© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2017] NSWLEC 152
Land and Environment Court (NSW)
2017-11-01
Pain J
Original judgment source is linked above.
SOLICITORS: Department of Environment Climate Change & Water (Prosecutor) Allens (Defendant) File Number(s): 16/376075; 16/376087
Judgment
Summons - matter no 16/376075 pollute waters The Prosecutor claims: 1 An order that the Defendant, Wambo Coal Pty Limited ACN 000 668 057, having its registered office at 100 Melbourne Street, South Brisbane, Queensland 4101, appear before a Judge of the Court to answer the charge that, between about 5 January 2016 and about 11 January 2016 inclusive, at or near the Wambo Mine, Jerry's Plains Road, Warkworth in the State of New South Wales (the Licensed Premises), it committed an offence against section 120(1) of the Protection of the Environment Operations Act 1997 in that it polluted waters. Particulars (a) Waters: The ephemeral drainage line leading to Waterfall Creek. (b) Pollutant: Sediment from a wall of the Montrose sediment dam (the Dam) and sediment laden water which was being stored in the Dam before the breach of the Dam wall, being soil, earth, mud, stones, sand, clay or similar inorganic matter. (c) Manner of breach: The Defendant was the occupier of the Licensed Premises, at which the Pollutant was introduced into the Waters from the Dam when the Dam wall failed. The Defendant had failed to ensure the Dam was adequately constructed for its purpose, leading to the collapse of the Dam wall, and: (i) the introduction into Waters of the Pollutant; and/or (ii) placing the Pollutant in a position where it is likely to fall, descend or be washed into the Waters or the dry bed of the Waters. 2 That the Defendant be dealt with according to law for the commission of the above offence. 3 An order that the defendant pay the prosecutor's costs. 4 Such orders pursuant to Part 8.3 of the Protection of the Environment Operations Act 1997 as the Court in its discretion sees fit to make.
Amended summons - matter no 16/376087 breach of licence condition The Prosecutor claims: 1. An order that the Defendant, Wambo Coal Pty Limited ACN 000 668 057, having its registered office at 100 Melbourne Street, South Brisbane, Queensland 4101, appear before a Judge of the Court to answer the charge that between about 28 November 2015 and 11 January 2016, at or near the Wambo Mine, Jerry's Plains Road, at Warkworth in the State of New South Wales (the Licensed Premises), it committed an offence against section 64(1) of the Protection of the Environment Operations Act 1997 in that it was the holder of [a - sic] licence, a condition of which was contravened by a person. Particulars a. Licence Environment Protection Licence Number 529. b. Licence condition contravened Condition 01.1, which states: "Licensed activities must be carried out in a competent manner. This includes: (a) The processing, handling, movement and storage of materials and substances used to carry out the activity, and (b) The treatment, storage, processing, reprocessing, transport and disposal of waste generated by the activity." c. Manner of breach The Defendant failed to carry out its licensed activities at the Licensed Premises in a competent manner, in that it: i. caused the spillway on the Montrose sediment dam (the Dam) to be constructed and/or modified in a manner such that it had insufficient capacity; ii. failed to ensure the Dam was constructed in a manner which was suitable and/or adequate for the soil type used; and/or iii. otherwise failed to ensure the Dam was fit for purpose. As a consequence, the dam wall collapsed, leading to sediment from the dam wall and the waters in the dam being deposited in the ephemeral drainage line leading to Waterfall Creek. 2. An order that the Defendant be dealt with according to law for the commission of the above offence. 3. Such orders pursuant to section 8.3 of the Protection of the Environment Operations Act 1997 as the Court in its discretion see fit to make. 4. An order that the Defendant pay the Prosecutor's costs.
