© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2000] NSWLEC 122
Land and Environment Court (NSW)
1993-11-22
Lloyd J
Original judgment source is linked above.
These proceedings were commenced on 25 September 1998. On 8 July 1999 a plea of guilty was entered by the defendant and an undertaking was given by the defendant to perform remediation works in lieu of the prosecutor seeking any orders under section 14 of the Environmental Offences and Penalties Act. This work has now been completed to the satisfaction of the prosecutor and no order under that section is now sought. This work encompassed all that could reasonably be done by way of remediation. Further environmental damage could be caused by any further attempt to remediate. The defendant has submitted a schedule of costings which discloses that the cost to it of carrying out the remediation works was $32,965.
I turn now to the question of environmental harm. Dr A C Roach is an environmental scientist employed by the prosecutor. He holds a degree of Bachelor of Applied Science majoring in environmental biology, and a doctorate of philosophy in science. He inspected the site on 14 November 1997 and was asked to assess the impact of the incident on the water quality of the creek. According to Dr Roach some of the sediment had been transported downstream past the dumped material and there had been significant erosion of the material in the first thirty six (36) days after the incident was first reported.
Dr Roach took samples of water in order to check its turbidity and the concentration of suspended solids. He took a number of samples not only from the unnamed tributary that was affected but from another tributary which was unaffected and from an area upstream of the particular dam in this case. It was Dr Roach's opinion that the level of suspended solids in the creek below the dumped material appeared to be higher than that which may be normally expected for this creek and the action of dumping the material appears to have polluted the water below the dam wall by increasing the suspended solid load in the water.
The principal effect on the environment caused by the incident according to Dr Roach is that where there is a discharge of water with a high concentration of suspended solids there is a reduction in the degree of light penetration into the water column, possible mortality of aquatic organisms, siltation and a decrease in aesthetic value.
As to turbidity, Dr Roach concluded that the effect appears to be mostly sublethal and therefore not permanent. According to Dr Roach the concentration of suspended solids were below those considered necessary to cause direct mortality to most animals, but the water below the dumped material did have a turbid appearance which was not evident in the unaffected turbidity or in the subject creek above the dam. The dumping of this material according to Dr Roach had a significant local effect where it smothered the vegetation. In terms of increases in turbidity, downstream water quality was degraded but not to acute levels. At the time of his inspection it appeared possible, however, that the material could move further downstream during a heavy rainfall event.
Professor M D Burchett is professor of plant biology at the University of Technology in Sydney and she made an inspection of the site on 10 February 1999. In her opinion an immediate result of the incident was that all of the low shrub and ground layer plants buried under the flow would have been killed by a mixture of uprooting, crushing, suffocation and absence of light. A number of shrubs and young trees that were caught in the flow were pushed over and then washed away, the remains of some of them being visible along the creek. Some of the other plants emerging through the sediment layer which are still standing are dead or apparently dying with severe loss and die back of branches. Other emergent trees and tall woody shrubs which are still buried for the first metre or more of their trunks may well be dying. This is because the trunks often rot if buried in soil.
According to Professor Burchett, in addition to the above impacts, the normal soil fauna and micro-organisms that comprise the soil ecosystem and live in a symbiotic relationship with plant roots will also have been destroyed by burial under a depth of sediment. While some may re-establish others will not since the life in the first metre of soil is different in composition from that which occupies deeper levels.
As to the likely future environmental harm, Professor Burchett is of the opinion that it seems likely that more of the emergent plants will die. The creek has re-established its path and in so doing has disturbed part of the sediment deposit further down the valley which will continue to have an effect further downstream. Native plants may recolonise the whole of the disturbed surface in time, but the area is also vulnerable to a massive weed invasion since there are some weeds higher up in the local area.
According to Professor Burchett, even if it were natives that would eventually recolonise the whole surface of the silt deposit, since the substrate is of different texture it will have a different mineral availability and organic matter content from the original soils and it can be expected that it will be a different subset of species and a different community structure from the original.
Since this would have been caused by human disturbance it must be regarded as anthropogenic harm to the ecosystem. There can also be expected to be new balance and relative abundance of faunal species which again is a human caused disturbance of the pre-existing ecosystem.
In considering the question of penalty, I am required to take into account a number of considerations set out in section 241 of the Protection of the Environment Operations Act.
The first is the extent of the harm caused or likely to be caused to the environment by the commission of the offence. Although there is some dispute in the evidence as to the amount of material which had been removed from the dam and deposited outside it, I accept the amount agreed upon by the parties and stated in the statement of agreed facts, namely approximately 1600 cubic metres of material. However the exact volume is secondary to the visible effect of the incident.
