© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2018] NSWCA 244
Court of Appeal (NSW)
2018-09-12
Macfarlan JA, Ward JA
Original judgment source is linked above.
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
Headnote [This headnote is not to be read as part of the decision] Mansfield Corporation Pty Ltd (the respondent) was engaged by Chengcheng (Aust) Enterprise Melbourne Pty Ltd (the appellant) under a Design and Construction Contract entered into on 20 July 2015 (the Contract) to refurbish restaurant premises in Melbourne. The Contract required the respondent to complete the works by 27 November 2015. However, clause 6.6 of the Contract provided that the principal "may direct the Contractor in writing to carry out a Variation which is within the general scope of the Works". Clause 9.4 of the Contract provided that, if the progress of the works was delayed by any matter, cause or thing beyond the control of the contractor, then the contractor was entitled to a reasonable extension of time for practical completion. Clause 10.4 of the Contract provided that, unless otherwise agreed by the parties, variations must be valued by the contractor on a fair and reasonable basis and must include the value of pricing work, time-related costs and expenses arising from the variation. Clause 10.6 provided that, if progress of the works was delayed or disrupted by (relevantly) "a Variation", then the contractor was "entitled (in addition to the extension of time referred to in Clause 9.4) to reimbursement of loss or expense as a result of the delay or disruption" at a specified daily rate. In November 2015 and December 2015, the appellant requested that the respondent carry out a number of additional works in the restaurant. An extension of time of 45 additional working days was approved and the appellant paid the respondent the agreed value of the additional works. Completion occurred on 5 February 2016. In August 2016, the respondent commenced proceedings in the District Court seeking payment of a sum payable under cl 10.6 of the Contract as reimbursement of loss or expense in respect of a 45 day period. Judgment was given for the respondent on 7 February 2018. The appellant appealed. The appellant also sought leave to file a further amended defence in the District Court. The respondent sought leave to file an amended statement of claim re-calculating the sum of the delay losses on the basis of 70 calendar days rather than 45 working days. Held (Macfarlan JA, Ward JA and Sackville AJA), dismissing the appeal, refusing leave to file an amended defence and refusing leave to cross-appeal: Per Macfarlan JA, Ward JA and Sackville AJA:
Judgment
Contract
Completion of the Works
Primary judgment
Grounds of appeal
Appellant's submissions as to the proper construction of cl 10.6 (grounds 5-8)
Appellant's submissions as to the new defence sought to be raised
Respondent's submissions as to construction of cl 10.6
Respondent's submissions on the proposed new point of defence
Application for leave to amend the statement of claim
Determination
Conclusion
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 26 October 2018
Chengcheng (Aust) Enterprise Melbourne Pty Ltd
Mansfield Corporation Pty Ltd