REASONS OF THE PRIMARY JUDGE
20 The primary judge accepted that s 82 of the Trade Practices Act 1974 (Cth) (the TPA) is analogous to s 49(1)(b) of the BCII Act (Reasons at [134]). In this regard, s 82(1) of the TPA provided:
Subject to subsection (1AAA), a person who suffers loss or damage by conduct of another person that was done in contravention of a provision of [a] Part ... may recover the amount of the loss or damage by action against that other person or against any person involved in the contravention.
21 The primary judge said (Reasons at [136]-[137]):
136 The statutory enquiry is as to actual damages suffered "by conduct of another person" (TPA s 82) or "as a result of the contravention" (BCII Act s 49). As to s 82 TPA common law and equitable remedies to compensate for damages suffered whether in tort, contract or otherwise, whilst they may be helpful are not determinative: Marks v GIO Australia Holdings Ltd (1998) 196 CLR 494. This too, in my opinion, is apt in respect to the BCII Act s 49.
137 Accordingly, the applicant here [is] requires[sic] to establish actual damage suffered by Diploma caused by the contraventions by the Respondents. The applicant has to prove that the damage suffered was a result of the contraventions on the balance of probabilities: Imperial Chemical Industries of Australia and New Zealand Ltd v Murphy (1973) 47 ALJR 122.
22 In assessing the quantum of compensation payable to Diploma, the primary judge considered the main objects of the BCII Act. His Honour said (Reasons at [149]-[150]):
149 In terms of the main object in s 3(1) of the BCII Act, Diploma is a building industry participant which is entitled to have its building work carried out fairly, efficiently and productively, free from unlawful industrial action. If it suffers damage as the result of a contravention, it should be compensated for that damage. Section 3(2)(b), (c) and (d) of the BCII Act are relevant here:
(2) This Act aims to achieve its main object by the following means:
(b) promoting respect for the rule of law;
(c) ensuring respect for the rights of building industry participants;
(d) ensuring that building industry participants are accountable for their unlawful conduct.
150 If Diploma had brought its own separate proceedings seeking compensation, it would have been no answer for the respondents to say that they had already been ordered to pay penalties to the Commonwealth.
23 Loss of an amount of the early completion bonus as a result of the industrial action was the major component of the ABCC's claim. The primary judge accepted at Reasons [171] the evidence of Mr Schober, a senior employee of Diploma, that on the five days in question some of the subcontractors on the site were required to perform "critical path" work being the sequence of activities that had to be completed on schedule for the entire project to be completed on schedule. Each task on the "critical path" was critical to the timing of the completion of the project. If a task on the "critical path" was delayed, then the entire project would be delayed by at least the same amount of time.
24 The primary judge also made the following findings at Reasons [172]-[173]:
172 Moreover, Mr Paul Day, Diploma's Project Manager who had day to day responsibilities for the Project at the Site, gave evidence to the same effect, at least concerning D&Z and Wards, when cross-examined during the interlocutory hearing on 17 July 2009. It was part of his job to deliver the Project on time. He said that there is no allowance in the construction timetable for "critical path" work to be delayed and that as a result, if "critical path" work is delayed by 1 day, the completion of the Project will be delayed by 1 day.
173 Significantly Mr Buchan agreed that these 3 sub-contractors performed critical path work on the Site and that their workers had taken industrial action.
25 Mr Buchan's evidence was "significant" because he was an officer of the CFMEU who gave evidence on its behalf. Indeed, he was himself a respondent to the ABCC's claim for penalties.
26 The primary judge dealt with the CFMEU's contention that Mr Schober's evidence was merely "theoretical" at Reasons [174-[176]:
174 The respondents point to the evidence of Mr Schober in cross-examination which, they contend, is to the effect that the asserted delay of 5 days was "theoretical". The evidence was as follows:
MS VERNON: So is that five days after 15 April?---No, not five days after 15 April, between 10 and 15 April, when the project, theoretically, could have bee[sic] finished, without five days delay.
So it's the cost of them for five days between 10 and 15 April 2010, that you say is the add-on cost; is that right?---Well, the costs - those costs were incurred on those particular days, on 5, 6 and 8 and 24 and 25 June.
Yes, but the evidence you just gave us is that you needed to have those people for another five days between 10 and 15 April 2010, to make up for the five days worth of industrial action - - -?---Correct.
- - - previously. But, of course, those people had worked on those five days, so you're talking about, now, some cost at the end; is that right?---Correct.
Well, the invoices that you have attached to your affidavit, though, Mr Schover[sic], they're not for the period from 10 to 15 April 2010, are they?---No.
They are actually their costs for the days that they were scheduled to work?---Correct.
So how can you actually say that they were required for another five days, between 10 and 15 April?---Because if there wasn't a five day delay on the job, the job would have been finished on the 10th and they were still working there on the 15th.
How do you know that? How do you know the job would have finished on the 10th?---Only by the - by reviewing, possibly, the program, which if you've got a five day delay in the middle of the job, unless it's - unless that time is made up you're going to incur that delay at the end.
So are you saying that in this case the time was never made up?---Correct.
175 The applicant submits, and I accept, that the effect of this evidence is that, but for the delay, the Project would have finished 5 days earlier. There is nothing "theoretical" about this statement. It is only "theoretical" in the sense that it was based on an hypothesis - what would have happened if there had been no industrial action.
176 The applicant's case assumes, favourably to the respondents, that the workers from the 3 sub-contractors performing critical path work were able to "pick up where they left off" immediately upon their return to work.
