INTEREST
1 HIS HONOUR: Before the Court is yet another contest between these two parties, this time concerning what allowance for interest should be made in respect of the verdict which the plaintiff has obtained against the defendant as a consequence of the adoption (with variations) of the report of Mr Easton of 23 May 2008.
2 The matter was last before the Court on 28 November 2008 when judgment was entered in favour of the plaintiff for $635,754.56, including $64,350.59 for interest, which the defendant conceded was the minimum amount owing.
3 The plaintiff, however, sought additional interest of $99,713.91.
4 I directed the parties to provide the Court with brief written submissions. The submissions they provided have been helpful. They do, however, reflect (as in the past) that neither party is prepared to give any quarter to the other.
5 The discretion to award interest on a verdict is now conferred on the Court by s 100(1) of the Civil Procedure Act 2005 (NSW) which provides as follows:
"In proceedings for the recovery of money (including any debt or damages or the value of any goods), the court may include interest in the amount for which judgment is given, the interest to be calculated at such rate as the court thinks fit:
(a) on the whole or any part of the money, and
(b) for the whole or any part of the period from the time the cause of action arose until the time the judgment takes effect."
6 In his report, Mr Easton found that of the amount for which the defendant was liable to the plaintiff, $161,446 plus GST was for damages for defective work; $10,000 was for an adjustment for incomplete work plus GST; and $12,600 was for liquidated damages calculated from the date for practical completion to the date of practical completion. These three amounts total $201,190 of the final amount owing (exclusive of interest) of $571,404.07.
7 During the course of the construction of the project, one of the claims which the defendant made on the plaintiff under the Building and Construction Industry Security of Payment Act 1999 (NSW) ("the Act") resulted in an adjudication by a Mr O'Mara on 10 March 2006 in the defendant's favour of $573,574, together with interest of $8,171.28 calculated from 30 January 2006 to 23 March 2006. The defendant proceeded to obtain judgment against the plaintiff in the District Court for the amount of $599,785.28 which included that interest and an allowance for adjudication fees and costs. Ultimately, and over time, the plaintiff paid the defendant $670,159.16 made up as to: O'Mara determination $573,574; O'Mara interest $8,171.28; interest on the District Court judgment $70,373.88; and adjudicator's fees of $18,040.
8 The plaintiff's approach to interest is, on the face of it simple. It says that the amount of the ultimate verdict in its favour is effectively a repayment of the O'Mara adjudication amount. It puts that its payment of the O'Mara adjudication amount was an overpayment and that it should be allowed interest on it at the Court rate from 30 January 2006 being the date of the final payment made by the plaintiff to the defendant in respect of the project.
9 The defendant resists this approach. It points out with some force that it simply cannot be the case that the award amount which the plaintiff has obtained is represented by the O'Mara adjudication. This is because the amounts found by the referee to be payable include (with GST) the amounts for defective work, for incomplete work and for liquidated damages totalling $201,190.60. It follows that of the O'Mara adjudication amount, only $370,213.47 is capable of being attributed to an overpayment (ie, $571,404.07 minus $201,190.60).
10 The defendant further puts that the plaintiff's claim was not one for restitution of the O'Mara adjudication amount, and that the referee did not approach it on that basis.
11 The referee's approach was to work out the amount paid by the plaintiff to the defendant to work out the adjusted contractual amount including damages payable by the defendant to the plaintiff and to deduct that amount from the amount paid, leaving a balance of $736,263.77 - which itself was subject to an agreed adjustment resulting the final verdict figure which was entered in favour of the plaintiff on 28 November 2008. In addition, the defendant submits that the plaintiff's claim did not include one for restitution of interest paid. It puts that amounts paid as interest on the District Court judgment cannot now be claimed by the plaintiff.
12 It seems to me that there is some merit on both sides of the argument. On the one hand the plaintiff paid more than it owed the defendant. In the ultimate reckoning, the defendant owed it money including for damages. On the other hand it is clear that the ultimate result is neither in form nor substance a verdict for the restitution of the O'Mara adjudication amount.
13 The purpose of an award of interest, which is a discretionary matter, is to permit a successful party to be properly compensated for the practical loss it has suffered.
14 On the approach which I have decided to adopt, it does not seem to me that any of the difficulties which each party places in the way of the other are real ones.
15 Following the approach of the referee, it seems to me that the exercise which will result in the fair and just outcome with respect to interest is as follows: that the plaintiff be entitled to interest at 9 per cent per annum on amounts which it paid beyond the figure which is reached by taking the full amount paid by it to the defendant, less the amount of $571,404.07, such interest to be calculated on the amounts paid beyond the result of that calculation from the dates that the payments were made by the plaintiff.
16 For example, if the amount finally paid by the plaintiff is $12,500,000, one would deduct from that $571,404 which would leave $11,928,596. Assuming on 1 January 2007 the plaintiff had paid to the defendant $11,928,596 and the day thereafter it paid it a further $1,000, it will be entitled to interest at the rate of 9 per cent on that $1,000 from the date of the payment to the plaintiff until the date of the defendant until the date the defendant pays it back.
17 I have adopted the figure of 9 per cent to take account of certain of the contingencies and the realities of the present economic situation.
17 DECEMBER 2008
INTEREST
18 The plaintiff has carried out an interest calculation in accordance with my reasons of 12 December 2008.
19 There is no issue between the parties as to the accuracy of the calculations which have been made on the stated basis.
20 The result of those calculations is that the plaintiff is entitled to interest of $74,973.89 rather than the $64,350.59 already ordered, a difference of $10,623.30.
21 The plaintiff is accordingly entitled to an ultimate verdict of $646,377.86 for which there will be judgment. The judgment of 28 November 2008 will be varied accordingly. Short minutes are to be brought in.
22 Mr Taylor of senior counsel on behalf of the plaintiff made a submission that in addition to the verdict referred to above the plaintiff was entitled to a further allowance of $78,545.16 for interest which it had paid to the defendant on the O'Mara determination and $18,040 which it paid as adjudicator's fees. It was put that there had been a slip on its part which translated into a slip reflected in paragraph 20 of my judgment of 19 November 2008 which refers to an agreed adjustment which the plaintiff says includes the aforesaid amounts. The plaintiff puts that by agreement the parties excluded those amounts from the final determination of the referee and that s 32(3)(a) of the Act requires the Court to allow for it in the order which the Court makes in these proceedings.
23 Section 32(3) is in the following terms:
" 32 Effect of Part on civil proceedings
(3) In any proceedings before a court or tribunal in relation to any matter arising under a construction contract, the court or tribunal:
(a) must allow for any amount paid to a party to the contract under or for the purposes of this Part in any order or award it makes in those proceedings, and
(b) may make such orders as it considers appropriate for the restitution of any amount so paid, and such other orders as it considers appropriate, having regard to its decision in those proceedings."
24 Mr Taylor accepted that there may be difficulty with the submission concerning the adjudication fees as being a matter that was required to be taken into account in the proceedings.
25 Mr Feller of senior counsel for the defendant, took the position that the defendant was not now in a position to deal with any slip rule application and would wish to put on evidence which might involve relying on agreements between counsel.
26 Ultimately the plaintiff was content for this aspect not to be dealt with at this time, on the basis that if it was later advised to bring a slip rule application it would do so, and that it would consider its position after the Court had dealt with costs.
COSTS
27 The question of costs was fully contested. The primary position of each party was that the other should pay all of its costs. Argument on costs took up a significant part of a day.