© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2000] VSC 353
Supreme Court of Victoria
2000-09-07
Warren J
Original judgment source is linked above.
CONTRACT - repudiation - construction - ambiguity in terms - severance of term DAMAGES - assessment - applicable accounting method
This Agreement shall cover the supply and servicing by the Supplier to the Purchaser of the items specified in the Schedule and other items subsequently supplied by the Purchaser at the request of the Purchaser. Supply shall continue under this contract for an initial period of three [3] years from the date the items are first supplied to the Cobram Plant and shall continue thereafter until three [3] months after written notice of termination has been given by either parties."
"5. PRICES & TERMS Rental charges as set out below:-
$0.50 for overalls only that are presented for laundry.
All charges shall be based upon the number of items serviced at each tall or the minimum service charges where applicable. All charges shall continue uninterrupted, including public holidays.
Where items supplied by the Supplier are not required by the Purchaser for any period greater than 4 weeks, the Purchaser may notify the Supplier in writing of the items not required and the period for which the items are not required. The Supplier shall remove the items and for this period, the Purchaser shall not be liable for charges for those items.
This Agreement shall cover the supply and servicing by the Supplier to the Purchaser of the items specified in the Schedule and other items subsequently supplied by the Purchaser at the request of the Purchaser. Supply shall continue under this contract for an initial period of three (3) years from the date the items are first supplied to the Cobram Plant and shall continue thereafter until three (3) months after written notice of Termination has been given by either party.
The prices above are fixed for the period of the Contract being 3 years."
"re: Contract S40/96. As previously discussed in our meeting in July of this year, we wish to request to have the above contract extended to a six 6 year term commencing on the 1st February 1998. Prices as outlined in Amendment Contract S40/96 dated 13/5/1997 will remain fixed for the original period of contract up until 1/11/1999. A price review will then take place for the remaining four 4 year period. We are requesting this change as we are about to commence construction of our new premises in which our laundry will be housed. This new building will comply with the Australian Standards for Laundry Practice ASA 4146 1994 and ISO 9002. As you can appreciate there will be a lot of capital expenditure involved and we would feel more comfortable with an extended contract period."
" Please note the following amendment to the above contract: 5. PRICE & TERMS Rental Charges as set out below : Charges Price Laundered & Folded into Lockers Overalls - White, Grey, Navy & Royal $1.30 each Laundered, Pressed & Delivered to Offices Lab Coats $1.20 each Laundered, Pressed & Folded into Lockers Jackets $1.15 each Shirts $0.80 each Trousers - White $0.75 each
Hire Charges Per Garment per week on total issue $0.40 The above prices are fixed until 1 November 1999. 6. PERIOD 4 November 1996 - 3 November 2002. All other terms and conditions remain the same."
"All other terms and conditions remain the same."
"The true rule is that evidence of surrounding circumstances is admissible to assist in the interpretation of the contract if the language is ambiguous or susceptible or more than one meaning. But it is not admissible to contradict the language of the contract when it has a plain meaning. Generally speaking facts existing when the contract was made will not be receivable as part of the surrounding circumstances as an aid to construction, unless they were known to both parties, although, as we have seen, if the facts are notorious knowledge of them will be presumed."
"that they will retrospectively perform and observe the several covenants provisoes and stipulations in the lease expressed as fully as if the same covenants provisoes and stipulations had been herein repeated in full with such modification only as may be necessary to make them applicable to this demise."
" ... The question of construction comes down to this: The words of clause 2 are wide and general and clear and on their reading alone, without regard to any other circumstances or context, they are wide enough to include all the covenants in the previous lease, including the covenant for renewal. The principle which ought to be applied in construing this sort of covenant was laid down long ago by Lord Ellenborough CJ in Iggulden v May [1806] EngR 82; (1806) 7 East 237 where he says, at p.241: 'The rules of construction applicable to the covenants are so well know, that it is hardly necessary to cite authorities to show that every covenant is to be expounded with a regard to its context; that such exposition must be upon the whole instrument, ex antecedentibus et consequentibus, and according to the reasonable sense and construction of the words ... In conformity to which rules, and in support of the apparent intent of the parties, covenants in large and general terms have been frequently narrowed and restrained.' It has been pointed out to me that in that case the narrow construction was put upon it because otherwise one would find a perpetually renewable lease. In my judgment, that case illustrates the principle of construction that wide words can be cut down if the context leads the court to conclude that the words must be construed more narrowly. What, then, are the circumstances and the context at which I am entitled to look to decide whether they should be cut down or whether their wide meaning should remain? It is common ground that I can look at the whole of the words used in the 1963 lease. It is also common ground that I can look at the 1957 lease because of the word 'supplemental' in the first recital, which has the effect of bringing in the whole of the 1957 lease by way of recital into the 1963 lease. It has been submitted on behalf of the tenants that I cannot look at the letters to which I have referred, those of June 21, 1963, and July 3, 1963, but in my judgment they are clearly part of the surrounding circumstances and it is permissible for me to look at them. The effect of the letter of June 21, 1963, was to exercise the option which had been granted to the tenants by the 1957 lease, and that option was for seven years only, but a request was made that instead of taking it for seven years, as the option required, the term should only be for four years and that was agreed to by the then landlords. When I turn to the 1963 lease, and particularly recital (b), I find these words again ' ... in satisfaction of the tenant's rights of renewal which the landlords have agreed to do.' The only right of renewal which the tenants had was once and once only, for seven years, and it was that option which they were exercising by the letter although they were asking for something less than that to which they were entitled under clause 4 (D) of the 1957 lease. Taking all these things into consideration, that is to say, the former lease, the exercise of the option and the 1963 lease, I am constrained to hold that the covenants in clause 2 must be given a narrow construction so as not to include the covenant for renewal. I therefore propose to dismiss the action and, as rectification does not arise, to make no order on the counterclaim."