Protection of the Environment Operations Act 1997
Evidence
Statement of agreed facts The Defendant 1) Wambo Coal Pty Limited (ACN 000 668 057) (Wambo) operates an open cut and underground coal mine located at Wambo Mine, Jerry's Plains Road, Warkworth, New South Wales (the Premises). 2) Wambo has operated a combined surface and underground mine in the upper Hunter Valley since 1969. 3) Wambo is an indirect subsidiary of Peabody Energy Australia Pty Ltd (Peabody). Peabody is the sole shareholder of Peabody Australia Mining Pty Ltd (ACN 002 818 699) (Peabody Mining), which in turn owns all of the ordinary shares in Wambo. The Licensed Activities 4) Wambo is the holder of Environment Protection Licence Number 529 in relation to the Premises (the Licence). A copy of the Licence is at Annexure A. 5) Wambo is the occupier of the Premises, the operator of the mine and carries out activities relating to the mining, processing and handling of coal at the Premises. At all relevant times, Wambo was carrying out activities at the Premises under the Licence. 6) At all relevant times, Wambo was authorised to undertake mining activities in accordance with the Development Consent dated 4 February 2004 (DA305-7-2003) (as modified) and the Development Consent dated 16 December 2004 (DA177-8-2004) (the Development Consents), the Licence and the mining tenements. 7) In accordance with the Development Consents, Wambo was required to prepare a site water management plan for the operation of mining activities at the Premises. A component of this site water management plan was an Erosion and Sediment Control Plan (the Premises ESCP) for the Premises. 8) The Premises ESCP was prepared by Wambo and approved by the Department of Planning and Environment on 27 November 2015. 9) The Premises ESCP was in place at all relevant times, and forms part of Wambo's environmental management system. 10) In order to allow the preparation of the ground surface (mulching vegetation and minor earthworks) prior to commencing open cut mining for the Montrose Pit, SLR Consulting Australia Pty Ltd (SLR) was engaged by Wambo to prepare an erosion and sediment control plan for the Montrose Pit to manage sediment laden runoff from the proposed stripping area, and to include a conceptual design of sediment control structures (the Montrose Pit ESCP). 11) On 19 August 2015, SLR provided the Montrose Pit ESCP to Wambo. The Montrose Pit ESCP noted that the pre-strip disturbance area is located on a generally steep slope, with a significant catchment area upslope and to the west of the proposed pre-strip disturbance area. 12) The Montrose Pit ESCP included a conceptual design for a sediment dam, the Montrose Sediment Dam (the Dam) (the Concept Design). The Concept Design included sizing of the Dam and spillway. A copy of the Montrose Pit ESCP, including the Concept Design is at Annexure B. 13) The Montrose Pit ESCP also noted that, as the pre-strip disturbance area would be mined in the near future and the proposed sediment dam capacity calculations incorporate high erosion potential, no temporary erosion controls were recommended on the pre-strip disturbance area. However, the Montrose Pit ESCP did recommend that stripping of the pre-site disturbance area be staged and be undertaken as close to the commencement of mining as possible. 14) In accordance with the Licence and the Development Consents, Wambo had approval to progress mining through the disturbance area surrounding the Dam in 2016, including the approximately 1.3km length of Waterfall Creek and its tributary downstream of the Dam. The extent of approved mining operations in 2016 is at Annexure C. The design of the Dam and spillway 15) The sizing of the Dam in the Concept Design was determined in accordance with the requirements of the Managing Urban Stormwater: Soils and Construction Vol. 1, 4th edition and Vol. 2E Mines and Quarries (Landcom, 2004 and DECC, 2008) (the Blue Book Guidelines). The sizing of the spillway was in accordance with the Best Practice Erosion & Sediment Control, Book 2 (IECA, 2008). 16) The Concept Design provided for a sediment dam sized for a 5 day, 80th percentile rainfall depth of 24.4 mm, with an average spill frequency of 6 times per year. The total minimum volume required for the sediment dam under the concept plan was 2.83 ML. 17) The Concept Design also provided for a spillway sized for a 100 year Average Recurrence Interval rainfall event, with a minimum base width of 4 m, water depth of 0.7 m and depth including the freeboard of 1 m. 18) SLR noted, in the Montrose Pit ESCP, that its scope of work involved the conceptual design of sediment control structures as required for the disturbance layout. SLR recommended that all new sediment dams should be the subject of further detailed investigation including geotechnical assessment and detailed design prior to construction. 