Consideration
Claim against ENS
45 ENS obtained a verdict in its favour. The usual order would be that it should have its costs. The plaintiffs, however, submit that not only should ENS not have its costs but that it should pay the plaintiffs' costs.
46 The basis for that submission is the Amended Defence filed by ENS on 11 May 2004 where supply to BC by ENS in July 1998 was admitted, but the specific date of such supply was disputed. The withdrawal of that admission on 16 May 2005, it was argued, had significantly prejudiced the conduct of the case against ENS by the plaintiffs. Until that time the plaintiffs had a reasonable expectation that the fact of supply was not in issue only the date. As a result, it was submitted, even though ENS ultimately succeeded on that issue the plaintiffs should still have their costs because of the way in which ENS had conducted that aspect of the case.
47 As I inferred in the principal judgment and which was confirmed in the affidavit of Ms Lawrence of 30 November 2006, ENS had always assumed that it supplied the plaintiffs with contaminated HEP. It was only when its solicitors somewhat belatedly examined its accounting records in early 2005 that it became clear that no such supply had occurred in June, July or August 1998. That was the reason that the withdrawal of the admission was foreshadowed in March 2005 and at the beginning of the trial. The admission was formally withdrawn and a Further Amended Defence was filed on 16 May 2005.
48 The plaintiffs' submission fails to have regard to two matters. The first is that the original Defence filed by ENS denied all matters in the Statement of Claim. Accordingly supply and the date of supply of the contaminated HEP was always in issue up to the filing of the Amended Defence on 11 May 2004. Any disadvantage suffered by the plaintiffs in reliance upon the admission of supply in that Defence, only existed between May 2004 and the commencement of the proceedings on 6 May 2005.
49 Secondly, in view of the findings which I made as to supply in the principal proceedings, it must have been clear to BC that once supply of the contaminated HEP during July 1998 again became an issue, it was an issue in relation to which the plaintiffs were likely to fail since no such supply to his knowledge had taken place during that month. It is also not without significance that after ENS was allowed to withdraw its admission, the plaintiffs did not avail themselves of the opportunity to administer interrogatories or seek further particulars in relation to the Amended Defence.
50 I am of the opinion that any disadvantage suffered by the plaintiffs as a result of the conduct of ENS in respect of its pleading in respect of the supply issue lasted no longer than 12 months. Absent other considerations I would have been minded to order that ENS not have its costs for the period 11 May 2004 to 6 May 2005 when the trial commenced. In view of the Offers of Compromise of June 2003 and April 2004 it is not necessary to consider that matter further.
51 At the time when the Offers of Compromise of June 2003 and April 2004 were made ENS had not filed its Amended Defence and the question of supply in July 1998 of the contaminated HEP was still at issue. It could not be said that the plaintiffs' refusal to accept either of those offers was in any way influenced by a belief that the question of supply was not at issue. Similarly it could not be said that at the time the offers were made the admission of supply was an "exceptional circumstance" justifying the non-acceptance of those offers.
52 The plaintiffs accepted that, if the Offers of Compromise of June 2003 and April 2004 were made in accordance with SCR Part 22, ENS was entitled to its costs on a party/party basis from 25 June 2003. It was accepted that both Offers of Compromise contained offers which were more favourable to the plaintiffs had they accepted either of them than was the judgment which they ultimately obtained.
53 The plaintiffs submitted, however, that neither offer was in accordance with SCR Part 22 or Part 52A r 22 because the defendants had not included an offer to pay the costs in respect of the claim as required by Part 22 and Part 52A r 22(2).
54 The plaintiffs put their argument in this way. Because the amounts offered in each Offer of Compromise were below $225,000 (see SCR Part 52A r33(2)) either the plaintiffs had no entitlement to costs under the rules or their entitlement could not be quantified so that the offers were not genuinely "plus costs" as required. It is for this reason, the plaintiffs submitted, that they had made requests for clarification of what "plus costs as agreed or assessed" meant, both before and after the 8 April 2004 offer.
55 This submission should be rejected.
56 In relation to the offer of 25 June 2003 there were no inquiries, either orally or in correspondence, as to what "plus costs as agreed or assessed" meant. I do not accept that in relation to that offer there was any such concern as to the meaning of those words as later emerged in relation to the offer of 8 April 2004. That offer was simply ignored by the plaintiffs.
57 Both offers were expressed to be for a specified monetary amount "plus costs as agreed or assessed". This fully conformed with the requirement of SCR Part 22. It is true that a difficulty was created for the plaintiffs by SCR Part 52A r 33 which relevantly provided:
"(2) Where: …
(f) In proceedings commenced after 1 October 1997, where a plaintiff recovers: …
(ii) in any other case - a sum not more than $225,000,
the plaintiff shall not be entitled to payment of his or her costs of the proceedings unless, it appearing to the Court that the plaintiff had sufficient reason for commencing or continuing proceedings in the Court, the Court makes an order for payment.
(3) Without limiting the generality of sub-rule (2), it shall be taken to be a sufficient reason if the plaintiff had reasonable grounds at the relevant time for expecting that he would recover an amount in excess of the amount prescribed by that sub-rule."
58 What that meant was that if the plaintiffs accepted either Offer of Compromise they would have to make an application to the Supreme Court for the purpose of establishing that they had sufficient reason for commencing proceedings in the Court before they would have any entitlement to costs. That is quite a different situation to that which was submitted by the plaintiffs, ie that in effect SCR Part 22 had not been complied with because in reality no offer to pay costs had been made.
