Environment Protection Authority v Eco Cycle Materials Pty Limited; Environment Protection Authority v Scanlan
[2003] NSWLEC 63
At a glance
Source factsCourt
Land and Environment Court (NSW)
Decision date
2003-02-04
Before
Talbot J, Mr P
Source
Original judgment source is linked above.
Judgment (9 paragraphs)
Introduction 1 HIS HONOUR: In matter No. 50091 of 2002 the company, Eco Cycle Materials Pty Limited ("Eco Cycle"), is charged that between 2 November 1999 and 21 March 2000 at Wetherill Park it committed an offence against s 48(2) of the Protection of the Environment Operations Act 1997 ("the PEO Act") in that it was the occupier of premises in which a scheduled activity was carried on and, at the time that activity was carried on, it was not the holder of a licence that authorised that activity to be carried on.
2 The scheduled activity is generally described in the particulars as crushing and grinding or separating works. 3 In matter No. 50092 of 2002 the defendant, Maxwell John Scanlan, is charged that between 2 November 1999 and 17 December 1999 at Wetherill Park he committed an offence against s 48(2) of the PEO Act in that, being a director of Eco Cycle, being a corporation that contravened the provision he contravened the same provision as a result of the operation of s 169(1) of the PEO Act. 4 The scheduled activity is defined in Sch 1 to the PEO Act in sub-paragraphs 1 and 2 under the heading "Crushing, grinding or separating works". There is no dispute that the activities, which the company carried on while Mr Scanlan remained a director, fall within that description. 5 The Environment Protection Authority ("the EPA") was first notified by the company's consultant on 30 October 1998 that the company proposed to develop the site as a road materials recycling transfer station, including crushing and screening of materials in the order of 500 to 1,000 tonnes per day and the environmental impact statement was presented on 6 May 1999. On 6 September 1999 the EPA issued general terms of approval to Fairfield City Council ("the council") and the company was informed of this fact. 6 Thereafter steps were taken to establish the necessary infrastructure on the site and machinery was delivered. By 2 November 1999 operations had commenced. The council granted development consent on 5 January 2000. 7 There was no formal application for a licence to the EPA until 23 February 2000. The Court is informed, and it is agreed, that a licence was subsequently granted to the company in May 2000. 8 In the meantime, the recycling operation continued at least during the periods specified in the summons. Mr Scanlan ceased to be a director of the company on 17 December 1999. That fact explains the discrepancies in the dates particularised in the respective summons. 9 Both the company and Mr Scanlan were aware that they were operating without a licence. On 28 October 1999 the council issued a notice of proposal to serve an order to cease activity on the site. 10 On 29 November 1999 a prevention notice, pursuant to s 96 of the PEO Act, was served on the company. Both of these notices referred to the carrying on of activities contrary to statutory requirements. 11 Although he ceased to be a director in December 1999 as I said, at all times up to February 2000 Mr Scanlan performed the role of general manager. In a record of interview conducted on 9 March 2000 he said as follows:- …I would like to say that we are eternally sorry that we started off on the wrong foot, because it was definitely not our corporate policy or intention. We invested a lot of money, and we got into the situation because of the elongated time span of getting the EIS prepared and getting everything done, that the money ran out and we got ourselves into an economic situation whereby, I guess, I'd have to take the rap for it. I made a decision to let a little bit of material into the site. Unfortunately, due to the comments of Mr Glen Apps at Fairfield Council, and the pending DA consent coming at any moment, that trickle of material started to develop into a stream, and I would be the first to admit that probably I did not control the situation as well as I should have…I can only apologise. I feel contrite…we are very conscious we have been in breach. We have done the wrong thing. We have been very poor performers. We are now in the processes of changing that all around. We apologise to all the statutory authorities.