Primary judge's reasons
12 In his reasons his Honour identified two potential relevant representations. The first ('the generating capacity representation') was that '[WPC] would only consider tenders that provided for a generated capacity of at least 300 megawatts to 330 megawatts constantly provided on a sent-out basis'. The second (the minimum environmental condition representation) was that '[WPC] would only consider tenders that satisfied the minimum environmental conditions specified in the tender documents'.
13 As his Honour expressed it, in simple terms Griffin said that WPC called for tenders for a 300 MW to 330 MW baseload plant which was required to meet prescribed environmental standards. However, it awarded the tender to a plant with a 240 MW baseload capacity and an 80 MW peaking capacity which did not meet the prescribed environmental standards.
14 In his reasons his Honour made clear that WPC opposed the application, firstly, on the grounds that FCR O 15A r 6(a) could not be satisfied and, secondly, on the basis that as a matter of discretion, relief should be refused.
15 Turning to the first of those issues, his Honour reviewed at some length the evidence of Mr Trumble and Mr Harvey.
16 Turning to Griffin's postulated potential claim for a contravention of s 52 of the Trade Practices Act, his Honour identified the elements required to be established as: misleading or deceptive conduct by WPC, reliance by Griffin and damage.
17 In then examining the evidence and whether it satisfied FCR O 15A r 6(a) his Honour relied upon the reasoning of Hely J in St George Bank Limited v Rabo Australia Limited (2004) 211 ALR 147 (St George Bank 211 ALR) at 153-154 to the following effect:
'…
(c) the test for determining whether the applicant has "reasonable cause to believe", as required by sub‑paragraph (a), is an objective one; …
(d) belief requires more than mere assertion and more than suspicion or conjecture. Belief is an inclination of the mind towards assenting to, rather than rejecting a proposition. Thus it is not sufficient to point to a mere possibility. The evidence must incline the mind towards the matter or fact in question. If there is no reasonable cause to believe that one of the necessary elements of a potential cause of action exists, that would dispose of the application insofar as it is based on that cause of action:…
(e) whilst uncertainty as to only one element of a cause of action might be compatible with the "reasonable cause to believe" required by sub‑paragraph (a), uncertainty as to the number of such elements may be sufficient to undermine the reasonableness of the cause to believe;
…'
18 At [82] his Honour said:
'82. The question, applying the test in Rabo, is whether there is evidence in support of the potential claim which elevates the potential claim beyond 'mere assertion' and 'more than suspicion or conjecture'.'
19 At [88] his Honour said:
'88 On the basis of that evidence, I am of the view that there is a foundation beyond mere assertion upon which the applicants can base a potential claim that, in referring in its press releases to the proposed power station as having a 300MW to 330MW of baseload generating capacity, the respondent, thereby, represented that it 'would only consider tenders that provided for a generated capacity of at least 300 megawatts to 330 megawatts constantly provided on that sent‑out basis'.'
20 At [91], having said that the evidence upon which WPC relied would in the context of the actual proceeding raise a serious question to be tried as to whether Mr Trumble did and could have held the understanding of baseload capacity which he did:
'91 … But this does not mean that, for the purposes of this application, the status of the applicants' postulated potential claim is thereby reduced to a 'mere assertion', 'conjecture' or 'speculation'; nor does it incline the mind against the characterisation of that potential claim as one which may give the applicants a right to relief.'
21 In relation to the second and third elements of the alleged s 52 claim, his Honour concluded at [92]:
'92 I am satisfied that the evidence as to reliance and damage in respect of the potential claim founded upon the generating capacity representation, also causes those elements to rise above the status of 'mere assertion'. It follows that, in my view, the applicants have established that there is reasonable cause to believe that the applicants may have the right to obtain relief founded upon the statements in the press releases issued by the respondent prior to 6 August 2004.'
22 In relation to the postulated claim relating to prescribed environmental conditions, his Honour concluded at [94]-[95]:
'94 Further, there is no dispute between the parties that on the evidence, the proposed Wambo power station does not meet the requirements that are stated in cl 6.3.1 and cl 6.3.2 of the Bid Information Memorandum. The answer which the respondent makes to the potential claim is that the requirements referred to in cl 6.3.1 and cl 6.3.2 did not impose absolute standards, but were only standards that a proponent should 'strive' to meet or exceed. Whether this is a complete answer or not, would be a matter for trial. It suffices to say that the evidence establishes that there is a potential claim for a contravention of s 52 of the TP Act, beyond a 'mere assertion', founded on the representation that the respondent would only accept tenders which satisfied the minimum environmental conditions specified in the tender documents.
95 There is, in addition, evidence from Mr Trumble that he relied upon those statements in submitting the tender and evidence that the applicants spent several million dollars on the bid, which I am satisfied also causes those elements of a potential claim under the TP Act to rise above the characterisation of 'mere assertion'. I, accordingly, find that there is reasonable cause to believe that the applicants may have a right to obtain relief against the respondent founded upon the statement in the Bid Information Memorandum and the Final Bid Invitation which relate to the compliance with environmental conditions.'
23 In relation to the contract claim, his Honour said there was no need to deal with it and it is suffice to say that the exclusion clauses in the Bid Agreement appeared, on the face of it, to comprise a substantial obstacle for Griffin.
24 His Honour therefore concluded that Griffin had satisfied the provisions of FCR O 15A r 6(a). There was no issue on satisfaction of other provisions of that Rule.
25 In relation to the discretionary considerations, these were founded on the affidavit of Mr Furphy and related to the confidential character of the bid proposals, submissions, presentations and other documents which record or evidence the content of any proposals submitted by Wambo to WPC.
26 In relation to those issues, his Honour concluded at [110]-[111]:
'110 … The fact that the documents in respect of which discovery is sought may contain confidential information will not usually in itself be sufficient to cause the Court, in the exercise of its discretion to decline to order preliminary discovery. In this case, the applicants recognise restrictions may need to be imposed upon the number of persons who may be entitled to inspect the discovered documents.
111 Further, limiting inspection also strikes a balance between the legitimate concerns expressed by senior counsel for the respondent as to the need to maintain confidence in the respondent's public tender process, and the applicants' concerns as to whether the process operated lawfully.'
Accordingly, his Honour concluded that Griffin's notice of motion was entitled to succeed.