19) The Concept Design included a conceptual pump line location and SLR noted that pump and pipeline systems would need to be determined, to enable the dams to be regularly drawn down following rainfall (within 5 days), in accordance with the Blue Book Guidelines, to minimise the chances of an uncontrolled discharge. 20) Between about 19 August 2015 and 28 November 2015, further detailed investigation and design was undertaken by Wambo's technical services team. Wambo engineering and survey personnel undertook the following further detailed investigation and design: a. An aerial survey of the catchment area; b. Development of a Location Plan and General Arrangement for the Dam and contour drains; c. Development of a Set Out Plan; d. Development of a Cross Section; e. Development of Construction Notes for the Dam and contour drains, including: i. Gradients; ii. Batter angles; iii. Cut and fill balance; and f. In-field Survey Set Out. A copy of the Set Out Plan and Cross Section are at Annexure D. The construction of the Dam 21) The Dam was constructed within an area of predominantly undisturbed grazing land in preparation for future open cut mining disturbance. At the time of the incident, approximately 25% of the Dam catchment was disturbed, limited primarily to mulching of existing vegetation, with mulch being retained in these areas to provide additional protection against runoff and rainfall impact. 22) Wambo contracted Shearer Contracting Pty Limited (the Contractor) to provide a bulldozer and operator to construct the Dam, on instruction from employees acting for Wambo. 23) The design and operation of the Dam was undertaken by a number of Wambo's employees, and contractors, including Mark Mills (Open Cut Technical Services Superintendent), Matthew Remington (surveyor), Peter Kane (Production Superintendent), Harry Egan (Environmental Adviser), Peter Jaeger (Senior Environmental Adviser), and Steven Peart (Environment and Community Manager). At all relevant times, these personnel were acting on behalf of Wambo with respect.to the design and operation of the Dam. 24) The Contractor carried out all construction works and Wambo's employees carried out surveying activities throughout the construction process. At all relevant times, the Contractor was acting on instruction of Wambo's employees during the construction of the Dam. 25) There was no formal commissioning or approval process prior to the construction of the Dam. The Darm was a temporary structure and the disturbance area was to be mined through during 2016 (i.e. within 1 year). Once mining commenced, all runoff from the Dam's catchment would be directed to the mine pit. 26) Between approximately 18 and 28 November 2015, the Dam was constructed using local soils compacted by a D6 bulldozer, as follows: a. The outline of the Dam, and the cut-and-fill areas, were pegged out by surveying using GPS from the 3D image produced by the Technical Services Team. b. The in-field survey set out of the Dam was completed on 18 November 2015. 29) As a result, the Dam as constructed departed from both the Concept Design and the detailed design prepared by Wambo. 30) Following the completion of construction of the Dam, Wambo did not undertake any verification that the Dam had been constructed in accordance with the design. Wambo did not undertake formal commissioning or approval for a structure such as the Dam and as such no engineering assessment of the Dam was carried out post-construction. Operation of the Dam 31) At the time of the incident, the total catchment area for the Dam was approximately 27.8 ha, comprising: a. Approximately 6.8 ha disturbed area (having topsoil and vegetative mulch either removed or exhibiting a high level of disturbance), primarily from mulching of existing vegetation, contributing to sediment-laden runoff; and b. Approximately 21 ha undisturbed area (including areas of existing vegetation and areas where a significant cover of vegetative mulch remained), contributing to clean-water runoff. 32) The Blue Book Guidelines provide that a sediment control structure such as the Dam should be drawn down, or dewatered, using a pump and pipeline system, generally within 5 days of completion of a rainfall event if the nominated water quality targets can be met. However, the number of days that the dewatering should be conducted within, following the completion of a rainfall event, is dependent upon site conditions. 33) Prior to the incident, Wambo did not install a permanent pump and pipeline system for the purposes of dewatering the Dam. However, Wambo maintains a trailer mounted, mobile Sykes High Head 100 pump capable of pumping water for dewatering purposes following a rainfall event (the Pump System). 34) A significant rainfall event occurred at the Premises between 3 January 2016 and 6 January 2016. Wambo did not mobilise the Pump System, or, any other pump and pipeline system, to dewater the Dam during or following the rainfall event. Pre-lncident Inspections and monitoring of the Dam 35) The Premises ESCP that applied at the time of the incident provided, in relation to inspections, monitoring and maintenance: "Sediment control structures will be inspected on a monthly basis, or following rainfall events ≥ 20 mm/day* (midnight to midnight), as recorded by the Wambo Meteorological Station. If no rain is received for at least a 24 hour period, any subsequent rain event ≥ 20 mm/day will trigger a new inspection. The sediment control structures will be inspected for capacity, structural integrity and effectiveness by Wambo's Environmental Personnel." 