Compagnie Francaise D'Assurance Pour le Commerce Exterieur t/as Coface Australia v Sims Group Australia Holdings Ltd
[2013] NSWCA 418
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2013-11-01
Before
Barrett JA, Ward JA, Hunter J
Source
Original judgment source is linked above.
Judgment (13 paragraphs)
12 00:00:00 Before: Walmsley DCJ File Number(s): DC 2011/024652
Judgment 1BARRETT JA: The orders proposed by Ward JA should be made for the reasons her Honour gives. 2WARD JA: The appeal before this Court involves a dispute arising out of a claim made by the respondent (Sims) on a trade credit insurance policy taken out by it with the appellant (Coface), which claim was denied by Coface. The primary judge held that Coface was liable under the policy in the amount claimed by Sims. Coface appeals from that decision both as to liability and quantum.
Background 3In June 2008, Sims sold its steel distribution business to another company, 7 Steel Pty Ltd. Sims and 7 Steel entered into an Agreement for Sale of Business on 24 June 2008 (Blue 25). Completion of the sale was due, and took place, on 30 June 2008 (clause 1.1 and Item 2 of Schedule 1). 4The sale included sale of the "Stock", defined in clause 1.1, relevantly, as meaning "the raw materials, work-in-progress and finished stock used or to be used in relation to or as part of the Business whether or not located on the Premises ...". As part of the sale of the business, arrangements were made for 7 Steel to take over the lease of various of the premises then leased by Sims (recital C, clause 6 and Item 4 of Schedule 1). (This is of some relevance in that at least some of the pre-completion purchase orders relating to the dispute nominated delivery to premises then leased by Sims but which, by the time specified for delivery, were occupied by 7 Steel.) 5The contract provided for payment of both a Purchase Price for the business ($2.5 million plus the written down value of the Plant and Equipment, but not including the Stock Price, as specified in Item 6 of Schedule 1) and a Stock Price, defined in clause 1.1 of the agreement as "the sum of money being the value of the Stock calculated in accordance with clause 4". Those amounts were payable in tranches pursuant to clause 7.5. Relevantly, the final tranche (being the balance of the Stock Price after payment of part of that amount in the earlier two tranches) was due pursuant to clause 7.5(b) on or before the date 180 days after completion (i.e., on or before 27 December 2008). 6Pursuant to clause 7.5(d) of the agreement, 7 Steel was required, as security for payment of the amounts referred to in clause 7.5(b) (those being amounts referable solely to payment of the balance of the Stock Price) to grant a first ranking floating charge over the Stock and all future raw materials, work-in-progress and finished stock used or to be used in relation to or as part of the business as conducted by it. The Charge was to be in the form of that annexed to the agreement (Blue 153). 77 Steel duly executed a Deed of Charge on 1 July 2008 (Blue 191), pursuant to clause 2.1 of which 7 Steel charged all of the Charged Property (defined as all of its present and future right title and interest in any Stock) in favour of Sims as security for payment of the Moneys Owing. That term was defined in clause 1.1 as meaning: all moneys and amounts which at any time for whatever reason or circumstance (whether or not within the contemplation of the parties at the date of this charge) [are] owing or remaining unpaid to [Sims] by [7 Steel] under or in connection with the Sale Agreement. (my emphasis) 8The Sale Agreement was defined, not surprisingly, as the agreement for the sale of business entered into on or about the date of the charge (clearly a reference to the agreement dated 24 June 2008 pursuant to which 7 Steel purchased Sims' steel distribution business). The maximum liability secured by the Charge was $50,000,000. 9Prior to the sale of its business, Sims had placed various orders for the delivery of steel from one of its suppliers, ThyssenKrupp Mannex (TKM), the delivery (and payment) dates for which fell due after completion of the sale of the business. In the case of two of the orders, payment was not due until after the date for payment by 7 Steel of the last tranche of the Stock Price. I will refer to such orders as the pre-completion purchase orders. 