DCL'S APPEAL
34In due course it will be necessary to address each of the alleged questions of law that DCL contends were erroneously answered by his Honour. However, at the outset it is necessary to note two matters. First, as noted, his Honour found that "there is no evidence to support a conclusion that the written quote was forwarded on to Colin Smith". In context, this is to be taken as his Honour finding that there was a lack of probative material to support the contention rather than that there was "no evidence" as used in the technical sense (see Broussard v Minister for Immigration and Ethnic Affairs (1989) 21 FCR 472 at 479 per Gummow J.) It follows that this finding was purely a finding of fact and was not one of law or even of mixed fact and law. It also follows from the early discussion that it was a finding that was clearly open on the evidence (Kostas and Bond id). The same observation applies in relation to his Honour's findings concerning whether Mr Smith was advised that laser levelling was required.
35Second, almost the entirety of DCL's complaints reduced to the single contention that his Honour was obliged, but failed, to find that the contract between the parties required the installation of footings in accordance with particular dimensions being those set out in Mr Stair's quote dated 15 September 2010 or, failing that, those set out in the email of 16 August 2010. His Honour rejected the entire premise behind that contention. His Honour, in effect, found that under the contract the dimensions of the footings were not a term of the contract but was, instead, a matter for Mr Smith and Range Harvester to determine. Instead, his Honour found that the relevant contractual term was one that required that, whatever the specifications, the footings "support the slats and the nesting system" that were to be installed.
36In submissions, counsel for DCL accepted that if that finding was correct, then the consequences spelled out in [37] and [38] of his Honour's judgment that have been set out at [33] above followed, i.e. Range Harvester succeeded.
37The reasons given by his Honour to support the construction of the contract were mainly derived from his Honour's analysis of the communications leading up to the entry into the contract of 20 September 2010. As stated, his Honour also relied on certain concessions made by Mr Howe in cross examination to the effect that neither he, nor Mr Kendon, was concerned with the specifications for the concrete footings. This latter aspect of his Honour's reasoning is doubtful (see Codelfa Construction Pty Ltd v State Rail Authority (NSW) [1982] HCA 24; 149 CLR 337). Nevertheless, I consider that his Honour's conclusion was correct. It is notable that no aspect of the negotiations that led to the entry into the contract involved any concern being expressed on the part of anyone from DCL as to the dimensions of the footings. To the contrary, and as noted by his Honour, the emails reveal that DCL did not want to descend into that level of detail because it wanted responsibility for the concrete footings supporting the nesting system to rest with Range Harvester. I consider that his Honour was correct to construe the agreement in the manner that he did.
DCL's Questions of Law
38DCL's summons identified ten questions of law that it is claimed that his Honour answered incorrectly. In substance, they were expressed in terms of errors of law that his Honour was said to have made. I will address each in turn.
39The first ground alleges that his Honour erred in finding that the agreement between the parties was for Range Harvester to supply and install concrete footings that would support the slats and the nesting system and that it was a further condition that if subsidence occurred causing a problem with the equipment, then Range Harvester had to rectify the problem or problems. It follows from what I have already stated that I find that his Honour did not err in law in so concluding.
40The second alleged error is that his Honour is said to have failed to take into account the whole or any part of the evidence adduced and given by Mr Colin Smith during his cross examination. It follows from what I have already stated that this does not raise any question of law, only a question of fact.
41The third alleged error is said to be that his Honour erred in directing that the proceedings proceed on an agreed basis, namely, inter alia, that a determination would be made as to whether the footings in situ were as agreed, and then misdirected himself by making findings of fact based on purpose and fitness of the footings. Nothing in the materials reveals that the approach adopted by his Honour involved any departure from some "agreed basis" which his Honour either directed or the parties had assumed. Instead, as the hearing unfolded, DCL's case was refined so that the outcome turned upon its contention that it was an essential term of the contract that the concrete footings would be in accordance with some specified dimensions. Once his Honour rejected that contention, then DCL's defence failed.
42The fourth error of law on the part of his Honour was said to result from his Honour "misdirecting himself by making findings of fact whether the said footings were installed so as to support the nesting machine and slats". As formulated, the alleged error refers to [34] and [35] of his Honour's judgment. Those paragraphs should be read together with [33]:
"33. Although a great deal of time has been spent on the dimensions of the concrete footings, they only have relevance if they are found not fit for the purpose for which they were installed.
34. The purpose for which they were installed was to support the nesting machine and slats.
35. The evidence as it stands does not support such a finding."
43In this part of the judgment his Honour was seeking to explain how, in light of his Honour's construction of the contract, the dimensions of the footings might have been relevant, namely, to a consideration of an allegation that they were not fit for purpose as alleged in cross claim. His Honour then noted that there was no evidence to support the contention that they were not fit for that purpose. These passages do not reveal any misunderstanding on the part of his Honour as to DCL's case. Instead, they reveal that once his Honour had rejected DCL's case as to how the contract was to be construed, then the relevance of any factual enquiry about the dimensions of the footings that were in fact installed fell away in circumstances when there was no overall allegation remaining that the footings were unfit for any purpose for which they might reasonably have been required.
