The Defendant's Evidence
54 Mr Kneebone is the General Manager of GWS. His description of the process of disposing wastewater generated by the wool scouring process is consistent with the explanation given by Miss Wakenshaw, to the extent of applying it to two geographically separated spray irrigation areas known as the Goulburn Irrigation Area and the Yarra Irrigation Area.
55 Mr Kneebone explained that the original system at Goulburn was constructed in or about 1982 and comprised two small run-off collection ponds with a design capacity to cope with 10mm of rain from the catchment.
56 After a meeting with State Pollution Control Commission Officer, Maurie Matthews, and representatives of GWS in November 1989 changes were proposed to the Goulburn licence whereby following collection of the initial run-off any further run-off should bypass the collection dams and not flush the collected wastes to waters. He explained this could be achieved by closing the valve on the pipe from the contour bank that collects all run-off from the irrigation field and channels into the run-off collection dam. Mr Kneebone was satisfied with the approach recommended by Mr Matthews as it was consistent with the design of the system, namely that there would be a capture of the first flush of 10mm of rain and then a discharge of stormwater run-off off-site. The Goulburn licence for 1990-1991 was granted on 1 June 1990. This licence included a number of new conditions as follows:-
s A definition of "dry weather conditions" to mean less than 10 mm of rain falling within a 24 hour period.
s Condition W2 which provided that "Under dry weather conditions, there shall be no discharge of effluent to any watercourse or to any other area than the defined irrigation area."
s Condition W5 which provided that "Stormwater runoff shall be diverted from the irrigation area".
57 Mr Kneebone says he understood that the practical operation of the system was that there be no discharge from the Goulburn area unless more than 10mm of rain had fallen within 24 hours. That discharge was only to consist of stormwater run-off from within the irrigation areas.
58 In 1991 GWS commissioned Dr John McCracken to prepare a Review of Environmental Factors relating to a proposed expansion of the production area and the use of Yarra. In December 1991 Warren and Associates were instructed to prepare an Environmental Impact Statement ("EIS") in respect of the proposal to develop Yarra. A copy of the EIS was delivered to the EPA. The EPA responded by advising GWS that it would envisage issuing approval for a second wool scour with conditions attached to the approval relating to the wastewater irrigation area. These conditions would include a condition that there should be no discharge from the irrigation area to waters except following specified rainfall events.
59 Following the determination of the development application made to Mulwaree Shire Council by consent, construction of Yarra commenced in early November 1992 and was completed in or about December 1992.
60 On 27 June 1997, after a major storm event, stormwater flowed off the Yarra site.
61 Between August 1997 and August 1998 two emergency storage dams were designed, approved by the EPA and constructed on the ridge of the Yarra area. Increased storage in respect of RCD1, RCD2 and RCD3 was designed, approved and constructed. In a letter to the prosecutor on 2 October 1997 GWS undertook to construct an increase in freeboard on storage dams to add a significant safety margin. A geotechnical consultant advised that the dams would remain in their safety limits with the increase in storage capacity.
62 In response to an emergency situation that occurred in August 1998 when the RCDs became full at Yarra Mr Kneebone suggested to Mr Wearne that GWS should install the same system at Yarra that was in place at Goulburn, namely to divert stormwater runoff around the RCD, not through them. A proposal to that effect prepared by Dr McCracken was submitted to the EPA on 18 August 1998.
63 The proposal was to construct a stormwater run-off diversion similar to that practiced at the Goulburn site on the basis that most of the contaminants would be expected to have been flushed from the surface of the irrigation sites into the catchment dams so that further stormwater run-off would be suitable for discharge from the site. It was put by Dr McCracken that it can be reasonably argued that the environmental impact from any contaminant that may be flushed from the site in the surface run-off to the receiving waters will be minimal because of the very considerable dilution that occurs from extreme periods of rainfall. Mr Wearne responded to the proposal by telephoning Mr Kneebone with words to the following effect:-
"I authorise GWS to go ahead with the works".