10It appears that on or before completion of the purchase, 7 Steel notified TKM of its acquisition of the business, because on 30 June 2008 TKM notified 7 Steel that, as it did not have any previous records on the "new owner" (i.e., 7 Steel), "all future deliveries have been put on hold subject to discussion with [TKM's] credit insurer" (Blue 185). In its letter, TKM suggested by way of an alternative that 7 Steel provide it with a third party security such as a bank guarantee, in which case it said it would be able to continue with the deliveries. It also advised that it would start to re-sell the material to alternative customers if it did not hear from 7 Steel by 11 July 2008. Hence, from 7 Steel's part, there was some urgency in resolving the problem with deliveries. 11Rather than taking up the suggestion that it provide third party security for TKM deliveries, 7 Steel asked Sims to assist it to obtain the supply of the pre-completion purchase orders. Sims agreed to do so (Blue 213), seemingly as a gesture of goodwill (and to pre-empt problems arising with payment of the subsequent payments due under the sale agreement) since the view taken within Sims was that there was no contractual obligation (presumably referring to a contractual obligation vis-à-vis 7 Steel, not vis-à-vis TKM) on Sims' part in relation to pre-completion purchase orders (Blue 384). 12The form that the assistance from Sims took was that Sims agreed to take delivery of the steel the subject of the pre-completion purchase orders from TKM and then to on-sell that steel to 7 Steel at cost plus a margin of $50 per tonne or part thereof (Blue 214 records Sims' internal advice to this effect in relation to the July deliveries). This arrangement was replicated for the balance of the TKM deliveries by which time 7 Steel had received legal advice (on 22 July 2008) that strategically it was far better for Sims to be the "enforcing party" in relation to the TKM orders because if 7 Steel became the "Customer" instead of Sims it was arguable that under TKM's Terms and Conditions TKM could terminate the supply arrangements and refuse delivery. Reference was made in that advice to clause 11(1) of those Terms and Conditions which, among other things, gave a right of termination if TKM received notice of circumstances which in its opinion reduced the customer's creditworthiness (Blue 274). 13It was a condition of Sims' agreement to enter into the on-sale arrangements that a trade credit insurance policy be taken out (at 7 Steel's expense) to cover its risk that 7 Steel would default on payment of amounts due to Sims for the steel the subject of those on-sale arrangements. 14Ultimately, three Product Sales Agreements were entered into between Sims and 7 Steel, setting out the arrangements between them for the on-sale of the steel in question (Blue 246; 288; 292), the first being on 15 July 2008. Those agreements are referred to in the primary judgment as the TKM contracts and, for consistency, I will so refer to them in these reasons. Those agreements expressly provided that, to the extent of any inconsistency, they were to override the 24 June 2008 business sale agreement (clause 6.4 of the respective agreements). 15The trade credit insurance that had been required as a condition of Sims' agreement to assist in relation to the TKM pre-completion purchase orders was duly taken out. On 14 August 2008, Coface issued a trade credit insurance policy dated 11 August 2008 in favour of Sims (Blue 302-312). The policy took effect from 1 July 2008 and covered the period to 30 June 2009. The policy covered a single risk buyer, 7 Steel, and insured against the non-payment by it of debts (defined as the "amount of one or more invoices owed by the buyer under a sales contract and falling within the scope of this agreement"), including non-payment due to insolvency of the buyer. The term "sales contract" was in turn defined as being "[a]ny agreement in any form which is legally binding upon the buyer and the seller and which is for the sale of goods or services against payment of a price". It was not suggested that the TKM contracts did not fall within the definition of "sales contract" in the policy. 16Meanwhile, Sims notified TKM (Blue 269), by letter dated 21 July 2008, that it required performance of the pre-completion purchase orders and sought confirmation that TKM was "proceeding to discharge its obligations under the Sale Contracts in accordance with their terms". 