"The documentary material before me indicates that the company [Zorba] was carrying on business during most of the relevant period albeit at a lower level of activity than previously because the applicant was unable to obtain sufficient work for the company. That affected the profitability of the company but does not alter the fact that the company continued to carry on business and it was the applicant who conducted that business for the company. There was no suggestion before me that any other person conducted the company's day to day business. I have taken into account the evidence that the company sometimes allowed others to use its facilities."
24 By reference to its "findings of fact", the following appears to be the findings based on documentary material which led to that conclusion:
(1) Zorba operated its bank account between March 1991 and June 1993, with some 45 deposits over that period of 27 months totalling $127,857 and averaging $4,735 per month, and with some 400 cheque withdrawals over that period (some were dishonoured) totalling about $125,000.
(2) Zorba entered into a number of contracts to perform structural steel work as follows:
(a) prior to May 1990, with Multiplex Construction Pty Ltd ("Multiplex") in relation to the Supreme Court Building, with a completion date of September 1990, and in late 1992 with Multiplex to supply and install a rubbish chute for which it was paid $2,608 in December 1992; Multiplex paid Zorba $99,719 between July 1990 and June 1993 of which $28,506 was paid after March 1991. [Although its findings simply recite that information as being contained in a witness statement, it has apparently been accepted by the Tribunal as the fact, and included in the "documentary material"]. There was no submission put, nor is there any indication in the Tribunal's reasons, that the $28,506 was for work performed after March 1991, apart from the small job for which it was paid $2,608.
(b) On an unspecified date, with John Holland Construction and Engineering Pty Ltd, to provide some shelving for $7,000 for which Zorba was paid $4,992 between October 1991 and January 1992. Again, no submission was put, and there is no indication in the Tribunal's reasons, that that contract was entered into after March 1991 or that the work was performed after March 1991.
(c) In August 1991, to sell steel to Darwin Steelworks for $1,000.
(d) In February 1992, to perform steel fabrication work for Watco Pty Ltd for $16,373, for which it was ultimately paid only a total of $6,000 in April and May 1992.
(e) In March 1992, to perform structural steel work for Eniky Pty Ltd for which it was paid $12,000, but then Eniky Pty Ltd successfully claimed damages for non-completion of $12,167.
(f) In April 1993, to construct a steel balustrade for which it was paid $2,000.
(g) In April 1993, to fabricate and supply an item of warehouse equipment, for which it was paid $450.
25 In addition the Tribunal found that until April 1993 Zorba maintained the lease on its premises at Winnellie. There was also evidence (although the Tribunal made no express findings on these matters) that Zorba maintained until then its telephone connection and its advertisement in the Yellow Pages, and also engaged in some other advertising of its business. The Tribunal also found that in May 1992 Zorba joined the Territory Construction Association, that between October 1990 and December 1992 there was consistent use of electricity at its premises (the accounts show a low level of electricity use of less than $1 per day), and that in 1993 the applicant tried unsuccessfully to sell Zorba's business.
26 The Tribunal also made findings as to the contents of Zorba's financial accounts over the years ending 30 June 1991, 30 June 1992 and 30 June 1993. It does not state that it accepted those records as accurate. In my judgment, however, it must be inferred from its general finding about Zorba's business activities in the relevant period that the Tribunal has accepted those figures as reliable. It is hard to see how it could have come to the general conclusion set out in par 22 above based upon the contractual documents themselves, as they indicated to the Tribunal contracts totalling no more than $36,473 in the financial year ended 30 June 1992 and $2,450 for the financial year ended 30 June 1993. The profit and loss accounts showed:
"1991 1992 1993
$ $ $
Gross Contract Revenue 123,088.00 45,626.00 57,306.00
Less cost of Goods Sold 34,112.00 12,723.00 3,474.00
Purchased Materials 4,706.00 270.00 20.00
Architects/Engineers/ 4,571.00 361.00 -
Drafting Fees 5,312.00 3,695.00 2,050.00
Hire of Plant and 3,324.00 535.00 147.00
Equipment 71,056.00 28,040.00 51,615.00
Subcontractors 92,380.00 62,110.00 68,078.00
Welding Supplies -21,324.00 -34,069.00 -16,463.00
Gross Profit from Trading 11,700.00 11,636.00 2.00
Less:Expenses 361.00 7,298.00 48,966.00
Net Operating Loss -9,263.00 -15,135.00 32,505.00
Add: Non Cash Items: 1,788.00 1,660.00 140.00"
Depreciation
Less on Asset
Realisation
Adjusted Profit/Loss
Electricity (incl in Expenses)