D.R. Design (NSW) Pty Limited v Grand City International Development Pty Ltd
[2018] NSWSC 287
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2018-03-08
Before
Ball J
Source
Original judgment source is linked above.
Judgment (6 paragraphs)
Introduction
- In these proceedings, the plaintiff, D.R. Design (NSW) Pty Limited (DR), sought to recover architectural and project management fees said to be owing by the defendant, Grand City International Development Pty Ltd (GCI), under a contract entered into on 8 October 2014.
- I delivered judgment in the proceedings on 19 December 2017 (see D.R. Design (NSW) Pty Limited v Grand City International Development Pty Ltd [2017] NSWSC 1778) and, in accordance with that judgment, the parties brought in short minutes of order which were made by the Court on 14 February 2018, by which the Court gave judgment in favour of DR against GCI in the sum of $131,870.73 and gave directions for the filing of additional evidence and submissions in relation to costs, with the intention that the question of costs would be dealt with on the papers.
- This judgment concerns that question.
- DR claims that it is entitled to its costs of the proceedings on the ordinary basis in accordance with Uniform Civil Procedure Rules 2005 (NSW) (UCPR) r 42.1, which provides: General rule that costs follow the event Subject to this Part, if the court makes any order as to costs, the court is to order that the costs follow the event unless it appears to the court that some other order should be made as to the whole or any part of the costs.
- GCI advances three reasons why the Court should depart from the general principle set out in UCPR r 42.1. First, it relies on a number of offers of compromise. Second, it relies on UCPR r 42.34. Third, it contends that the Court should, in the exercise of its general discretion in relation to costs, refuse to make a costs order in DR's favour because the costs of the proceedings were completely disproportionate to the amount recovered.