3812/01 Castle Constructions Pty Limited v Fekala Pty Limited & Others
JUDGMENT
1 MASTER: On 28 June 2001 the plaintiff, as purchaser, and the defendants, as vendors, entered into a contract for sale of land at 5-7 Rose Street, Eastwood (Eastwood). The sale price for the property was $3 million. The plaintiff payed the deposit of $300,000.
2 By late July a dispute had arisen between the parties. The fixtures and fittings had been removed and on 1 August 2001 the plaintiff commenced these proceedings seeking, inter alia, a declaration that the contract included the in sale items of plant and equipment.
3 On 14 August 2001 the defendants served a notice to complete on the plaintiff requiring completion by 3pm on 29 August 2001, time being of the essence. Notwithstanding that the notice was issued by the defendants the defendants were unable to complete on that date and the plaintiff terminated the contract.
4 On 28 August the defendants' solicitors informed the plaintiff's solicitors that they would be unable to complete on 29 August and advised that they were withdrawing the notice to complete and extending the date for completion to 12 September.
5 The plaintiff ignored the second notice to complete and on 25 September 2001 filed an amended summons seeking a declaration as to the validity of the termination of the contract. Subsequently, on 28 September 2001, the defendants filed a cross claim seeking, inter alia, specific performance of the contract.
6 On 26 February 2002 Windeyer J held that the plaintiff had validly terminated the contract and referred the question of damages to a Master for enquiry. The defendants' cross claim was dismissed. The defendants lodged an appeal, however, on 6 September the Court of Appeal dismissed that appeal.
7 There are two matters to be determined on the referral. Firstly, whether or not the plaintiff has sustained damages as a result of the breach by the defendant and if so, the extent of those damages. Secondly, whether the plaintiff had taken steps to mitigate its loss.
Background
8 The defendants were mortgagees of a property known as 5-7 Rose Street, Eastwood. They offered to sell the property to the plaintiff. On 28 June 2001 a contract for sale of land was entered into. The contract provided for completion on the forty second day after 28 June 2001, ie 9 August 2001. On 14 August 2001 the defendants served a notice to complete on the plaintiff fixing 3pm on 29 August 2001 as the time and date for completion. Time was of the essence for both time and date.
9 On 27 August 2001 the defendants' solicitor forwarded to the plaintiff's solicitor a draft settlement statement and a form of transfer for execution. On 28 August 2001 the defendants' solicitors wrote to the plaintiff's solicitors waiving completion by 3pm on 29 August and extending it to 3pm on 12 September 2001.
10 On 29 August 2001 the plaintiff's solicitor attended the defendants' at 11.55am with the necessary cheques for settlement. There was a discussion about the validity of the extension of the settlement. The plaintiff's solicitor left, but returned at 2.55pm and was once again advised by the defendants' solicitor that the defendant was not ready to complete. Thereafter, on that day the plaintiff sent a notice of termination.
11 On 11 September 2001 the defendants had the transfer signed by all vendors and was ready to settle by 3pm on 12 September. Settlement did not take place.
12 The business of the plaintiff is that of a developer and builder of commercial and residential sites. The company has operated as a developer since 1978. The evidence of Victor Lahoud, the sole director of the plaintiff, was that he identifies and selects sites which are suitable for redevelopment. Once a property is purchased he then proceeds to obtain development consent from the local authority. The company then either sells the site with the benefit of the development consent of the local council or constructs the buildings on the site for sale. Most of the company's projects since 1992 have resulted in the sale of sites with the development consent rather than carrying out construction on the sites. Mr Lahoud's evidence was that where he sees an opportunity to purchase more than one site during a current development phase if, in his opinion, it has good investment value and the potential to develop in the future, the company would then purchase that site. The company also has a policy in relation to whether it will construct buildings on the site or merely obtain development consent from the local council and then on sell to a larger builder. His evidence was that where the site will accommodate more than 24 units or town houses the company's policy is to obtain development consent from the local council and then on sell the site with the development consent to another builder. Another factor in considering whether or not the company will construct is the proximity of the project to the plaintiff's offices at Northbridge. As a general rule his evidence was that anything within a five kilometre radius of Northbridge is regarded as a potential construction site rather than merely obtaining development consent and then on selling. Since 1985 the plaintiff has only constructed six projects. The remaining projects have been on sold to other developers once the plaintiff obtained the development consent from the local council.
13 Mr Lahoud's evidence was that he is continually researching and looking at new sites with the potential to develop. However, it is not every site that he inspects that the company ultimately enters into a contract to purchase the site. His evidence was that the nature of the business requires him to be continually inspecting sites and determining the potential of those sites.
14 On or about 2 June 2001 Mr Lahoud saw an advertisement in the Sydney Morning Herald advertising for sale by way of auction the Eastwood property. The property was advertised with vacant possession and zoned commercial.
