is there a serious question to be tried?
31 On the current state of authorities, although the High Court in Cardile recommended that asset preservation orders of the Mareva type not be described as injunctions, it is still necessary for a court to make an assessment of whether there is a serious question to be tried and, so far as may be possible, to assess the strength of an applicant's case. In this matter the relevant case is the Principal Application.
32 Nearly all of the evidence in relation to the Principal Application comes from the applicant whose affidavit evidence at this stage remains largely unchallenged, in the sense that no affidavits alleging contrary facts have been filed. But Mr Neil McLennan, Senior Development Manager of MAB, who is also the Development Manager of the first respondent, has sworn an affidavit in opposition to the motion. Mr McLennan, in part of his affidavit, gives particulars of a claim by the first respondent against the applicant for liquidated damages under the Contract of at least $5,420,000 said to have been incurred by delays on the applicant's part in achieving practical completion.
33 Mr McLennan's affidavit shows what the first respondent contends is the position as at 18 October 2002 in relation to achieving practical completion of the building works. He explains that practical completion has been delayed by 271 days. The rate of liquidated damages provided for in the contract is $20,000 per calendar day.
34 It would appear from affidavits filed on its behalf that the applicant has claimed extensions of time amounting to a total of 272 days. The applicant has claimed $4,300 per day for delay costs. Some, but not all of the extensions of time claimed relate to the removal of asbestos. These claims and other claims deposed to by the applicant's officers, which are disputed by the first respondent are said to amount in total to $4,034,106. According to Mr McLennan's affidavit, PPM as the Superintendent under the Contract, which it will be recalled is the second respondent in the Principal Application, has decided that the applicant should only be entitled to an extension of time of 9.75 days. As this is less than the provisional delay period of 20 days, the position of the first respondent and the Superintendent is that the applicant is not to be allowed any extensions of time.
35 Thus, by way of rough approximation, if the first respondent is wholly successful in relation to its claim for liquidated damages, presumably by way of cross-claim in the Principal Application, or by way of arbitration, it will recover about $5.4 million. If the applicant is wholly successful in establishing its claims then it will recover about $4 million. As Mr M J Badman deposes in paragraph 28 of his affidavit, the applicant's projected loss on the Contract of $5.15 million will be reduced by the extent to which it is successful in relation to those claims, but will be increased to the extent that the first respondent is successful in recovering liquidated damages.
36 There is no basis upon which I can assess the relative strengths of the respective claims in relation to liquidated damages, extensions, delay costs and the like under the Contract. The best that I can do is to note the approximate range of possible outcomes.
37 The applicant's main affidavit in relation to the Principal Application was sworn by Mr Andrew Peppercorn, its Managing Director. That affidavit runs to some 536 paragraphs and, as might be expected, gives a very detailed and precise recitation of the applicant's case.
38 In my view, it is quite clear that the applicant has established that there is a serious question to be tried on the issue of misleading or deceptive conduct as between the applicant and the first respondent. The representations about the limited presence of asbestos (on which the claims are largely based) were in writing and there does not seem to be any dispute that they were made. The applicant's evidence about the actual extent of the asbestos which was found in the Building and the problems which that caused has not been challenged in these proceedings. However, there are disputes between the parties (considered immediately below) which go to the issue of liability. I do not find it possible, at this stage, to form any assessment of the strength of the applicant's case other than to say that, on a prima facie basis, it has substance. I return below to the issue of damages in the Principal Application.
39 There were two other matters which Mr Colvin advanced in relation to the merits of the Principal Application.
40 First, he submitted that there was a real issue as to the first respondent's responsibility for what took place before 15 December 1999 when it took over the role of Principal (from Aherns Holdings Pty Ltd) in the negotiations which led to the execution of the Contract. Mr Colvin pointed out that there was no allegation that the first respondent itself had made any representations about the asbestos in the Building.
41 I acknowledge that this is a hurdle which the applicant faces. However, I do not see it as an insurmountable problem. The evidence is that as early as 7 September 1999, Mr Andrew Buxton of MAB was being kept in touch with the post-tender negotiations. On that date PPM asked the applicant to let it know what allowance it would require to the tender price for a guaranteed maximum price in respect of asbestos removal or hazardous material. The applicant may well, at trial, be able to persuade a court that the conduct of the first respondent from 15 December 1999, taken in the context of the representations which had been made earlier by PPM (which became its project manager) and, in particular, its conduct leading up to the execution of the Contract may in all the circumstances have amounted to misleading or deceptive conduct.
42 Next it was submitted on behalf of the first respondent that the applicant's claim for damages amounting to about $5 million was based on the premise that, but for the misleading or deceptive conduct, it would never have entered into the Contract, as Mr Peppercorn had sworn. Mr Colvin submitted that the evidence did not support the proposition that the issue about asbestos was a "make or break point". He referred me to paragraph 112 of Mr Peppercorn's affidavit which is to the effect that if the applicant had been aware of the problems relating to friable asbestos, it would have qualified its tender. I note also paragraph 56 of Mr Peppercorn's affidavit which gives an indication of the keenness of the applicant to win this Contract. On the other hand, as Mr M W Odes QC, who with Mr A N Siopis SC appeared for the applicant, submitted, there is room for an inference that had the applicant qualified its tender, the first respondent would have rejected the qualification and the Contract would not have been entered into.
43 I accept Mr Colvin's submission that I should take into account and make some allowance for the possibility that the applicant will not be able to make good its claim for the total loss.