The facts
5 In late October 2011, Bechtel (Western Australia) Pty Ltd (Bechtel) and ESS Thalanyji Pty Ltd (ESST) entered into a contract for ESST to provide operations, catering and maintenance services during the construction phase of the Wheatstone project, which involved the construction of an onshore facility that produces liquefied natural gas near Onslow, in the Pilbara region of Western Australia.
6 ESST commenced work under the contract in May 2012.
7 ESST initially engaged Delta Facilities Management Pty Ltd (another Compass Group company) to provide the maintenance services under the contract.
8 In mid-2017, the respondent took over the performance of those maintenance services. The employees who had been engaged by Delta Facilities Management Pty Ltd were "transferred" to the respondent.
9 No issue arises on this appeal about the effect of the transfer, because the primary judge found, and the appellant did not dispute on appeal, that each of the three employees the subject of the application was at all material times bound by relevantly identical contracts of employment. See the reasons of the primary judge at [63]-[66]. Where appropriate, references in these reasons to the respondent will include Delta Facilities Management Pty Ltd.
10 Originally the construction phase of the work that ESST was contracted to perform at Wheatstone was to finish around June 2017. After a number of extensions, in October 2017 the final "demobilisation date" was extended to 31 December 2018.
11 In August 2018, Bechtel notified ESST that provision of maintenance services under the contract would conclude on 30 September 2018. This meant that staff of the respondent were no longer required at the site.
12 On 31 December 2018, Bechtel issued a notice of final acceptance to ESST certifying that all maintenance services under the contract had been completed.
13 Mr Neil Cooper, Mr Timothy Redmond and Mr Robert Dickson (collectively, the employees) were all employed by the respondent to work at the Wheatstone project. On 30 September 2018, the respondent no longer required their jobs to be done by anyone and so their employment was terminated. They were not paid any redundancy payments.
14 Mr Cooper commenced employment with the respondent at the Wheatstone project in May 2013 as a full-time plumber.
15 Mr Redmond began working for the respondent in February 2012. At this time he was engaged to work at the Citic Pacific mine project at Eramurra in Western Australia on a full-time basis. At the end of July 2013, before that project had finished, the respondent told Mr Redmond that it had been unsuccessful in renewing its contract at that project. Mr Redmond was told that he would be redeployed to work at the Wheatstone project. He commenced employment with the respondent at the Wheatstone project in October 2013 as a full-time refrigeration technician.
16 Mr Dickson began working at the Wheatstone project in April 2014 as a casual electrician employed by another company. He was later engaged by the respondent as a casual electrician on the same project. In June 2015 he was offered a full-time contract of employment, which he accepted.
17 In early August 2018, each of the employees received a letter from the respondent informing them that they were being given two months' notice that the project was coming to an end; that the respondent would attempt to secure suitable alternative employment for them, but, if this proved unsuccessful, their employment would cease on 30 September 2018; and that they would be paid their final pay and accrued leave entitlements. The full text of the letter is set out in the reasons of the primary judge at [71].
18 In the events that occurred, the respondent could not find alternative employment for the employees.
19 Each of the employees gave evidence before the primary judge of their understanding or expectations about their employment with the respondent.
20 Some of the primary judge's findings in that regard need to be set out because they are relevant to the way that the appellant sought to argue the appeal.
21 Mr Cooper said that he was not made aware that his employment was on a project basis; that he was not provided with an end date for the project; that he was never made aware that his employment was temporary; that he believed that his employment was permanent because it was on a full-time basis; and that he believed that if the project ended, the respondent would redeploy him. He said that he was told that the respondent would always try to secure him alternative employment, and that he "did not think that [he] would not get a redundancy" if he were not redeployed. Mr Cooper also said that whilst he was not informed as to how long the project would take to complete, he was given verbal progress updates by management. He said that in July 2018 he and his crew were verbally advised that the project was winding up, and that he was repeatedly assured that the respondent would find him alternative employment if its bid for further work on the project did not succeed.
22 Mr Redmond said that when he began working at the Wheatstone project he was given a completely new contract which designated that his work would be at Wheatstone as a full-time refrigeration technician; that he was not told that his employment would cease at the completion of the project; that he was not provided with an expected timeframe as to when the project would be complete; that he formed a view that, when the Wheatstone project finished, he would transition to another position as had previously happened to him with regard to his work on the Citic Pacific mine project; and that he assumed that if the respondent's tender at Wheatstone was unsuccessful he would be redeployed, as had happened previously.
23 Mr Dickson said that because the project involved the construction of a mine he knew that it would end at some stage, but he did not know exactly when; that in his experience it was standard for redundancy payments to be paid to employees who stop working because a project has ended; that he believed that he would be transferred elsewhere once the Wheatstone project had ended; and that when he and his crew were told that they would finish their work at the project on 30 September 2018, he assumed that he would either receive a redundancy or be redeployed.
24 The employees also said that they had not read, or carefully read, their respective contracts of employment; that they did not understand what they, or a related enterprise agreement (to which reference is made below) relevantly provided for; and that the effect of the relevant provisions was not explained to them by the respondent. The primary judge held that such evidence was irrelevant, citing Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165 at 180-1 [45] (Gleeson CJ, Gummow, Hayne, Callinan and Heydon JJ). See the reasons of the primary judge at [109]-[110]. The appellant did not challenge the finding about the irrelevance of that evidence.
25 Each of the employees' contracts of employment relevantly provided in cl 3:
POSITION & WORK LOCATION
Your job title is …
You are employed on a Full Time basis under the classification …
Your site will be Wheatstone
During your employment, you may be required to work in another classification of work that is within your skills and competencies and the Company may transfer you to another work location which is reasonable. If your position or work location changes (other than on a temporary basis) you will be issued with a new contract.
26 Each of the employees' contracts of employment relevantly provided in cl 9:
CONTINUING EMPLOYMENT
The Company operates on sites under contracts between the Company and its clients. Your continuing employment is subject to the operational requirements of the Company's business, which is directly affected by the needs of our clients. You understand that continuous employment and wages, working hours or other conditions of employment cannot be guaranteed.
As a result of changes in operational requirements, there may no longer be a position for you at your current site. If that occurs, you may be given the opportunity, or required, to transfer to another location on different wages or other terms and conditions of employment. Any such changes will be discussed with you and, if agreement is reached, you will be given a new contract of employment.
If an alternate position is offered and not accepted by you, or if there are no suitable alternative positions available for you, the Company may terminate your employment by giving you notice (or payment in lieu) in accordance with this contract.
Termination of employment due to a change or loss of contract between the Company and a client is a usual reason for a change in the Company's workforce and is part of the ordinary and customary turnover of labour within the Company.
Under contractual terms between the Company and its client, a client may, at their sole discretion, withdraw your site access. In such circumstances, wherever practicable, the Company may relocate you to another site on similar terms and conditions or subject to such variations as are agreed, in writing, with you. However, where site access is withdrawn as a result of your refusal or neglect of duty, or serious misconduct, this may lead to disciplinary action or termination of your employment.
27 Each contract also contained an acknowledgement that the employee had read, understood and accepted the contract.