Commonwealth of Australia v Shenzhen Energy Transport Co Ltd
[2015] FCA 1273
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2015-11-18
Before
Mr J, Greenwood J
Catchwords
- ADMIRALTY - consideration of an application for leave to amend the reply of the Commonwealth of Australia in the proceeding
Source
Original judgment source is linked above.
Catchwords
Judgment (10 paragraphs)
Background 1 These proceedings concern an interlocutory application made by the applicant (the "Commonwealth") pursuant to r 16.53 of the Federal Court Rules 2011 for leave to amend the Commonwealth's reply filed on 9 July 2014. On 16 November 2015, the Court made orders granting leave to amend the reply and other directions. The parties were advised that reasons would be published within a few days. These reasons are the reasons in support of the orders made on 16 November 2015. 2 It is necessary to say something about the background to the present application. 3 In the principal proceeding, the Commonwealth pleads a general maritime claim under s 4(3)(a) of the Admiralty Act 1988 (Cth) for damage done to the Great Barrier Reef by the ship Shen Neng 1 arising out of the grounding of the ship on the Douglas Shoal "on 3 April 2010, at about 1710 hours": para 2, statement of claim. 4 The cause of action relied upon by the Commonwealth is the tort of negligence. The Commonwealth seeks to recover the loss and damage it says it has suffered (para 5, statement of claim) by reason of the extensive damage caused to the Douglas Shoal: para 4, statement of claim. 5 If the cause of action is made good, the Commonwealth seeks to recover all of the loss and damage flowing from the contended negligence of the respondent, the nature and extent of which is to be the subject of expert evidence at the trial: para 4, statement of claim. 6 The ship remained grounded for 12 days before ultimately being re-floated. The damage to the Great Barrier Reef is said to extend to an area between 80,000m2 and 400,000m2: para 4 of the statement of claim. 7 During the period of 12 days between the grounding and the re-floating, a number of steps were taken and things done in connection with the grounding and attempts to re-float the ship. 8 The respondent, by its amended defence filed on 23 June 2014, admits that the grounding was "caused solely by the negligent navigation of the Chief Officer of the vessel" but otherwise denies para 3 of the statement of claim which asserts that the said grounding was caused solely by the negligent navigation of the ship "by the servants or agents of the respondent". 9 The respondent, by its amended defence, pleads that it does not know and cannot admit the matters pleaded at paras 4 and 5 of the statement of claim. As to the cause of action in negligence, as pleaded against the respondent, the amended defence limits the negligence for which the respondent is said to be liable to the negligence of the Chief Officer alone. 10 By the amended defence, the respondent also pleads that having regard to factual assertions pleaded at paras 6 to 8 of the amended defence, the respondent is entitled to avail itself of a limitation of liability under the Convention on Limitation of Liability for Maritime Claims 1976 (the "Convention") adopted into the domestic law of Australia by the Limitation of Liability for Maritime Claims Act 1989 (Cth) (the "Limitation Act"), on the footing that Articles 2(1)(a) and (f), 6, 9(1) and 10 of the Convention and s 25 of the Admiralty Act 1988 (Cth) (the "Act") are engaged with the result that the respondent's liability is limited to the Convention limit as pleaded in the amended defence. 11 The pleaded matters at paras 6 to 8 are these: Limitation of liability under the Limitation of Liability for Maritime Claims Act 1989 6. The Respondent was at all material times the owner of the Shen Neng 1. 7. The Shen Neng 1 is a seagoing ship. 8. The claim made in the Statement of Claim is: a. a claim in respect of loss of or damage to property occurring in direct connection with the operation of the Shen Neng 1 and/or consequential loss resulting therefrom; and/or b. a claim in respect of loss resulting from infringement of rights (other than contractual rights) occurring in direct connection with the operation of the Shen Neng 1; and/or c. a claim in respect of measures taken in order to avert or minimise loss of the type referred to in sub-paragraph (a) and/or sub-paragraph (b) above and/or further loss caused by such measures. 12 By paras 10 and 11, the respondents plead that the tonnage of the ship is 36,575 tonnes and that any liability of the respondent is limited to the value of 14,172,500 Special Drawing Rights as defined by the International Monetary Fund. 13 The effect of the relevant Articles and the Act is that the "limits of liability" for relevant "claims" arising on any distinct occasion are to be calculated in the manner described in Article 6 of the Convention, and the limits of liability so determined are to apply to the aggregate of all claims which arise on any distinct occasion as contemplated by Article 9(1)(a) of the Convention. 14 The Commonwealth filed a reply on 9 July 2014 by which it admitted two things, the respondent having sought to engage a defence of limitation of liability as just described in partial answer to the claim. First, that the Shen Neng 1 is a seagoing ship and, second¸ that the tonnage of the ship is 36,575 tonnes. 15 Subject to those two admissions, the Commonwealth joined issue with the respondent as to all other matters. 16 As the Full Court observed, the question of whether the respondent can establish a right, as pleaded, to limit its liability for all of the loss or damage claimed by the Commonwealth to simply those acts, neglects or defaults that resulted in the original grounding (as the only distinct occasion) is, ultimately, a question of fact the examination of which was not foreclosed by the qualified admission by the respondent that the acts, neglects or defaults of the Chief Officer of the ship, on or prior to 17:05 (as now seems to be the time of grounding) on 3 April 2010, was the only cause of the grounding: Commonwealth of Australia v Shenzhen Energy Transport Co Ltd [2015] FCAFC 116 at [26]. 17 By its reply, the Commonwealth joined issue with the respondent and put the respondent to proof of the factual matters which would make good the engagement of the limitation of liability. Should the respondent fail to make good the limitation, the Commonwealth, subject to proof of all elements of its claim, would be entitled to recover the loss and damage flowing from the pleaded negligence. 18 Mr Scott QC for the Commonwealth accepted before the Full Court that the Commonwealth by its reply was "just putting them to proof as to how it happened": T, p 12, lns 16-19. Mr Scott QC also accepted (at T, p 11, lns 45-47; T, p 12, lns 1-8) that the point or logic of the matter of putting the respondent to proof on the limitation defence may properly be put this way: … once [the vessel was] stuck on the reef, then everything else that flowed was so interconnected with trying to get off it in a safe way when you've got partial holing, you've got oil leaks, you've got stability problems and the like. But you can't distinguish, factually, any of those acts as being anything other than perfectly well connected to the original grounding that - … it's all one event. But on the other hand, there may have been some decision taken at one point or other during the course of the grounding that aggravated particular damage, that did something that was particularly egregious, that changed that to a second occasion, a second series of events. [emphasis added] 19 Mr Scott QC also accepted (at T, p 12, lns 10-14) that if the Commonwealth is going to run a positive case that claims made arise on more than one occasion (thus attracting distinct applicable caps), the Commonwealth would need leave to amend its reply to make a positive case.