44The fifth and sixth errors on the part of his Honour are said to be as follows, namely, that his Honour:
"Erred in concluding that there was 'no evidence' to support a finding that the footings failed to support the nesting equipment and slats because of the way the case was run when there could be no evidence adduced to support a finding the footing had failed to support the nesting equipment and slats.
Erred in finding that the plaintiff had 'satisfied the court that it provided footings in accordance with the finalised agreement' [para 35], when there was no evidence to support such a finding."
45These complaints all fall away for the reasons given in relation to the fourth ground and bearing in mind the concession that I noted earlier.
46The seventh error on the part of his Honour was said to be in making:
"[N]o findings, either ignoring the evidence or not giving any weight or due weight to the evidence which was before the court that the footings as laid, on balance, were not installed in a workmanlike manner."
47This allegation falls away for the same reasons that I have given earlier, namely, once his Honour construed the contract in the manner that he did and bearing in mind that DCL did not maintain an allegation that the footings were not fit for the purpose that his Honour identified, then it was irrelevant to the issues whether or not the footings had been installed in a workmanlike manner.
48The eighth and ninth grounds relied on by DCL all relate to the cross claim. It follows from what I have stated that once his Honour came to the construction that his Honour did and when it became clear that there was no ultimate submission being made on behalf of DCL that the footings were not fit for their purpose, then no aspect of the cross claim remained to be determined. During the hearing it was made clear to his Honour that the quantum sought to be recovered pursuant to the cross claim was the amount necessary to remove the concrete footings. In turn, this depended upon DCL establishing that the footings that were installed were not those that it had contracted to receive. This was said to be so because they had only contracted to receive footings of particular dimensions. Of course, that premise was rejected by his Honour. Thus, the foundational step for the success of the cross claim was not established.
49The tenth ground relied on by DCL alleges that his Honour's reasons were inadequate. This ground was not developed in DCL's submissions. In my view, once his Honour's judgment is read in light of the issues that were raised at the hearing, it is clear that his Honour adequately dealt with the questions of fact and law that arose for determination.
50I should add that aspects of DCL's written submissions appear to travel beyond the questions of law set out in its summons. However, as best as I can ascertain and with one possible exception, those complaints are all addressed by the above reasons. The possible exception is the suggestion in part of those submissions that his Honour failed to address and make findings concerning what DCL described as a unilateral variation of the contract by Range Harvester. The unilateral variation was said to arise from the fact that Mr Smith ultimately installed footings that were 200 by 250 millimetres, whereas the dimensions that had been raised by the parties were 400mm by 100mm and (arguably) 300 millimetres by 300 millimetres. The short answer to all of these submissions is that, according to his Honour's finding, that action of Mr Smith was not a variation of the contract at all because the contract never required footings of any particular dimensions in the first place.
Mixed questions of law and fact
51As stated, DCL also sought leave under s 40(1) of the Local Court Act to raise various questions said to be of mixed fact and law, namely:
"The Magistrate:-
a. Erred in directing that the proceedings proceed on an agreed basis inter alia that a determination would be made as to whether the footings in situ were as agreed and proceeded to misdirect himself by making findings of fact based on 'purpose and fitness' of the footings, and
b. Further erred by misdirecting himself by making findings of fact whether the said footings were installed so as 'to support the nesting machine and slats'. (Para 34 and 35).
c. Erred in making no findings, either ignoring the evidence or not giving any weight or due weight to the evidence which was before the court, that the footings as laid, on balance, were not installed in a workmanlike manner.
d. Erred in concluding that there was 'no evidence' to support a finding that the footings failed to support the nesting equipment and slats because of the way the case was run' (Para 37) when there could be no evidence adduced to support a finding that the footing had failed to support the nesting equipment and slats.
e. Erred in finding that the plaintiff had 'satisfied the court that it provided footings in accordance with the finalised agreement' (Para 38), when there was no evidence to support such a finding.
f. Erred in failing to consider adequately or of [sic] all, the cross claim or any of the issued [sic] raised by it.
g. Erred in making no findings about and either ignoring or not giving any or any due weight to the evidence before the Court relating to the cross claim.
h. Erred in concluding that judgment be entered in favour of the cross defendant before there was no evidence to support such a conclusion."
52I am doubtful whether any of these matters are truly questions of mixed law and fact. In any event, I have already addressed the same complaints when characterised as questions of law. In the end, they all fall away having regard to his Honour's construction of the contract, with which I respectfully agree, his Honour's findings of fact which are not open to challenge and the manner in which the hearing was conducted in the Local Court. Leave to raise those grounds is refused.