The proposed amendments
18Some amendments are not opposed. The disputed amendments contained in the P2FASC are set out below.
19The amendments that the plaintiff seeks to make against Allen Jack & Cottier, the architect, fall into two broad categories. They are firstly, the failure to advise the plaintiff about the terms of Taylor Thomson Whitting's terms of engagement; and secondly, the failure to advise the plaintiff about Taylor Thomson Whitting's level of competence (these amendments are also pleaded against Greenwood Constructions).
20The proposed amendments as against Allen Jack & Cottier are as follows:
"7C In or about early March 2002 the first defendant became aware that the second defendant was incompetently discharging its functions under the Engineering Contract or alternatively lacked the expertise to properly discharge its functions under the Engineering Contract.
Particulars
(i) Correspondence dated 4 March 2002 from the third defendant to the first defendant.
7D By reason of the matters pleaded in paragraph 7 above and otherwise by reason of the nature of the relationship between the first defendant and the plaintiff, the first defendant was under a duty to advise the plaintiff that the second defendant was incompetently discharging its functions under the Engineering Contract or alternatively to advise the plaintiff that the second defendant lacked the expertise to properly discharge its functions under the Engineering Contract.
7E In breach of the said duty the first defendant did not:
(ii) advise the plaintiff that the second defendant lacked the expertise to properly discharge its functions under the Engineering Contract.
7F By reason of the matters pleaded in paragraphs 7, 7C and 7E the plaintiff has suffered loss and damage. [failure to advise of engineer's competence]
7G In engaging the second defendant as consulting engineer in connection with the construction of the Home, or alternatively in recommending to the plaintiff that the plaintiff engage the second defendant as consulting engineer, the first defendant:
(i) was aware, or ought to have been aware, of any standard conditions of engagement, including the conditions of engagement, pleaded at paragraph 20 of the defence of the second defendant filed on 18 November 2011 in so far as any such conditions of engagement are found to bind the plaintiff;
(ii) was aware or ought to have been aware that the plaintiff did not know of the existence of any such conditions of engagement;
(iii) was under a duty to warn the plaintiff of the existence of the such conditions of engagement.
7H The plaintiff was not aware of such conditions of engagement.
7I In the premises the first defendant was under a duty to advise the plaintiff of any such conditions of engagement.
7J The first defendant did not advise the plaintiff of the existence of, or the terms of, any such conditions of engagement.
7K If, as alleged by the second defendant and denied by the plaintiff:
(i) the said conditions of engagement formed part of the Engineering Contract; and
(ii) by reason of clause 4.3 of the conditions of engagement:
(a) the second defendant has been discharged from all liability in respect of the Engineering Contract; and
(b) the plaintiff was not entitled to commence and/or is not entitled to continue its proceedings against the second defendant
then by reason of the failure of the first defendant to advise the plaintiff of the existence of, or the terms of, any such conditions of engagement, the plaintiff has suffered loss and damage.
Particulars
(i) Loss of opportunity to prosecute proceedings against the second defendant. [failure to advise of terms of Taylor Thomson Whitting's engagement]
21As against Greenwood Constructions, the builder, the plaintiff's proposed amendments fall into three broad categories. They are firstly, building defects; secondly, the construction was not in accordance with the Douglas engineering report and specifications; and thirdly, failure to advise the plaintiff of Taylor Thomson Whitting's competence.
22The proposed amendments as against Greenwood Constructions are as follows:
"17AA As part of its duty of care to the plaintiff and as required by the statutory warranties pleaded in paragraph 10, the third defendant was, in the performance of the Building Contract, under a duty to the plaintiff:
(i) to ensure that the upper level timber-framed floor was tied down so as to resist wind actions; and
(ii) to ensure that the lower level masonry internal and external walls were sufficiently tied together so as to prevent lateral movement and separation.