36) Following the completion of the construction of the Dam on 28 November 2015, further inspections of the Dam were carried out by Mr Jaeger in mid-December, and by Mr Remington on 22 December 2015 (following a rainfall event). Mr Remington considered that on 22 December 2015 the Dam appeared to be working. The Incident 37) Between 3 and 6 January 2016, there was significant rainfall at the Premises, leading to significant regional flash and riverine flooding (the Storm Event). The rainfall recorded for the 71 hours from 3 January to 6 January 2016 was 118.6 mm. According to Bureau of Meteorology records for the Cessnock weather station, located approximately 39km from the Premises, 6 January 2016 recorded the highest amount of rain in a single day in January, since records began. 38) The following rainfall data was recorded at the Premises by the Wambo Meteorological Station between 3 and 6 January 2016 (midnight to midnight): Date Rainfall (mm) 3 January 3.6 4 January 13.8 5 January 76.8 6 January 24.4 Total 118.6
Affidavit of Mr Baker
Affidavit of Mr Peart
Purposes of sentencing
Objective seriousness of offences
Extent of harm caused or likely to be caused to the environment by the commission of the offence (s 241(1)(a))
Practical measures that may have been taken to prevent, control, abate or mitigate that harm (s 241(1)(b))
Extent to which the person who committed the offence could reasonably have foreseen the harm caused or likely to be caused by the offence (s 241(1)(c))
The extent to which the person who committed the offence had control over the causes that gave rise to the event (s 241(1)(d))
Whether, in committing the offence, the person was complying with orders from an employer or supervising employee (s 241(1)(e))
Maximum penalties
Reasons for committing the offences
Conclusion on objective seriousness
Prior record and good character of defendant (ss 21A(3)(e)-(f))
Discount for early guilty pleas (ss 21A(3)(k), 22)
Remorse and contrition (s 21A(3)(i))
Assistance to authorities (ss 21A(3)(m), 23)
General deterrence
Specific deterrence
Retribution and denunciation under the CSP Act
Totality principle
Even-handedness
Penalty in matter no 16/376087
Penalty in matter no 16/376075
Additional orders
Costs
Orders
ANNEXURE A
WAMBO COAL PTY LIMITED CONVICTED AND FINED $62,000 FOR DAM FAILURE AT WARKWORTH Wambo Coal Pty Limited ("Wambo Coal") has been convicted and fined $62,000 by the Land and Environment Court of New South Wales for two offences under the Protection of the Environment Operations Act 1997. Wambo Coal was prosecuted by the Environment Protection Authority (EPA) and pleaded guilty to one offence of water pollution and one offence of contravening its Environment Protection Licence by failing to carry out its licensed activities in a competent manner. The conviction related to an incident occurring at the Wambo Mine premises in Warkworth in January 2016 when a sediment dam built to retain rainfall and runoff from disturbed soil failed following heavy rainfall. Between about 5 and 11 January 2016, a section of the dam wall collapsed, resulting in material from the failed section of the dam wall and approximately 2.5 ML of sediment-laden waters being released. The sediment-laden waters flowed along an ephemeral drainage line to Waterfall Creek. No visible sediment deposition was observed outside of the boundary of the mine site. Any impact from the incident would have been temporary. Following completion of construction of the dam in late November 2015, Wambo Coal did not carry out an engineering assessment to verify that the dam had been constructed to design. Whilst the precise cause of the failure of the dam was unable to be determined conclusively, contributing factors include that the spillway capacity was insufficient due to a decision to place rock armouring in the spillway. Additionally, the construction methods used were deficient in several respects for the type of soil used and for the intended purpose of the dam. On 20 November 2017, Wambo Coal was convicted and ordered by the Land and Environment Court to:
Amendments 29 November 2017 - Annexure A - typographical errors in the heading and second paragraph of the annexure. DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 29 November 2017
Environment Protection Authority
Wambo Coal Pty Ltd
[1988] HCA 70
(2006) 145 LGERA 234
(1993) 32 NSWLR 683
(2009) 168 LGERA 121
(2001) 115 LGERA 391
(2006) 148 LGERA 299
(2010) 242 CLR 520
(1989) 167 CLR 348
(1999) 199 CLR 270
(2000) 49 NSWLR 383
(1993) 78 LGERA 349
(1988) 166 CLR 59
(1997) 189 CLR 295
(1988) 194 CLR 610