CITY OF BAYSWATER -v- VIVA ENERGY AUSTRALIA PTY LTD [2021] WASC 373 (27 October 2021)
[2021] WASC 373
At a glance
Source factsCourt
Supreme Court of WA
Decision date
2021-10-27
Before
Le Miere J, Newnes JA, Buss JA
Source
Original judgment source is linked above.
Judgment (34 paragraphs)
1 This is the plaintiff's application for a split trial. The plaintiff seeks to have its contractual claim against the defendant determined separately from the damages claim. Essentially, it is said that is the most expeditious way to deal with the action. The defendant says the questions of liability and quantum are inextricably linked and there will be no savings to the parties nor the court's time if separate trials are ordered.
2 The application is made under O 32 r 4 of the Rules of the Supreme Court 1971 (WA). That rule reads as follows:
4. Time of trial of questions or issues
The Court may order that any question or issue arising in a cause or matter whether of law or fact or partly of law and partly of fact, and whether raised by the pleadings or by agreement of the parties or otherwise be tried separately from any other question or issue whether before at or after the trial or further trial of the proceedings, and may direct that a case and the question or issue for decision be stated.
Shell agrees, to construct the Slip Lane within 60 days following the relocation of the Communications Pits, in accordance with the plans and specifications approved by the City, copies of which are annexed and marked 'B'.