Environment Protection Authority v Truegain Pty Limited
[2003] NSWLEC 277
At a glance
Source factsCourt
Land and Environment Court (NSW)
Decision date
2003-11-19
Before
Talbot J
Source
Original judgment source is linked above.
Judgment (12 paragraphs)
Introduction The Offence 1 The defendant pleads guilty to the charge that on 17 December 2001 it polluted waters being a drain that runs along the eastern boundary of its premises at 62 Kyle Street, Rutherford ("the premises"). The original allegation that waters downstream were polluted has not been pursued. 2 The defendant carries on a business at the premises of receiving, storing and processing waste oils and oily water emulsions. The defendant refines and re-processes these products into re-usable petroleum-based products. 3 A wastewater treatment plant is located within a bunded area at the eastern side of the premises. The subject bund is constructed of four concrete walls and at the time of the incident the floor of the bund comprised two concrete slabs. The main slab was 150mm thick and the second slab, or apron slab, was 100mm thick. The two floor slabs were joined by an epoxy expansion joint, traversing the floor of the bund. 4 A concrete-lined stormwater drain runs along the eastern boundary of the premises ("the stormwater drain"). The stormwater drain is about two metres deep and is located down a steep embankment from the subject bund. The floor of the stormwater drain is about five metres down the embankment from the boundary of the premises and the subject bund. 5 On 17 December 2001 liquid escaped from the subject bund through a separation in the epoxy expansion joint between the two concrete floor slabs and some liquid entered the stormwater drain. 6 It is an agreed fact that the separation in the epoxy expansion joint was caused by a weak area of sub-material under the floor of the subject bund. The weak area under the subject bund caused the 100mm apron slab to sink and fall towards the stormwater drain by approximately 25mm. The movement of the 100mm apron slab caused the epoxy expansion joint between the two slabs to open, breaking the integrity of the subject bund. 7 There is a factual dispute as to whether the company failed to respond to a complaint raised by an adjoining owner and the Environment Protection Authority ("the EPA") on 14 December 2001. Nevertheless, it is clear from the evidence and not disputed that the defendant shut down the plant on 17 December 2001, promptly provided a report to the EPA, removed contaminated soil, water and vegetation from the drain under the subject bund and within two weeks commenced construction of new bunds onto the main concrete slab. 8 Since the incident the defendant has taken the following steps:-