64 Mr Wearne confirmed in a file note dated 21 August 1998 that he had advised Mr Kneebone to begin constructing an earth contour diversion bank to prevent catchment water entering FFD3 at Yarra to prevent over topping.
65 It is Mr Kneebone's evidence that the works included the installation of a valve, 150mm inflow pipe and a diversion bank as installed and operating at Goulburn. Mr Kneebone explains that the system was designed so that the design capacity of the inflow to the pipes installed was such as to handle a run-off of greater than 23mm over approximately 24 hours. His observations at the time were that it would take approximately 23mm of rain in a 24-hour period before any stormwater discharged off the site. The construction was completed on 27 August 1998 and the company diverted stormwater run-off off site. From then on the system at Yarra replicated the system in place at Goulburn since 1989.
66 The notes of a site meeting on 24 September 1998 between representatives of the EPA, GWS and the neighbour, Mr Gibson, report that continuing environmental improvement programs include contours being constructed at the Yarra site to divert stormwater run-off. It was agreed at that meeting, inter alia, that early warning of any discharge or possible discharge from the site would be given. It was also agreed that work at the Yarra site progress to achieve a zero discharge.
67 A further major storm event occurred on 5 February 2001. Mr Kneebone observed that during the rain event stormwater run-off was diverting away from the RCDs, after the first flush had been collected therein in accordance with the design adopted in 1998. Mr Kneebone expressly notes that the EPA did not commence any legal proceedings against GWS as a consequence of the diversion of stormwater off-site that occurred following the 5 February 2001 storm event.
68 At a meeting on 31 May 2001 Miss Wakenshaw, Mr Parker and Mr Kneebone reviewed a SCA report recommending that 15mm be collected and returned back to the system. Miss Wakenshaw spoke to Miss Stein about the proposal and advised her that the EPA has "always intended the site to be zero discharge site". Moreover, that the EPA may not approve a certain design storm as it believes the site to be zero discharge. Mr Kneebone has told the Court that works necessary to guarantee the first flush system at Yarra would collect a minimum of 15mm of stormwater run-off were completed by July 2001. Small contours were installed in front of the stock water dam directly below RCD3 and RCD2 to improve the environmental performance of the system by ensuring that at least 15mm of water was collected, retained and then returned back to the site. After that work was carried out there was, according to Mr Kneebone, a capacity to hold 70mm of a rain event on the site, an increase from 23mm before the work was completed.
69 In his affidavit Mr Kneebone says that when the rainfall events commenced on or about 3 February 2002 it took about 70mm of rain before discharge of stormwater from the site took place. He further says that the stormwater that was being discharged was after collecting about the first 70mm in the run-off collection dams, the FFDs and the irrigation fields. In his opinion, the discharge that occurred on or about 5 February 2002 occurred strictly in accordance with the design of the system. In his view, the manner of the discharge was "100% predictable". It is his contention that the EPA licence operating on 5 February 2002 was a licence granted in respect of a system that was in place and had been designed in collaboration with the EPA.
70 Mr Kneebone relies upon the fact that during the period from 18 August 1998 until 5 February 2002 the company had made known to the EPA the inevitability of stormwater discharge occurring off site as a consequence of the operation of the irrigation system. A close reading of the letter from the company to the EPA dated 18 August 1998 and the proposal by Dr McCracken of the same date shows that this was certainly the case at that date. Even the expectation expressed by Miss Wakenshaw in her note of the meeting on 31 May 2001 recognises this prospect as against the intention for the site to be a zero discharge site.
71 On 18 June 2001 the EPA wrote to the company in relation to a difference of opinion as to the interpretation of condition O3.5. In the letter GWS was advised that "To ensure the condition is clearly understood, the EPA proposes to issue a Section 58 Notice rewording the condition so that it reads "Stormwater runoff from areas other than the utilisation areas must be prevented from flowing onto the utilisation areas"". No action was taken to re-word condition O3.5 in the manner proposed in the letter dated 18 June 2001. Mr Kneebone makes the point that notwithstanding the knowledge that discharge from the site was contemplated the EPA neither varied, suspended nor revoked the licence so as to avoid what Mr Kneebone describes as the "inevitable discharge". Furthermore, the principle of the irrigation system was at all times that it would inevitably discharge stormwater in certain circumstances. This principle, according to Mr Kneebone, has been inherent in the Yarra area system since 1992 and in the Goulburn system since 1982.