17By late November 2008, 7 Steel considered that there were "some serious issues with regards to amount which may well be owing to Sim's [sic] pursuant to the Asset Sale Agreement and to the various stock transactions which have been carried out subsequently between the Companies relating to TKM and to [other products]" (email dated 24 November 2008 from the chairman of 7 Steel's holding company, Mr Hill Blue 389). In particular, issue was taken by Mr Hill as to the arrangements that had been agreed in the TKM contracts (he apparently seeking to revisit the terms of that agreement). Mr Hill asserted, among other things, that Sims had a duty to pass on the benefit of the forward orders without profit; not to take the benefit of a rebate arrangement with TKM; and was not entitled to demand insurance cover for the transaction noting that there was an indemnity relating to "this specific issue" in clause 4.1(c) of the sale of business agreement. By that last comment, it appears that 7 Steel was taking the position at that stage that the indemnity in clause 4.1(c) covered the cost of steel ordered by Sims under the pre-completion purchase orders and purchased by 7 Steel under the TKM contracts. 187 Steel's position, as then communicated to Sims, was to confirm that it would be making payments "as due" pursuant to the various TKM transactions (i.e., the TKM contracts) but to advise that "the payments are made on account and are without prejudice". The first payment, for the July deliveries, was due on 25 November 2008. 7 Steel advised that there were further amounts due over the coming months from which 7Steel would be seeking deductions. 19Sims rejected the complaints made as to entry into the TKM contracts and made it clear that it considered 7 Steel could not walk away from those contractually binding agreements (Blue 387). 20It was against that background that arrangements were made between Sims and 7 Steel in December 2008 in relation to the forthcoming payment due for the balance of the Stock Price pursuant to clause 7.5(b) of the sale agreement; i.e., the final payment tranche. 7 Steel's lawyers (Turtons) sought confirmation on 12 December 2008 that on the making of that payment an ASIC form for the release of the charge (form 312) and deed of release would be handed over (Blue 404). The lawyers acting for Sims (Dibbs Abbott Stillman) responded by agreeing that at settlement a release of the charge would be handed over (Blue 402). 21Clause 8.5 of the charge provided that: [Sims] will be under no obligation to grant a release of the Charged Property from this Charge unless at the time the release is to be provided, none of the Moneys Owing i.e., including all amounts owing or remaining unpaid by 7 Steel to Sims under or in connection with the Business Sale Agreement is owing (whether actually, contingently, or prospectively) and it is not reasonably foreseeable that there could be any Moneys Owing in the future. 22A query was raised within Sims as to the legal implications of releasing the charge, including any such implications in relation to the TKM debts (Blue 401). The response from Sims' director (Mr Nelson) was that the charge over the stock would be released when the balance of the purchase price was received and that the TKM contracts "run their ordinary course - we're covered by credit insurance and we keep the rebate and the $50 per MT". Coface later pointed to this comment in contending that Sims had breached its obligation to act as a prudent uninsured. 23The charge was released on 15 December 2008 at the time the balance of the Stock Price was paid. 24During the course of 2009, there were ongoing disputes between 7 Steel and Sims as to set-offs claimed by 7 Steel in relation to the amounts it acknowledged were due under the TKM contracts. It is not disputed that during this period various amounts were paid to Sims that were referable to TKM deliveries, though (as noted above) 7 Steel had indicated that the payments would be made "on account" and "without prejudice" and that it would be seeking deductions therefrom. 25By letter dated 30 January 2009, Turtons wrote to Dibbs Abbott Stillman in connection with the outstanding matters in dispute between their respective clients, including the TKM arrangements. In that letter, Turtons recorded that 7 Steel maintained its entitlement to the sum of $994,476 as set out in the 24 November 2008 email to which I have earlier referred (at [17]) and noted 7 Steel's intention to set off that sum against amounts "owing" for TKM stock as set out in a table of invoices. The invoices listed in that table included four particular invoices (invoices 1063, 1066 and 1072, which were due for payment on 29 January 2009 and invoice 1015, which was due for payment on 8 February 2009). I will refer to them collectively as the four disputed invoices. The first three invoices totalled $259,073.08; invoice 1015 was in the sum of $27,902.93. 