17AB In breach of the said duty, and in breach of the statutory warranties pleaded in paragraph 9A, the third defendant:
(i) did not ensure that the upper level timber-framed floor was tied down so as to resist wind actions and did not tie down the upper level timber-framed floor so as to resist wind actions; [resist wind actions]
(ii) did not ensure that the lower level masonry internal and external walls were sufficiently tied so as to prevent lateral movement and separation and did not tie the lower level masonry internal and external walls sufficiently so as to prevent lateral movement and separation. [failure to tie down]
17AC As part of its duty of care to the plaintiff and as required by the statutory warranties pleaded in paragraph 9A, the third defendant was, in the performance of the Building Contract, under a duty to the plaintiff to build the Home in compliance with Condition 22 and Condition 27 pleaded in paragraph 6BE.
Particulars
(i) The plaintiff repeats the particulars to paragraph 10BA above.
17AD In breach of the said duty, and in breach of the statutory warranties pleaded in paragraph 9A, the third defendant did not build the Home in compliance with the said Conditions 22 and 27.
Particulars
(i) The plaintiff repeats the particulars to paragraph 10BC above.
(ii) The recommendations in the Douglas Partners report were not complied with as pleaded in paragraph 12 above.
...
17IA In the alternative, the third defendant was under a duty of care to the plaintiff, in the discharge of its duties, to construct the Home in accordance with the plans supplied by the second defendant.
17IB In breach of the said duty the third defendant did not construct the Home in accordance with the engineering design supplied by the second defendant.
Particulars
(i) The engineering design supplied by the second defendant required that foundations be taken to a minimum depth of 900 millimetres unless rock was encountered prior to 900 millimetres.
(ii) The third defendant did not build the Home so that foundations were taken to a minimum depth of 900 millimetres or to rock where rock was encountered prior to 900 millimetres. [not in accordance with Douglas specifications]
17J By reason of the breaches by the third defendant pleaded in paragraphs 17AA, 17AB, 17AD, 17G, 17I, 17IB the plaintiff has suffered loss and damage.
Particulars of damage
(i) cracking to external and internal walls and ceiling linings;
(ii) misalignment of internal doors;
(iii) cracking of bathroom tiling;
(iv) jamming of front door;
(v) jamming of garage door;
(vi) the Home is unsafe and unsound and liable to collapse;
(vii) the Home is not structurally adequate, stable and in a safe condition for occupation;
(viii) penetration of water into the Home.
Particulars of loss
(i) rectification costs for repair of cracking to external and internal walls and ceilings linings;
(ii) rectification costs for repair of misaligned of internal doors;
(iii) rectification costs for repair of cracking of bathroom tiling;
(iv) rectification costs for repair of jamming front door;
(v) rectification costs for repair of jamming of garage door;
(vi) (a) rectification costs for repair of to make
Home sound, not liable to collapse and safe for occupation; alternatively,
(b) costs of demolition of Home and cost of rebuilding; alternatively
(c) cost of demolition of Home and costs expended on building Home.
[construction not in accordance with report and plans]
17K In or by early March 2002 the third defendant had become aware that the second defendant lacked the expertise to properly discharge its functions under the Engineering Contract.
Particulars
(i) Correspondence dated 4 March 2002 from the third defendant to the first defendant
17L By reason of the matters pleaded in paragraph 17K above and otherwise by reason of the nature of the relationship between the third defendant and the plaintiff, the third defendant was under a duty to advise the plaintiff that the second defendant did not have experience in domestic construction or alternatively to advise the plaintiff that the second defendant lacked the expertise to properly discharge its functions under the Engineering Contract.
17M In breach of the said duty the third defendant did not:
(i) advise the plaintiff that the second defendant did not have experience in domestic construction;
(ii) advise the plaintiff that the second defendant lacked the expertise to properly discharge its functions under the Engineering Contract.
17N By reason of the matters pleaded in paragraphs 17K, 17L and 17M, the plaintiff has suffered loss and damage."
[failure to advise plaintiff about engineer's lack of competence - same as the allegation against Allen Jack & Cottier]