the person be joined as a party to the appeal.