26On 10 March 2009, Sims issued a statutory demand in respect of the amounts it claimed were owing in relation to the supply of goods and services to 7 Steel. Of the four disputed invoices, only invoice 1015 (that was due for payment in February) was listed in the schedule of outstanding invoices set out in the affidavit accompanying that statutory demand (Blue 420). That is consistent with the fact that Sims' bank records show the receipt, from 7 Steel, on 29 January 2009 of a sum of $259,073.08 (that amount corresponding precisely to the total of the three invoices that had been payable in January) (Blue 412). The statutory demand also noted that there was a disputed amount of $994,476, referring to the Turtons' letter of 30 January 2009. 27There followed negotiations that led to the payment (without prejudice or admissions) of an amount by 7 Steel if Sims agreed to withdraw the statutory demand (Blue 423-425). On 26 March 2009, a sum of $1,033,854.04 was recorded in Sims' bank statement as having been received from 7 Steel (Blue 426). Relevantly, the remittance advice issued by 7 Steel in respect of that payment listed invoice 1015 as one of the invoices included as paid in the said sum (Blue 427). Subsequent statutory demands issued by Sims omitted reference to the 1015 invoice (Blue 433; Blue 447). 28Ultimately, Sims and 7 Steel resolved their disputes in relation to the TKM contracts by entry into a Deed of Release and Settlement made in around November 2009 (Blue 465). The recitals to that deed included that the "Invoices" (defined as those set out in Schedule 1 in the sum of $994,476.00) remained outstanding (Recital H). Schedule 1 included the four disputed invoices. 29Pursuant to clause 1 of the deed, it was agreed that 7 Steel would pay the sum of $750,000 in four instalments but also that if any instalment or part thereof was not paid within five business days of the due date then the amount claimed in the Invoices (less any amount paid pursuant to the deed) was immediately to become due and payable. 7 Steel made the first three of those payments (totalling $375,000). It failed to make the final payment of $370,000 due in February 2010. 7 Steel went into receivership on 1 March 2010. It was subsequently placed into liquidation on 10 August 2010. 30In May 2010, Sims submitted a claim under its insurance policy with Coface for the insured percentage (90%) of the amount of $619,476 that it claimed was the indebtedness of 7 Steel. An updated version of the claim form as at 18 April 2010 is at Blue 477. The details of the outstanding debt listed 7 invoices, totalling $619,476. Those invoices did not include the four disputed invoices. 31Following the refusal by Coface of Sims' claim under the policy, Sims commenced proceedings in the District Court, claiming (at [15]) that pursuant to the TKM contracts, the "Invoices" listed at [7] (which included the four disputed invoices), and the Deed of Release, 7 Steel was indebted to it in the amount of $619,476. That amount represented the total of the 14 invoices listed at [7] (totalling $994,476 and including the four disputed invoices), less the three payments that had been made by 7 Steel to Sims under the Deed of Release (i.e., the $375,000). 32Coface, by its Amended Defence filed in September 2011, pleaded that it had no liability to Sims under the policy. Among other things, it alleged that Sims had breached its obligation, under clause 2.1 of the General Provisions of the policy, to act as a "prudent uninsured", by releasing the charge over 7 Steel's assets on 15 December 2008 (paras [37]-[39]). It did not deny, but did not admit, that 7 Steel was indebted to Sims in the amount claimed by Sims (para [15] of the Amended Defence). 33In Sims' Reply, relevantly, it contended that 7 Steel's obligation to pay for steel supplied by TKM arose under the TKM contracts and not under the indemnity contained in clause 4.1(c) of the sale agreement ([8(3)]) but that, if it was required under the policy not to release the Charge, Coface's interests had not been prejudiced thereby.