59 The situation created by the Offers of Compromise was no different to that which eventuated, ie judgment being entered for a figure less than $225,000. Before the plaintiffs are entitled to any costs in this matter, they have to persuade the Court that they had sufficient reason for commencing proceedings in the Supreme Court. Put another way, if the submission by the plaintiffs were correct, defendants in a Supreme Court action would be precluded from making an Offer of Compromise where the monetary amount nominated was less than $225,000. This is because any offer to pay the costs of a plaintiff could never satisfy SCR Part 22. There is no justification for so interpreting either SCR Part 22 or Part 52A r 22.
60 On behalf of ENS, it was submitted that I should apply Schedule 6 (Savings Transitional and Other Provisions) of the Uniform Civil Procedure Rules (2005) (UCPR) s5 of which provides:
"5(1) Subject to sub-clause (2), this Act and the Uniform Rules apply to proceedings commenced before the commencement of this Act in the same way as they apply to proceedings commenced on or after that commencement.
(2) A Court before which proceedings have been commenced before the commencement of this Act, may make such orders dispensing with the requirements of the Uniform Rules in relation to the proceedings, and such consequential orders (including orders as to costs), as are appropriate in the circumstances."
61 If the UCPR applied, Part 42 r 42.15 entitles a defendant to costs assessed on an indemnity basis where a plaintiff fails to obtain a judgment which is as favourable or less favourable to the plaintiff than an Offer of Compromise made by a defendant. ENS submitted that the plaintiffs should pay the costs of ENS on an indemnity basis from the date of the first Offer of Compromise, 25 June 2003.
62 Although the transitional provisions of the UCPR allow such an order to be made, in my opinion the circumstances of this case do not justify it. At the time when both Offers of Compromise were made such offers were governed by the provisions of SCR Part 22 and Part 52A r 22. The consequences of a failure to accept Offers of Compromise were clearly set out by those rules. Accordingly, it would be unduly harsh to the plaintiffs to invoke to their disadvantage rules which were not in force at the time when the Offers of Compromise were made and refused.
63 In that regard I note that s10 of Schedule 6 UCPR authorises such an approach.
"10. Subject to this Schedule and the regulations:
(a) anything begun before the commencement of this Act or the Uniform Rules under a provision of the old legislation for which there is a corresponding provision in this Act made be continued and completed under the old legislation as if this Act had not been enacted, and
(b) subject to paragraph (a), anything done under a provision of the old legislation for which there is a corresponding provision in this Act or the Uniform Rules (including anything arising under paragraph (a)) is taken to have been done under the corresponding provision of this Act or the Uniform Rules, as the case requires."
64 That does not end the matter. After the Offer of Compromise of 8 April 2004, a number of other offers were made. These purported to be Calderbank offers. ENS submits that the refusal to accept any of those offers by the defendants was unreasonable and that consequently it should have its costs paid on an indemnity basis from the date of those offers. It also relies upon the letters accompanying the Offers of Compromise as constituting Calderbank offers.
65 I propose to disregard the offers of 28 October, 3 November and 14 December 2004. The first two offers were made on an inclusive of costs basis which did not enable the plaintiffs to accurately calculate what was being offered to them and I propose to disregard them. I also propose to disregard the offer of 14 December 2004 because at that time the plaintiffs may well have had false expectations as to their chances of success against ENS because of the admission of supply in the Defence filed on 11 May 2004.
66 The letters accompanying the Offers of Compromise did not in terms purport to be separate offers or to be made as Calderbank offers. No reference was made to indemnity costs. They would have been understood by the plaintiffs as being no more than explanatory of the Offers of Compromise. I find that they did not constitute Calderbank offers.
67 The offer of 12 September 2005, however, was effective as a Calderbank offer. Although the letter does not contain a reference to Calderbank v Calderbank and although it does not expressly refer to indemnity costs being claimed if the offer contained in it was not accepted, it still operated as a Calderbank offer. This is because the offer which it contained was made as part of a series of offers and counter offers which were clearly intended by the parties to operate as Calderbank offers. The considerations identified in Nobrega v The Trustees of the Roman Catholic Church (No 2) [1999] NSWCA 133 were clearly made out. The defendants gave to the plaintiffs 15 days within which to accept the offer. In the context of offer and counter-offer that was a sufficient amount of time to allow a considered decision to be made by the plaintiffs.
68 In the 15 September 2005 letter the defendants offered to settle the plaintiffs' claim on the basis that each party pay their own costs and that the defendants waive the benefit of costs orders which they had in their favour at that time. That offer involved a real compromise on the part of the defendants. A very detailed Bill of Costs had been forwarded to the plaintiffs which calculated the value of the costs orders in favour of the defendants at $134,711. Even allowing for the rejection of some of those amounts, it is clear that the burden of those orders was in excess of $100,000. At that stage 11 days of hearing had already been completed and the matter had been fixed for a further 10 days. The proceedings had been on foot since 2001. If the Offers of Compromise of June 2003 and April 2004 were effective, the defendants were agreeing to give up significant costs.
69 The refusal by the plaintiffs to accept that offer was unreasonable. By that time the plaintiffs must have realised (for the reasons set out in the principal proceedings) that they would not be able to prove supply by ENS of the contaminated HEP. The plaintiffs' credit had been seriously damaged in cross-examination. I had given clear indications (20 May 2005) of difficulties which they faced in maintaining important parts of their claim. The letter itself identified the costs orders against the plaintiffs, identified difficulties in their property damage claim, referred to the Offers of Compromise and also referred to the problems associated with recovering any costs because of the provisions of SCR Part 52A r 33.
70 The offer contained in the letter was significantly more favourable than the outcome achieved by the plaintiffs from the litigation. In those circumstances ENS is entitled to its costs on an indemnity basis from 15 September 2005.
71 It should also be noted that much of the hearing time was devoted to issues in relation to which the plaintiffs failed. In normal circumstances this would be relevant to costs and would favour the defendants. In view of the conclusions which I have reached it is, however, not necessary to pursue that matter further.