"It is a rule of construction, moreover, that whatever expression found in a written instrument is inconsistent with the real intention of the parties, as it appears from the language of the instrument, ought to be rejected as superfluous: Walker v Giles [1848] EngR 20; (1848), 6 CB 662; 136 ER 1407; Re O'Brien, [1975] 1 NSLR 688. The rule was stated by Sir John Romilly, MR in Re Strand Music Hall (19865)[1865] EngR 570; , 35 Beav. 153 at p.159; [1865] EngR 570; 55 ER 853 at p.856, as follows: 'The proper mode of construing any written instrument is to give effect to every part of it, if this be possible, and not to strike out or nullify one clause in the deed, unless it be impossible to reconcile it with another and more express clause in the same deed.' In Gwyn v Neath Canal Navigation Co. (1868), LR 3 Ex. 209 at p.215, Kelly, CB expressed the rule in these words: 'When a court of law can clearly collect from the language within the four corners of a deed, or instrument in writing, the real intention of the parties, they were bound to give effect to it by supplying anything necessarily to be inferred from the terms used, and by rejecting as superfluous whatever is repugnant to the intention so discerned'."
"The function of a court of construction is to ascertain what the parties meant by the words which they have used. For this purpose the grammatical and ordinary sense of the words is to be adhered to, unless they lead to some absurdity or to some repugnance or inconsistency with the rest of the instrument, in which case the grammatical and ordinary sense of the words may be modified so as to avoid the absurdity or inconsistency, but no further; see the speech of Lord Wensleydale in Grey v Pearson [1857] EngR 335; (1857) 6 HLC 61 at 106, repeated by Lord Blackburn in Caledonian Railway Co v North British Railway Co (1881) 6 App. Cas. 114 at 131."
"I would accept that in commercial transactions the court should strive to give effect to the expressed arrangements and expectations of those engaged in business, notwithstanding that there are areas of uncertainty and notwithstanding that particular terms have been omitted or not fully worked out. Where one should draw the line is difficult to state and equally difficult to apply. ... Where parties have deliberately written the terms upon which they wish to bargain but have omitted or inadequately expressed a term which might in other circumstances have been expressly or more precisely stated, the courts will endeavour to give effect to the fact that the parties did not see the absence or deficiency of such a term as preventing them from reaching agreement."
"In a commercial agreement the further the parties have gone on with their contract, the more ready are the courts to imply any reasonable term so as to give effect to their intentions. Where much has been done, the courts will do their best not to destroy the bargain."
" ... for the present I would accept that in those circumstances where the court is satisfied that the parties have reached agreement, judged by objective standards, then it should be more generous in giving effect to what is necessary to achieve business efficacy and the parties' intentions, although their communications might have an air of uncertainty and incompleteness about them".
"The case was heard in the commercial list. As is well known, that list is dedicated to the prompt, efficient and economical resolution of commercial disputes. Consistently with that philosophy applications to amend pleadings, once they are put in proper shape for a trial, are discouraged and are very sparingly allowed, especially after the trial has begun. The reasons for that attitude are manifest and notorious."
[1] B.P. Refinery (Westernport) Pty Ltd v Hastings Shire Council [1977] HCA 40; (1977) 52 ALJR 20; Codelfa Construction Pty Ltd v State Rail Authority of New South Wales, supra; Hospital Products Limited v United States Surgical Corporation [1984] HCA 64; (1984) 156 CLR 41; Hawkins v Clayton (1988) 164 CLR 539.
Cobram Laundry Services Pty Ltd
Murray Goulburn Co-operative Co Ltd [2000] VSC 353
(1992) 2 VR 732
(1994) 2 VR 32
(1982) 149 CLR 337
(1990) 20 NSWLR 251
(1986) 60 ALJR 1
(1956) 95 CLR 420
(1990) 170 CLR 394
(1995) 1 VR 209
(1991) 174 CLR 64
(1997) 189 CLR 146
(1996) 2 VR 535
(1996) 1 VR 594
(1986) 161 CLR 475
(1977) 52 ALJR 20
(1984) 156 CLR 41
(1988) 164 CLR 539