15 On or about 21 June 2001 Mr Lahoud spoke with Mr Peter Matthews from Ray White Real Estate who were listed as co-agents in the advertisement. Mr Lahoud advised Mr Matthews that the plaintiff was principally a developer of residential and commercial property.
16 The auction was to take place on 28 June 2001. On 27 June 2001 Mr Lahoud meet with Mr David Wolski, an architect, with the view of having Mr Wolski prepare a development application for the site. The following day, 28 June 2001, Mr Lahoud attended the auction of the property and was ultimately the successful bidder. The contracts were exchanged and Mr Lahoud handed over a cheque in the sum of $300,000 being the deposit under the contract. At the conclusion of the auction he met Mr James Carter who was the solicitor acting for the mortgagees on the sale.
17 During July the plaintiff consulted with and gave instructions to Mr Wolski to prepare the development application to be lodged with Ryde Council. The company also instructed a registered surveyor and a town planner to work with Mr Wolski with a view of obtaining development consent from the Ryde Council. Throughout July, August and September 2001 there was consultation with Ryde Council's town planner with a view to ensuring that the application by the plaintiff ultimately received favourable consideration by the Council.
18 On or about 24 July 2001 Mr Lahoud had a conversation with a Mr Roberts who was a director of the mortgagor of Eastwood. During that conversation Mr Roberts informed Mr Lahoud that there was a dispute between the mortgagees and the mortgagor and that the mortgagor would be taking steps to ensure that that dispute went to court. Mr Roberts implied that any court case would be lengthy and would involve Castle Constructions as well as the mortgagees. Subsequently, there was a further conversation with an associate of Mr Roberts who indicated that a deal could be done between the mortgagor and Castle Constructions if Castle Constructions were to give the mortgagor a lease of the premises and were to fit out the premises with the necessary fixtures and fittings to the sum of approximately $1 million. Those discussions did not go any further.
19 There was now some concern by Castle Constructions about the success of the project. The plaintiff did not want to get involved in litigation which may render the project uneconomical.
20 In accordance with the company's practice, Mr Lahoud continued to look for other potential sites. In late July the plaintiff gave instructions to its solicitor to approach the defendant with a view each party giving releases in respect of the contract, that there be mutual rescission. Ultimately that did not find favour with the defendants. At about this time Mr Lahoud continued to look at other sites which may have some potential for the plaintiff. Two sites in particular were considered, one at Cammeray and one a Waitara. However, in relation to the Waitara property he was informed by the estate agent that the property had sold. So far as Cammeray was concerned the company had discussions on 27 July 2001 with a real estate agent and gave instructions to make an offer for that property. The agent informed the plaintiff that the asking price for the property was $3.6 million but that he believed that $3.3 million would be sufficient to enable it to be purchased. Mr Lahoud's instructions on behalf of the plaintiff were to make an offer of $2.8 million.
21 After the plaintiff terminated the Eastwood contract on 29 August he instructed the agent in respect of the Cammeray site to make a bid for $3.1 million. Shortly thereafter the agent informed him that another party was very close to purchasing the property and informed Mr Lahoud that the plaintiff would have to move quickly to secure the property.
22 Mr Lahoud's evidence was that the Cammeray site would only be pursued on the basis that as a result of the termination of Eastwood the deposit would be refunded and that that deposit could be used as the deposit for the purchase of the Cammeray site. The defendant declined to return the deposit and the plaintiff, therefore, did not pursue the purchase of Cammeray.
23 The plaintiff asserts that as a result of the failure of the defendant to complete the contract it lost the opportunity to develop the Eastwood site. Alternatively, by refusal to refund the $300,000 deposit the plaintiff was unable to proceed with the purchase of the Cammeray site. Therefore, the plaintiff asserts that it has sustained damages as a result of the breach of the contract by the defendant.
Damages
24 It is submitted by the defendant that the damages that are sought by the plaintiff are damages to be assessed at the date of breach of the contract namely 29 August 2001. It is submitted that the plaintiff's measure of damages is the difference between the price that it bargained to purchase the property and the market value of the property at the date of default. Further, it is submitted that as there is no evidence of what the market value was of the property as at 29 August 2001 there is no evidence that the plaintiff has sustained any loss.
25 In Robinson v Harman (1848) 154 ER 363 at 365; the court said:
"Where a party sustains a loss by reason of a breach of contract, he is, so far as money can do it, to be placed in the same situation, with respect to damages, as if the contract had been performed."
26 In Hadley v Baxendale (1854) 156 ER 145 at 151; the court said:
"Where two parties have made a contract which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally, ie according to the usual course of things, from such breach of contract itself, or such as may be reasonably be supposed to have been within the contemplation of the parties, at the time they made the contract , as the probable result of the breach of it."
