Donau Pty Limited v ASC AWD Shipbuilder Pty Limited
[2018] NSWSC 1589
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2018-10-04
Before
Ball J
Source
Original judgment source is linked above.
Judgment (5 paragraphs)
Background
- These proceedings concern a contract (the 2HA) entered into on 26 October 2012 between the plaintiff, Donau Pty Limited, formerly known as Forgacs Engineering Pty Ltd (Forgacs), and the defendant, ASC AWD Shipbuilders Pty Limited (ASC), which varied the terms of an earlier contract (the Original Contract) between Forgacs and ASC by which Forgacs agreed to construct for ASC certain parts of the hulls of three air warfare destroyer ships that ASC, with others, had contracted to build for the Commonwealth of Australia.
- During the course of the proceedings, a large number of issues were raised by the parties in connection with their dispute. Some of those issues, such as a claim by ASC that the 2HA should be rectified and claims by Forgacs that various estoppels operated in its favour, raised substantial factual issues.
- Many of those issues were abandoned before trial with the result that the trial itself concerned two principal issues. One was the correct construction of the 2HA and whether on its correct construction it had come into effect and, if so, whether ASC had validly terminated it and the consequences of termination if it had. The second issue was whether ASC had been induced to enter into the 2HA by the misleading and deceptive conduct of Forgacs in contravention of s 18 of the Australian Consumer Law.
- In a judgment I delivered on 20 August 2018 (see Donau Pty Limited v ASC AWD Shipbuilder Pty Limited [2018] NSWSC 1273), I concluded: 1. Contrary to ASC's submissions, the 2HA had come into effect; 2. Contrary to Forgacs' submissions, ASC had validly terminated the 2HA; 3. Contrary to Forgacs' submissions, the effect of termination was that ASC was largely entitled to the rights it had under the Original Contract and in particular the right to adjust the Payable Fee payable by it under that contract by reference to the mechanism set out in the contract; 4. Contrary to ASC's submissions, the 2HA did have the effect of releasing any right that ASC may otherwise have had to liquidated damages; and 5. Had it been necessary to decide, contrary to ASC's submissions, its case based on misleading and deceptive conduct failed.