Chambers v Borness
[2014] NSWSC 890
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2014-07-01
Before
Pembroke J
Source
Original judgment source is linked above.
Judgment (5 paragraphs)
Judgment - EX TEMPORE 1This is a claim commenced by the plaintiff seeking, among other things, an order that the 15 per cent deposit of $445,650, paid pursuant to a contract for sale of land between the plaintiff as purchaser and the defendant as vendor, be repaid to the plaintiff with interest, pursuant to Section 55(2A) of the Conveyancing Act 1919 (NSW). The entitlement to interest is a discretionary statutory entitlement given by subsection (2A). The relevant facts are as follows.
The Facts 2The contract for sale of land was entered into on 10 August 2012. The purchase price was $2,971,000. Special Condition 11 authorised the deposit to be released to the vendor upon exchange of contracts. A completion date 12 months after the date of contract was specified. Completion was therefore required on 10 August 2013. Clause 15 permitted either party to serve a notice to complete if completion had not occurred by the completion date. Special Condition 7.2 provided that if the purchaser failed to complete the contract on or before the completion date, otherwise than through the vendor's default, then the purchaser shall pay at completion, in addition to the balance of the purchase price adjustments and any other money payable under the contract, interest on the balance of the purchase price, calculated at the rate of 12 per cent per annum with effect from the completion date specified in the contract. However, for the reasons that I will explain, this clause has no direct application on the facts of this case. 3The contract has been validly terminated by the vendor. Special Condition 7.2 is predicated on a completion by the purchaser but at a later date than the completion date specified in the contract. No such completion has occurred or will now occur. 4Clause 18.2.2, together with Special Condition 1(m), provided: The purchaser must not before completion make any change or structural alteration or addition to the property, other than as provided in Special Condition 17, or as otherwise agreed in writing by the vendor. 5Special Condition 17 provided that four weeks following exchange of contracts the purchaser was authorised to take possession of the property and undertake certain specified works that were specified in the Special Condition. Significantly, Special Condition 17 concluded with the following paragraph: The parties further agree that if the contract is not completed for any reason, other than the default of the vendor, then the purchaser shall not call upon the vendor to contribute for the cost of any work undertaken and the purchaser further covenants with the vendor that the warranty is indemnified in favour of the vendor or any complaint will not merge on completion. 6Included in the contract, and collateral to it, was a licence agreement which set out the terms of the contractual licence given to the purchaser to occupy the property until the specified date, being 12 months after the date of contract. The licence agreement provided for the purchaser to pay a licence fee of $4,166.66 per month in advance. The vendor had sought a licence fee of $100,000 per annum but agreed to accept a fee of $50,000 per annum, which equated to $4,166.66 per month. The licence agreement also required the purchaser to pay all rates, taxes, levies and other outgoings payable in respect of the property. The licence commenced four weeks after the date of contract. Special Condition 12 stated that the contract (including the licence agreement) embodied an entire agreement and that all other conditions, warranties, promises and obligations were excluded.