I accept the opinion in particular of Professor Burchett who summarised the environmental consequences and likely future consequences as follows: physical destruction to plants and soil in the flow path which is much wider than the creek bed itself; some continued erosion from the surface down the waterway and along the banks so long as it is not covered and stabilised by vegetation; possible massive weed invasion and even if completely colonised by native plants it can be expected to have a different subset of species and relative abundances from the original; and whether covered by weeds or native plants, the formal suite of species supported and their relative abundances will also be different from that of the pre-existing ecosystem.
Further runoff of suspended solids has the potential to cause the effect outlined by Dr Roach, principally a reduction of light penetration into the water column, possible mortality of aquatic organisms, siltation and decrease in aesthetic value.
The next consideration is the practical measures which may be taken to prevent, control, abate or mitigate that harm. No measures were taken by the defendant or by anyone else before the work was commenced. Sediment control measures could and should have been in place as it was likely that sediment would descend into waters. Alternatively, the material could have been placed where if adequate sediment controls were in place it was not likely to descend into waters.
I note that the prosecutor concedes that the measures taken since the entering of the plea by the defendant to mitigate the harm are all that could reasonably be done to mitigate that harm. It would appear that the primary reason that the defendant did not start earlier with the remediation works was that it did not accept responsibility for the incident, arguing that the Warringah Radio Control Society was responsible.
The next consideration is the extent to which the person who committed the offence could reasonably have foreseen the harm caused or likely to be caused to the environment by the commission of the offence. I accept the submission of the prosecutor that the defendant was in the business of earthmoving and should have foreseen the likely harm, that it should have been aware of the need for sediment controls and that its operators should have been aware of the danger of placing material in a position where it was likely to pollute waters.
Next is the extent to which the person who committed the offence had control over the causes which gave rise to the offence. Again I accept the submission of the prosecutor that the defendant had ultimate control over the works performed by its employees.
The next consideration is whether in committing the offence the person was complying with orders from an employer or a supervising employee. This factor has no relevance in this particular case.
I am also required to take into consideration a number of other matters. First is the fact that the defendant has pleaded guilty to the offence. In pleading guilty to the offence I accept that it is contrite and remorseful and pursuant to section 22 of the Crimes (Sentencing Procedure) Act 1999 I am required to take that factor into account.
Next, I accept that the defendant has co operated with the prosecutor and has carried out remediation works to the satisfaction of the prosecutor at a cost of $32,965. The defendant has also agreed to pay the prosecutor's costs in the sum of $10,000. The defendant must also bear its own costs. The defendant has had no prior convictions for environmental offences. The fact that this has been a costly exercise for the defendant I think makes it unlikely that it will re-offend.
As I have said, the defendant's gross return on the contract was $6,870 and it has been required to meet the costs of remediation, the prosecutor's costs and its own costs. Nevertheless there remains an element of general deterrence in the policy of fixing penalties and I can do no better than quote from the judgment of Mahoney JA in Axer Pty Limited v Environment Protection Authority in the Court of Criminal Appeal delivered on 22 November 1993 unreported: The legislation does not seek merely to prevent deliberate or negligent pollution. It envisages that at least in many cases proper precautions must be taken to ensure that pollution does not occur. Experience has shown that it is not enough merely to take care, accidents will happen. The legislation envisages that in many cases care must be supplemented by positive precautions. Business must be arranged and precautions taken so as to ensure that pollution will not occur. Mahoney JA continues: But I believe legislation of this kind contemplates that in general the cost of preventing pollution will be absorbed into the cost of the relevant industries and in that way will be borne by the community or by that part of it which uses the product which the industry produces. In assessing the quantum of a fine considerations of this kind are to be taken into account. The fine should be such as will make it worthwhile that the cost of precautions be undertaken. And then finally Mahoney JA states: I do not mean by this that the legislature saw the legislation as providing by payment of a fine a licence to pollute. In the end the object of the legislation is to prevent pollution and to do this inter alia by the deterrent effect of a substantial fine and by in consequence persuading the industries concerned to adopt preventive measures" 38. I conclude from these remarks of Mahoney JA that there is necessarily included, therefore, an element of general deterrence in any penalty.
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Environment Protection Authority
Aaron Plant Hire & Earthmoving Pty Ltd
CITATION : Environment Protection Authority v Aaron Plant Hire & Earthmoving Pty Ltd [2000] NSWLEC 122 PROSECUTOR: Environment Protection Authority
(1997) 97 LGERA 368
(1982) 2 NSWLR 104