Cudgegong Australia Pty Limited v Sydney Metro
[2018] NSWCA 298
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2018-11-21
Before
Meagher JA, Leeming JA, Davies J
Source
Original judgment source is linked above.
Judgment (12 paragraphs)
Background
- There is a long history of litigation arising out of the acquisition of the Land. The primary Judge summarised the history as follows: [10] "2 [In 2008] the registered proprietor of the land was Golden Mile Property Investments Pty Ltd. That company had been placed in liquidation and the mortgagee, Stacks Managed Investments Ltd, exercising its power of sale under a registered mortgage, entered into a contract for sale of the land to [Cudgegong] on 22 September 2008 for a purchase price of $2.25 million with completion being due on 1 June 2012. 3 When the proposed acquisition notice was issued [on 31 May 2012], the vendor and purchaser on 21 June 2012 entered into a rescission agreement, and on the same day entered a further contract for sale to [Cudgegong] for $2,888,648 with the completion of the contract scheduled for 1 July 2013. The purchase price was not paid and the sale did not complete due to the acquisition of the land which occurred on 21 September 2012 [by publication of the notice in the Government Gazette]. 4 [Cudgegong] maintained it had an interest in the land and on 12 July 2012 submitted a claim for compensation under s 39 of the [Land Acquisition] Act. The completed form sought $19.3 million for the market value of its interest in the land, and loss attributable to disturbance. That claim was later revised to $16,382,108. 5 On 5 December 2012, the Valuer-General determined that compensation was payable under the Act to Golden Mile as the registered proprietor and to the two mortgagees, Stacks (as first mortgagee) and RTS Super Pty Ltd (as second mortgagee) in the amount of $4,223,400. 6 On 12 December 2012 [Transport NSW] issued a compensation notice under s 42 of the Act to Stacks and to RTS Super offering $3,026,478 in compensation. The mortgagees accepted and were paid that compensation amount. The balance of the compensation was to be held on trust pending a determination whether Golden Mile or [Cudgegong] was entitled to the balance of the compensation. 7 On the application of the former liquidator of Golden Mile, that company was ordered to be re-registered. 8 [Cudgegong] then commenced proceedings under s 66 and/or s 67 of the Act in Class 3 proceedings in the Land and Environment Court. In those proceedings [Cudgegong] sought compensation amounting to $16,273,522 plus disturbance costs. Golden Mile applied to be joined as a party to those proceedings. 9 In June and July 2013 [Cudgegong] and [Transport NSW] exchanged town planning evidence. The experts conferred and produced a joint report. On 10 July 2013 [Cudgegong] filed a notice of motion seeking an order that [Transport NSW] make an advance payment of compensation to [Cudgegong]. 10 Justice Pain in the Land and Environment Court held on 13 March 2014 that [Cudgegong] had an interest in the land for the purposes of the Act and ordered [Transport NSW] to make an advance payment of $757,300 to [Cudgegong] under s 68(2)(b) of the Act. [11] 11 Golden Mile sought leave from the Court of Appeal to appeal from that interlocutory order. The appeal was upheld on 16 April 2015 and the matter was remitted to the Land and Environment Court for the purpose of hearing and determining according to law the respective interests of Golden Mile and [Cudgegong]. [12] 12 At a second hearing in the Land and Environment Court Pain J held on 1 December 2015 that [Cudgegong] had the relevant interest in the land for the purpose of the Act. Golden Mile again sought leave to appeal. [13] Leave to appeal was granted but the appeal was dismissed on 25 August 2016. [14] Thereafter, the compensation proceedings resumed. 13 On or about 6 September 2016 [Transport NSW] paid [Cudgegong] $765,468.59 being the total of the advance payment plus interest. That payment represented a $3 shortfall in interest that was paid to [Cudgegong] the next day. 14 Thereafter, valuation evidence was exchanged between the parties in the compensation proceedings. A conciliation conference was held on 16 December 2016 but no agreement was reached. 15 On 23 February 2017 the present proceedings were commenced."