7 The School was eligible to apply for an annual grant from the Federal Government to assist with repaying the principal of a loan for the construction of secondary school buildings, which the School expected would be approximately $250,000 per annum; and an annual interest subsidy from the State Government payable in each year for 20 years to assist with paying interest on that construction loan.
8 In mid 2006, the School approached the Bank and explained its circumstances and applied to the Bank for a loan of approximately $7.5M, being the costs it had incurred to date in progressing the second school project and the likely further costs of construction of the secondary school buildings. The School had contemplated construction commencing before January 2007.
9 On 9 August 2006, the Bank informed the School that it would not be able to issue loan documents for the construction loan until after the development approval had been granted and a quantity surveyor's report setting out the costs of the works had been obtained. The School asserts that the Bank said to the School that the School should apply for an advance of credit of $600,000 and that loan would be rolled into this (construction loan) facility repaying the overdraft out in full.
10 On 1 September 2006, the Bank formally approved an overdraft of $60,000 in advance of the $600,000. The school says that it relied on the Bank's representations and advice, and drew upon the account. As at 15 September 2006, the account was in debt in the sum of $103,187.92. As 28 September 2006, the account was in debit for the sum of $160,403.70. On 29 September 2006, the Bank formally approved an overdraft of $180,000. The School says that it continued to rely on the Bank's representation and advice and drew on the account. On 12 October 2006, the account was in debit in the sum of $230,807.18. On 13 October 2006, following the signing of the security documents, the overdraft was extended to $600,000.
11 The Bank's approval was provided for the reason and on the terms outlined in the enclosed acceptance document and terms schedule "the agreement"). The facility is an overdraft in the amount of $600,000.
12 On 28 March 2007, Baulkham Hills Shire Council approved the development application for the secondary school buildings. On 19 June 2007, the State Government terminated the interest subsidy scheme. However, the scheme was reinstated for those schools which had progressed at to the DA stage including the School. On 6 December 2007, the School contacted the Bank. The Bank files were missing and there had been a change in personnel.
13 On 9 May 2008, the overdraft account was $630,782.26 in debit and the Bank gave the School the name of a quantity surveyor to assist "with the tender and selection process". On 27 May 2008, the School advised the Bank that Altius, architects, were assisting with the construction certificate and asked for an extension of the overdraft to $800,000. On 29 June 2008, the School asked the Bank if it required anything else to consider the extension of the overdraft to $800,000. During June and July 2008, the Bank commenced dishonouring cheques on the account.
14 On 15 August 2008, the Bank in an internal file note stated that, "the relationship [with the School] is now considered to be in default". On 15 August 2008, the Bank sent emails to the School in which it stated that the Bank "will not finance the building projects". On 18 August 2008, the School wrote to the Bank stating, "the bank initially lent the school $250,000.000 (sic) without any form of guarantee or security from the school. This was for site and design work to begin. Some time later this was formalised with a mortgage over the $600,000.00 in total (October 2006). It was agreed and understood between us and the bank that this was to be the first tranche of the money to be borrowed and that the mortgage would be extended to meet the total cost of the project when this amount had been identified. …"
15 On 19 August 2009, the Bank in an internal email noted that, "It is not clear on what basis the existing funding was provided to the school … However, clearly the intention of the Bank was to see the construction through to completion." Thereafter, cheques drawn on the account appear to have been considered by the Bank on a case by case basis. At all material times during 2009 the account remained open and the Bank allowed the School to pay for services using the credit available on the account.
16 On 9 June 2009, the Bank allegedly made a demand for repayment in full of the overdraft account. The School denies that it ever received this notice. On 7 September 2009, the Bank commenced the present proceedings. The property is valued at $10M.