Centennial Mandalong v Delta Electricity
[2013] NSWSC 1860
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2013-12-16
Before
McDougall J
Source
Original judgment source is linked above.
Judgment (9 paragraphs)
Judgment 1HIS HONOUR: The plaintiff (Centennial) produces coal from its Mandalong Mine in New South Wales, and sells some of that coal to the defendant (Delta). Centennial is obliged to pay carbon charges under the Clean Energy Act 2011 (Cth) and related legislation. Centennial claimed that the price payable for coal sold by it to Delta should be increased to reflect the amount of carbon charges incurred by Centennial that were attributable to that coal. Delta disputed Centennial's claim. On 17 October 2013 I gave judgment ([2013]) NSWSC 1505) in which I held, in effect, that in principle, carbon charges incurred by Centennial could be passed along under the price adjustment formula of the contract. 2Accordingly, I granted declaratory relief, the effect of which was to establish that in principle, carbon charges incurred by Centennial were to be taken into account as part of Government Charges Per Tonne for the purposes of the price adjustment formula.
The remaining question 3The remaining question is to identify the carbon charges that are to be taken into account in adjusting the price of coal sold by Centennial to Delta. Since carbon charges are levied (relevantly) on methane emissions from the Mandalong Mine, the answer to the question requires identification of the methane emissions that, adapting the words of the price adjustment formula, are attributable to coal sold by Centennial to Delta. 4At this point, I note that the contract provided for "Technical Disputes" to be referred to an expert for "determination" (cl 16.5). The expression "Technical Dispute" is defined to mean "any dispute or disagreement... arising out of or in connection with [the contract] which relates to technical or scientific facts or issues". To my mind, identification of the emissions that are "attributable" to coal sold by Centennial to Delta under the contract is a matter that could and should have been referred for expert determination, as a Technical Dispute. However, although I raised that possibility with the parties, they chose not to take that course, but to ask the court to decide the matter. 5The parties accept that in principle a prorating exercise carried out by comparing coal sold to Delta in any given year with total coal sold in that year, would be appropriate. In Delta's case, its acceptance of that position is on the basis that it flows from what I have already decided. 6It is common ground between the parties that, as I found in my earlier reasons at [8] to [18], there are various sources of methane emissions from Centennial's mining operations at Mandalong. They are: (1) the pre-draining of methane gas from areas that are to be mined; (2) the construction of roads within the mine, both to define panels that are to be mined and to enable men and equipment to move through the mine (and in the course of which saleable coal is produced); (3) the process of longwall mining itself; (4) what I referred to as the stockpiling of mined coal; and (5) goafs: mined areas which are left void, and into which methane is pumped so that its concentration is above the combustible level. 7There is a sixth source of emissions, which I mention only to put to one side. It is a fan ventilating Centennial's nearby mine at Cooranbong. Since the parties agree (as in any event I would have concluded) that these emissions are not to be taken into account, there is no need to explain them. 8It was common ground that emissions from the first three categories identified at [6] above - predraining, roads and longwall mining - were to be taken into account. (Again, in Delta's case, its agreement to that position is on the basis that it flows from what I have already decided.) The disputed sources of emissions are, therefore, what have been called stockpiles, and from goafs. 9I approach the resolution of the remaining dispute on the basis of the written submissions that the parties, having had an opportunity to consider my reasons, have put before me. I do not think it necessary to invite the parties to put further submissions.