27 His Honour held that, because work on the "critical path" could not be performed on any of the five days of the industrial action, the project was completed five days later than it would otherwise have been completed: Reasons at [182]. That delay of five days caused Diploma to suffer actual damage by reason of the reduction in the value of its contractual entitlement to be paid a bonus of $9,000 per day for every day that the project was completed before 29 April 2010. It was irrelevant that the project was in fact finished ahead of the contractual date for Practical Completion, save for the enlivening of the possibility of the early completion bonus. But for the industrial action, Diploma would have achieved Practical Completion of the project five days earlier than it did. Accordingly, his Honour was satisfied that Diploma suffered damage of $45,000 under this head of compensation.
28 The primary judge then addressed a claim for the extra cost of Diploma staff. This claim was for the costs of employing staff for a period of five days longer on the project at the Diploma project site than would have been the case but for the admitted contravention. The total claimed was $7,991.96.
29 His Honour allowed the extra cost of employing site-manager Mr Davis, OHS Representative, Ms Sherrell, and site clerk, Mr Newbound. His Honour declined to award compensation for the cost of employing Mr Day. In this regard, his Honour said (Reasons at [189]):
189 Mr Day left the employ of Diploma more than three months before the completion of the Project. I am not prepared, absent other evidence, to infer that there was another Project manager employed on Site during those five days at the end of the Project. It follows that I would award compensation only in respect to the other three in the sum of $4,608.36 calculated as follows:
$
Site Manager: L Davis 1446.22
OHS Rep : L Sherrell 1993.52
Site Clerk: M. Newbound 1168.62
4608.36
30 Compensation was also claimed for extra payments to Hays Recruitment for the provision of casual labour (additional to Diploma's subcontractors and direct employees) for work on the last five days of the Diploma project. This work involved:
(a) site cleaning;
(b) safety compliance rectification;
(c) traffic management;
(d) Alimak operation; site logistic activities; and
(e) general housekeeping.
31 His Honour accepted the evidence of invoices from Hays Recruitment totalling $16,865.49 (Reasons [191]) and allowed this claim in full, saying at Reasons [193]:
193 For reasons I have already stated, I do not regard this evidence as based upon his "theory" that the Project was delayed by 5 days. [Mr Schober's] evidence as to this was as to matters of fact within his knowledge. I consider it reasonable to infer that the daily cost of recruiting this staff for the additional five days was not less than during the five days of the industrial action. I would allow this claim in full.
32 The material handling and scaffolding costs consisted of the cost of a tower crane, two Alimak hoists and a forklift which were on site on the days of the industrial action, together with scaffolding. The invoices for the five days totalled $9,707.51. The primary judge accepted that, but for the five days lost, each of these items of equipment would have been returned to the owner five days earlier. Accordingly, these costs were also allowed at Reasons [196].
33 The next claim by the ABCC was that, as a result of the industrial action, Diploma was required to engage the services of Deacons, a firm of lawyers, to provide advice relating to the CFMEU's industrial action and to assist the ABCC in the prosecution of its claim against the CFMEU. This claim was for $21,514.05.
34 The primary judge allowed this aspect of the claim. His Honour said at Reasons [204]-[206]:
204 There will ordinarily be a question as to whether the legal costs were reasonably incurred. I consider that Diploma acted reasonably in obtaining the legal advice and assistance which it did from Deacons. I am satisfied that, but for the contraventions by the respondents, there would have been no necessity for that to have occurred. In my view, Diploma was entitled to obtain that advice in relation to its rights and remedies and in particular to assist the applicant in the claim, in effect made on behalf of Diploma in these proceedings, for compensation. I accept the submission of the applicant that to the extent that the work done by Deacons assisted these proceedings, as I find that it did, then the costs of the applicant have, to a considerable extent, been reduced. The applicant will not be entitled in its claim for costs in these proceedings to claim for costs for work done by Deacons. Diploma, on the other hand, is not a party to the proceedings and is accordingly unable to obtain a costs order in its favour in respect of them. I find that the work done by Deacons was reasonably incurred by Diploma in assisting the applicant both to prove the contraventions of the civil penalty provisions in order to establish statutory liability against the respondents to pay compensation under s 49(1)(b) of the BCII Act.
205 The costs incurred by Diploma with Deacons are properly characterised as damages. The fact that Diploma, "chose" to get that legal advice does not, contrary to the respondents' submission, break the chain of causation. Indeed that very choice I regard as a quite reasonable decision on the part of Diploma to assist the applicant who was running an action for both civil penalties as well as for compensation which would be payable to Diploma. That course seems to me to have been quite a sensible approach in combining the claims in one action rather than in separate actions which could have occurred. Indeed had that alternative course been followed it may well have resulted in greater costs to the respondents having to confront two separate actions. This would likely also have occasioned greater cost to the Court.
206 The statutory entitlement for compensation under s 49(1)(b) of the BCII Act can only be realised if the person which suffers damage is able to put together the evidence to support its claim, both in terms of establishing the contravention and the resulting damage. It is, in effect, a means of achieving the statutory object under s 3(1) of the BCII Act to facilitate such claims: s 3(2)(b), (d) and (3)[sic]. Diploma's legal costs are damage suffered as a result of the contraventions the subject of the proceeding and are in my opinion compensable under s 49(1)(b).
35 The primary judge rejected a submission by the CFMEU that Diploma had failed to take steps necessary to mitigate its losses by pursuing claims for recompense from the sub-contractors whose employees had taken the industrial action which disrupted the project.
36 In summary, his Honour ordered that compensation be paid to Diploma in the amount of $97,695.41 consisting of:
$45,000 - loss of early completion bonus;
$4,608.36 - extra wages of Diploma employees;
$16,865.49 - extra hire costs of Hays Recruitment temporary personnel;
$9,707.51 - extra hire cost of equipment;
$21,514.05 - legal costs paid by Diploma to Deacons.