72 As the person responsible for ensuring GWS complies with the conditions, Mr Kneebone sets out in considerable detail the manner in which the company has carried out its activities at the irrigation site relevant to the conditions of the licence. The EPA has not sought to challenge the accuracy of Mr Kneebone's account in this respect.
73 In cross-examination, Mr Kneebone admitted the fact that on 5 February 2002 stormwater run-off from the company's irrigation area left the site and it contained the signature of the company's wool scour, including suspended solids, ph and potassium and that it reached Kangaroo Ponds. He could only point to condition O3.5 to justify the discharge as well as the requirement not to cause environmental harm. In his opinion, and to his knowledge, GWS has never caused any environmental harm. Nevertheless, notwithstanding the deletion of condition W8 he understood the first flush design should be observed as an operating condition of the system as it was installed. Effluent has never been discharged to any watercourse and RCD3, which is the main storage facility for storing high strength effluent, has never overflowed.
74 Mr Kneebone does not agree that the response to the circumstances that arose in August 1998 was merely a response to an emergency situation but rather, although the system was in trouble, indeed wildly out of control, the response was intended to be a permanent management tool to make the area work more effectively.
75 Notwithstanding evidence of Mr Wearne to the contrary, Mr Kneebone claims condition W8 was deleted from the licence without reference to him. Although the removal of condition W8 in 1998 meant that the only condition expressly in terms authorising discharge from the site, and then only in specific circumstances of a one in 10 year event of 72-hour duration, was taken out of the licence, Mr Kneebone maintains the view that the situations at Yarra and Goulburn were identical operations carried out in accordance with the instruction given by Mr Matthews in November 1989, namely that the system should be operated in accordance with its design to collect the nominated first flush of 10mm of rainfall run-off from the irrigation areas in the RCDs and direct any additional water away from the RCDs to Mulwaree ponds.
76 He said to Mr Rushton SC, who appears on behalf of the prosecutor, that he has held the belief that condition O3.5 permitted the company to divert stormwater from within the irrigation area off the site since November 1989. After GWS submitted the proposal by Dr McCracken to convert Yarra to a first flush system in August 1998 Mr Kneebone was of the view that GWS was to operate at Yarra in a similar manner to Goulburn so that it can only be stormwater that is discharged from within the irrigation area, provided it did not cause environmental harm.
77 The 10mm requirement no longer appears as a condition of the licence but nevertheless Mr Kneebone claims it remains as an operating condition for the system. His understanding of the reason for deleting condition W8 is that it was done to avoid confusion with the provisions of condition W5. Thereafter he believes condition W5 permitted discharge of stormwater from within the irrigation area without limitation, except in respect of harm to the environment.
78 Mr Kneebone draws a distinction between the express provision of discharge points for raw effluent by field irrigation referred to in condition P1.3 and condition 03.5 providing for stormwater to be diverted.
79 The evidence of Mr Parker consists primarily of a challenge to the evidence of Mr Julli and the conclusions that he reaches firstly, about the level of pollution and secondly, the alternative wastewater treatment options available to the defendant. By his own admission in respect of the former matters Mr Julli is eminently more qualified than Mr Parker as an ecotoxicologist. Mr Parker nevertheless maintains that from his own experience and knowledge, global best practice for managing or disposing of wool scouring wastewater includes discharging partially treated wastewater directly to sewers or, if a sewer is unavailable, directly to waters.
80 Dr McCracken agrees that contaminated stormwater left the site on 5 February 2002. However, he says, there was not sufficient background data available from sampling to be sure that the stormwater run-off from the site was likely to affect the waters in Kangaroo Ponds. He says the loadings of some contaminants in run-off from the site could have been greater than the loadings in stormwater run-off from other areas, but not necessarily. He agrees that the background readings off-site show less contamination on a concentration basis but not necessarily on a contaminant-loading basis.