Casbee Properties Pty Ltd v Patoka Pty Ltd
[2003] NSWCA 361
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2003-11-24
Before
Mason P, Giles JA, McColl JA, Nicholas J, Coll JA
Catchwords
- Huxley Electronics and Construction Ltd v Forsyth (1999) All ER 268
- CASES CITED : Natoli v Walker (CA, 26 May 1994, unreported)
- New South Wales v Coya (Constructions) Pty Ltd (CA, 4 August 1995, unreported)
- Promenade Investments Pty Ltd v State of New South Wales (1992) NSWLR 203
Source
Original judgment source is linked above.
Catchwords
Judgment (14 paragraphs)
Background 3 The Principal owned land at Middle Road, Paxton, near Cessnock. It obtained the approval of Cessnock City Council ("the Council") to the sub-division of the land into twenty-one residential blocks. Sub-division in accordance with the approved plans required the construction of a bitumen sealed kerbed road running off Middle Road and ending in a cul-de-sac and, at three places off the road, bitumen sealed driveways providing access to battle-axe blocks. 4 By a written contract executed by the Contractor on 2 August 2000 and by the Principal on 20 August 2000, the Principal engaged the Contractor to construct the road and the driveways for a contract price of $339,465.30. 5 Disputes arose concerning the payment of progress claims and completion of the works. The Contractor left the site and, having served a statutory demand, brought proceedings to wind up the Principal. In April 2001 the proceedings were settled. It was agreed that the Contractor would return to the site to undertake the work set out in a quotation from Wallis Constructions, which work "would be regarded as complete when performed within four weeks from 11 April 2001 and when the Council certified in writing that the Contractor had completed the work to its satisfaction". This description of the agreement is taken from the reasons of Nicholas J, the terms of settlement not being in the appeal papers: a similar description is also found in the report. It was also agreed that the Principal would "make various payments in the form of bank guarantees" and that "an arbitration could be proceeded with in relation to the original disputes". These descriptions of the further agreement are found in the award and the report. 6 The winding-up proceedings were dismissed. An arbitration was subsequently established, in which the Contractor was the claimant and the Principal cross-claimed. 7 Further disputes arose in relation to the performance of the Wallis Construction works. The Contractor brought proceedings against the Principal and the Principal cross-claimed against the Contractor. It was ordered that the proceedings be the subject of a reference and report. 8 The arbitration and the reference were conducted contemporaneously by Mr A M N Grieve. In the arbitration the Contractor claimed $152,460.27 and the Principal cross-claimed for $124,725.54. In the reference the Contractor claimed $78,674.59 under a bank guarantee and unspecified damages and the Principal cross-claimed for $107,266.10. There were many items of claim and cross-claim. 9 According to Mr Grieve's award and report, the award "address[ed] disputes which arose during the first visit of the Contractor to complete the works" and the report "address[ed] disputes which arose during the second visit of the Contractor to complete the works". The first visit was the original contract works, the second visit was the Wallis Constructions works. Mr Grieve said in the report that "the applicability of the Contract to the settlement works was not disputed in the proceedings", meaning as I understand it the Wallis Constructions works, but that "[t]he effect of the settlement proceedings was to vary some of the terms of the original Contract such as the time to complete and the method of payment". 10 Mr Grieve delivered a report on 21 August 2002 and an award on 4 September 2002, with a corrected award on 11 December 2002. He determined by the award that the Principal should pay the Contractor $109,233.39 and the Contractor should pay the Principal $15,396.00, a net payment by the Principal to the Contractor of $93,837.39. He reported that the Principal should pay the Contractor $87,720.80 and the Contractor should pay the Principal $7,360.00, a net payment by the Principal to the Contractor of $80,360.80. 11 The Principal brought proceedings applying for leave to appeal from the award. By notice of motion in the existing proceedings the Contractor sought orders that the report be adopted and the Principal pay to it the $80,360.80, and by notice of motion in the existing proceedings the Principal sought an order that the report be rejected save as to two of the items. 12 The application for leave to appeal from the award and the notices of motion were heard contemporaneously by Nicholas J. Not all of the items of claim and cross-claim were ultimately in issue before him, although it seems that some were abandoned only during the course of the hearing. In the application for leave to appeal from the award the items in issue were Contractor's bonus ($4,500.00) and the reciprocal Principal's liquidated damages ($32,400.00), rutting to roads ($5,400.00), hourly hire ($3,830.00) and provisional items ($32,839.83). In the notices of motion the items in issue were table drains on high side ($10,280.00), sealing of drains ($29,930.00) and liquidated damages ($18,900.00). As will appear, there was duplication in the items of liquidated damages. 13 The present applications for leave to appeal were from his Honour's decisions with respect to Contractor's bonus and Principal's liquidated damages and with respect to table drains on high side.