27 In Wenham v Ella (1972) 127 CLR 454 at 463; Barwick CJ also referred to what had been contemplated by both parties at the time the contract was made in the event of there being a breach.
28 In Smith and Newcourt Securities Limited v Citibank [1997] AC 254 at 265; the court said:
"The general rule in other areas of the law has been that damages are to be assessed as at the date the wrong was committed. But recent decisions have emphasised that this is only a general rule: where it is necessary in order to adequately compensate the plaintiff for the damage suffered by reason of the defendant's wrong a different date of assessment can be selected. Thus in the law of contract, the date of the breach is 'not an absolute rule: if to follow it would give rise to an injustice, the court has power to fix such other date as may be appropriate in the circumstances.'"
29 In Diamond v Campbell Jones [1962] Ch 22; the court said that in order to recover loss of profits which would have been made on a development the plaintiff must establish that the defendant had actual knowledge at the time of making contract of how the plaintiff proposed to deal with the property. In that case the court was not prepared to impute such knowledge to the defendant. Buckley J said:
"Special circumstances are necessary to justify in imputing into a vendor of land that the purchaser intended to use it in any particular manner."
30 In Cottrill v Steyning and Littlehampton Building Society [1966] 1 WLR 753 at 756 the claimant entered into a contract to purchase certain land with the view of developing the land. In breach of the contract the defendant sold the land to a third party. Dealing with the question of special circumstances the court said that the defendants knew that the claimant intended to develop the land. Therefore, special circumstances where established which entitled the claimant to have damages assessed by reference to the profits which both parties contemplated that he would make. Accordingly, damages were assessed at the market value of the land at the date of completion of the development less expenses attributable to carrying out the development.
31 In Commonwealth of Australia v Amman Aviations Pty Limited (1991) 174 CLR 64 the court stated that the award of damages for breach of contract for the purpose of protecting the plaintiff's expectation of receiving the defendant's performance the onus of proving damages lies on the plaintiff and any damages awarded are to be determined objectively rather than subjectively ascertained. That is, the plaintiff must prove, on the balance of probabilities, that his expectation of a certain outcome, as a result of performance of the contract, had a likelihood of attainment rather than being a mere expectation.
32 Brennan J at pages 98 and 99 reviewed some of the authorities that I have already referred to; his Honour also cited an English authority, C Czarnikow Limited v Coufos [1969] 1 AC 305 at 385. His Honour cited the following passage of Lord Reid:
"The crucial question is whether, on the information available to the defendant when the contract was made, he should, or the reasonable man in his position would, have realised that such loss was sufficiently likely to result from the breach of contract to make it proper to hold that the loss flowed naturally from the breach or that loss of that kind should have been within his contemplation."
33 The plaintiff relies on expert valuation evidence put on by Craig Miller. In his report of 4 April 2003 Mr Miller assesses the valuation of the property as $7,280,000 based on the council's consent to a development application for the site. Mr Miller's report was not challenged. Therefore, as a starting point the value of the property can be accepted as being $7,280,000 if the plaintiff had acquired the property and obtained the consent of Ryde Council for its development application and then on sold the site. The evidence of Mr Lahoud is that the expenses associated with the project would come to approximately $3,582,000. Those expenses include the purchase of the Eastwood land as well as the work that had been performed in relation to the development application and the legal and promotional costs in relation to the on sale of the property. Thus, on the plaintiff's evidence, the net profit would have been $3,698,000.
34 The plaintiff also seeks to add to that a sum for the fixtures and fittings that were wrongfully removed from the property. In relation to those items the evidence is very unsatisfactory. Figures ranging from $300,000 to $500,000 were given as the damages sustained by the wrongful removal of those items. However, there was no evidence before me which established any figure in relation to those items. In the absence of any such evidence I am not prepared to make an assessment of the loss, if any, sustained by the plaintiff in respect of those items.
35 It is clear on the authorities that I have cited that the damages are based on what the parties may have reasonably contemplated at the time the contract was made. The plaintiff's evidence is that the property was zoned commercial and was advertised as a commercial site. The plaintiff's discussions with the defendants' agent included advice that it was a developer and that it was looking to develop the site. It is clear from the name of the plaintiff company that its business is that of construction and developing properties for the purpose of making a profit.
36 In my view, having regard to the evidence of the conversation with the defendants' agent, the way in which the property was advertised and the nature of the plaintiff's business, the defendants had knowledge that the plaintiff intended to develop the site. Therefore, in my view at the time that the contract was entered into it was contemplated by both parties that the plaintiff was acquiring the site for the purposes of developing it. The measure of damages, ie the loss that flowed naturally from the breach is the difference between the value of Eastwood according to the valuer less the expenses associated with the acquisition of the site, development and marketing of the site.
37 Therefore, the measure of damages that the plaintiff is entitled to recover, subject to the defendants' submissions in relation to mitigation, is as follows: