(c) in any event, Cargill was not then entitled (by reason of the fact that it had reached an enforceable agreement to resolve disputed rights, or had by its conduct waived or would be estopped in equity from asserting any entitlements, in respect of demurrage for that part of the force majeure period) to raise the question whether demurrage was payable in the period from 0815hrs on 8 June 2007 to 1800 hrs on 21 June 2007 (to which I refer as the estoppel/waiver finding); though the Arbitrator went on to say that if Cargill had been so entitled he would have concluded that demurrage was not payable in that period by reference to the conclusion he had already reached in relation to the force majeure period.
4 There is no challenge to any of the Arbitrator's findings summarised in (a) to (c) above (though Cargill does seek to challenge the conclusion that demurrage was not payable during the period of force majeure as so found). Rather, Cargill challenges the Arbitrator's December 2009 award by reference to what is contended to be the Arbitrator's failure to deal (or to deal correctly) with an alternative argument said to have been put by Cargill to the Arbitrator in relation to its demurrage claim.
5 That alternative argument, in essence, is that the period between the commencement of conditions amounting to force majeure (0815 on 8 June 2007) and the giving (at 1348 on 13 June 2007) of a force majeure notice, whether or not that notice had been given as early as practicable (and hence whether or not that notice was a valid and effective notice in compliance with clause 17.2 of the agreement), should have been accepted as counting as "laytime" under the agreement.
6 If that alternative argument were to be correct, then it seems not to be disputed that laytime would have continued to run from 0815 on 8 June 2007 and would have expired not long after that at 0956hrs on 8 June 2007. (On any view, this would mean, on the Arbitrator's findings, that force majeure commenced before, albeit only very shortly before, the expiration of laytime.) Once laytime had expired, the Iron Bradyn would have been on demurrage (and once on demurrage all time lost, including time lost on account of force majeure, continues to count as demurrage).
7 Leaving aside for the present the import of Excel's arguments (which were accepted by the Arbitrator) based on waiver/estoppel or the like, Cargill contends that, had the Arbitrator found that the vessel went on to demurrage as at 0956hrs on 8 June 2007, this would have meant that Cargill's counterclaim for demurrage ran for the whole of the force majeure period from 8 to 25 June 2007.
8 In the present proceedings, Cargill seeks to challenge the Arbitrator's award in one of two alternative ways, depending on the conclusion which is reached as to an initial jurisdictional question, that being whether the arbitration is governed by the Commercial Arbitration Act 1984 (NSW) (the State Act), as Cargill contends, or the UNCITRAL Model Law in accordance with s 16 of the Commonwealth Act, as Excel contends.
9 The first is under the State Act. Cargill seeks leave pursuant to s 38(4)(b) of the State Act to appeal from the award (which requires it to establish that the State Act applies and then to satisfy the threshold requirements of section 38, namely that there was an error of law that substantially affects the parties' rights and either that there has been a manifest error of law on the face of the award or that there is both strong evidence of error and the question is one which is likely to add substantially to the certainty of commercial law).
10 Secondly, if (contrary to Cargill's primary submission) the State Act does not apply, Cargill seeks an order setting aside the award under article 34(2)(b)(ii) of the Model Law, on the basis that the award is in conflict with the public policy of the State due to the failure of the arbitrator to address Cargill's alternative argument (that failure, it is said, amounting to a denial of natural justice).
11 In its Amended Summons in these proceedings, Cargill sought not only leave to appeal but also, if successful in obtaining leave, a determination of the relevant questions of law upon the hearing of that appeal. However, before me it was conceded that it was not appropriate to entertain any appeal in the context of the present application, having regard to what was said by Allsop P (with whom Spigelman CJ and Macfarlan JA agreed) in Gordion Runoff Limited v Westport Insurance Corporation [2010] NSWCA 57, from [103]. Accordingly, the relief now claimed by Cargill (in the event that the State Act applies) is limited to the grant of leave to appeal.
12 I note that it is contended by Excel that, if the Model Law applies, then Article 34 of the Model Law provides the exclusive recourse against an arbitral award in the present case and that Cargill is thus precluded from applying for leave to appeal under s 38(4)(e) of the State Act because that provision is inconsistent with the more limited form of recourse against an arbitral award available under article 34 of the Model Law (and thus the State Act is, to the extent of the inconsistency, invalid by operation of s 109 of the Commonwealth Constitution). It was conceded by Mr Stevenson, though only for the purposes of this application, that if there were found not to have been an agreement between the parties to 'opt out' of the Model Law, then there would be a section 109 inconsistency between the two modes of review and that Cargill could proceed for a review of the Arbitrator's decision only under the provisions of the Model Law.
13 Finally, in the event that the Model Law does apply, and Cargill succeeds on its application to set aside the award, then Cargill requests that the matter be remitted to the Arbitrator pursuant to article 34(4) of the Model Law for a determination by the Arbitrator of what I will refer to as the Alternative Argument.
Background Facts
14 The agreement (a standard form agreement developed by an entity known as globalCOAL and of which there have been successive versions since May 2001) was for the delivery, over the period from March 2006 to December 2008, of coal FOB ("free on board") to three specified vessels at the port of Newcastle. (There was some dispute as to the extent to which the SCoTA form of agreement was used in the Australian coal industry in transactions for the sale of coal in and from Australia but it does not seem to be disputed that it is and can be used for the sale of seaborne thermal coal; and that it is so used in a percentage of trading contracts entered into in this country.) The version used by the parties in this case was version 5a (the standard terms of which incorporated all revisions effective as at 0630 GMT on 19 October 2005); however, there has been no subsequent change to the force majeure provisions in the current version of the agreement (hence any determination of a point of construction on the force majeure provisions of the earlier version has potentially wider relevance than for this case alone).
15 The coal deliveries were made by rail. Unfortunately, those deliveries which were due to take place in June 2007 were delayed due to disruption to the rail infrastructure in the Hunter Valley caused by severe storms in that month. The consequential delay in loading and departure of the three vessels in question gave rise to a claim for demurrage by Cargill. For the purposes of the present application, the particular dispute between the parties relates only to the claim for demurrage in respect of the delivery of coal to the MV Iron Braydn.
16 Cargill's claim for demurrage in respect of the late delivery of coal due in June 2007 seems first to have been raised shortly after the coal was in fact delivered in July 2007. Excel relied upon the force majeure provisions of the agreement to deny the claim for demurrage. There was some correspondence between the two entities during the latter part of 2007 and early 2008 in relation to that claim.
17 The Arbitrator, in his award, referred to the communications between Excel and Cargill in relation to that claim from 2007 onwards and expressed the opinion that, as at November 2007, the only matter in issue between the parties in relation to the demurrage claim was whether it extended to the period beyond 21 June 2007.
18 Relevantly, the Arbitrator noted that, by February 2008 (when Cargill issued an invoice for an "undisputed amount" of demurrage, without prejudice to its claim for the balance, which was described as the "disputed amount"), there was no hint that Cargill was reserving to itself an entitlement to claim demurrage for the period extending back before 21 June 2007. The so-called "disputed amount" (in respect of which Cargill had reserved its position at that time) related to the claim for demurrage for the period from 21 to 25 June 2007. It represents the USD amount for which Excel was ultimately successful in the arbitration before the Arbitrator. However in relation to the "disputed amount", the Arbitrator noted (at [7]) that the effect of the correspondence between the parties was that it was accepted that Excel was not liable for demurrage in the period from 8 June to 21 June 2007. (This becomes relevant when considering one of the threshold requirements for the grant of leave under the State Act, as the Arbitrator's estoppel/waiver finding, which is not challenged, has the effect that Cargill is precluded from revisiting any claim for demurrage at least in the period prior to 21 June 2007.)
19 No further steps seem to have been taken by Cargill, whether in relation to the overall demurrage now claimed or for the "disputed amount", until the term of the contract was coming to an end. At that point, when Cargill made payment in respect of the final invoice issued by Excel for the later (2009) coal deliveries it withheld an amount which included the "disputed amount" in respect of the 2007 coal deliveries. Excel then made a claim for short payment of that sum (USD299,882.47), after which Cargill served revised invoices claiming demurrage for the whole of the period from 8 to 25 June 2007. That claim was maintained by it by way of counterclaim in the arbitration (Excel being the moving party in the arbitral proceedings).
20 The Arbitrator noted that in the arbitration proceedings Cargill had put in issue every step which might lead to an entitlement on the part of Excel to rely on the force majeure provisions. The issues before the Arbitrator (which he observed were more numerous than would ordinarily be found in a commercial arbitration involving amounts of the kind there involved) included the time at which the force majeure event had occurred; whether notice of the force majeure event had been given as early as practicable, as required under the agreement; whether, under the agreement, as properly construed, demurrage was payable during a force majeure period; and whether Cargill was estopped or otherwise precluded from then asserting its claim for demurrage.
21 The issue which is the nub of the Alternative Argument (and which Cargill contends the Arbitrator failed properly to address) relates to the calculation of the period of laytime under the agreement and, in particular, whether (after commencement of force majeure) laytime continues to run up until the time at which a force majeure notice (valid or otherwise) is given. As Senior Counsel for Cargill, Mr Stevenson SC, accepted, the logical extension of this argument (if correct) is that unless a force majeure notice is given simultaneously with the commencement of a force majeure event, then laytime continues to run until such notice, valid or otherwise, is given. (By contrast, the effect of the Arbitrator's determination is that if a valid force majeure notice is given in compliance with clause 17.1 of the agreement, then clause 17.3 means that a party does not become liable for demurrage during the period from the happening of the force majeure event the subject of that notice and that the giving of a notice of intention to claim force majeure under clause 17.2 as early as practicable in the circumstances means that time lost on account of force majeure does not count as laytime.)
22 The practical context in which this issue arose was as follows. As noted earlier, the coal was to be delivered on board the Iron Bradyn at the port of Newcastle. The procedure for the delivery and loading of coal involved the giving of a notice of readiness once the particular ship had arrived in port. There was then a period of 'turntime' (12 hours), following which 'laytime' commenced.
23 Laytime (defined in clause 1.1) is the time allowed under the agreement for the loading of the vessel at the delivery point, after which time demurrage (defined in clause 1.1 as the financial compensation payable if the time used in completing loading was longer than laytime) became payable. Under the agreement, laytime was to be calculated by reference to the nominated quantity of coal to be loaded on the vessel according to the formula set out in clause 7.5 (namely, the number of hours or part thereof calculated by dividing the tonnage of the shipment, expressed in metric tonnes, by the relevant "Cargo Handling Rate" expressed in Metric Tonnes per hour). (In that regard, I note that Cargill also asserts that the Arbitrator made an error of law in placing reliance, for the purposes of addressing the argument as to laytime, on the definition of Cargo Handling Rate including its reference to Weather Working Days, a matter I consider in due course.)
24 In respect of the coal to be delivered in June 2007 to the Iron Bradyn, the issue between the parties is now not as to the time of commencement of force majeure (although that was previously in issue); rather the question is whether, in the circumstances, laytime continued to run after the commencement of the force majeure period for the purposes of calculating when Excel became liable for demurrage.
25 It seems to be accepted that, but for the severity of the storms that occurred in early June 2007 and the consequential disruption to the rail infrastructure over most of that month, laytime (the period in which the Iron Bradyn was required to be loaded and after which demurrage would have been payable by Excel) would have ceased (and the Iron Bradyn would have gone on demurrage) at 0956hrs on 8 June 2007. It also seems to be accepted that, had the Iron Bradyn been on demurrage prior to the commencement of force majeure, the operation of force majeure would not have affected Excel's liability for demurrage (it being broadly said that 'once in demurrage, always in demurrage', although there seem to be some exceptions (not material in the present case) to that principle, as identified by the Arbitrator at [170]).
26 Excel gave a notice of intention to claim force majeure of the kind contemplated by clause 17.2 at 1348hrs on 13 June 2007. (It had the day before given a notice of force majeure for the purposes of clause 17.1 and in that regard I note that the agreement contemplated two separate force majeure notices, only the second of which was in contention before the Arbitrator.) Whether the 13 June 2007 force majeure notice had been given as early as practicable for the purposes of clause 17.2 of the agreement was in issue before the Arbitrator, who ultimately found that it had. (Cargill had asserted that the failure to give a notice as early as practicable rendered it of no effect.)
27 As noted earlier, the Arbitrator ultimately found that Excel did not become liable for demurrage in respect of the Iron Bradyn until 25 June 2007 (after the cessation of the force majeure period).
28 Cargill's principal submission in relation to the force majeure notice was that it was not valid or effective, as it had not been issued as early as practicable in the circumstances. It does not seek the challenge the Arbitrator's finding in that regard. It relies now on the alternative submission it says it raised, namely that, even if the notice was not held to be invalid or ineffective, nevertheless the "delay" in its issue was to be taken into account when calculating whether laytime had expired and whether the vessel had gone on demurrage (as Cargill contended) on 8 June 2007. I consider in more detail below the content of the submissions put to the Arbitrator. For present purposes I simply note that Cargill's complaint, in substance, is that the Arbitrator failed to deal at all (or dealt incorrectly) with the Alternative Argument identified now as being to the effect that (irrespective of whether the force majeure notice was a notice compliant with clause 17.2) laytime continued to run until a force majeure notice was given. (As I understand it, this argument requires acceptance of the proposition that a notice given as early as practicable in all the circumstances may nevertheless still be a notice the giving of which was the subject of delay for the purposes of clause 17.2.)
29 Senior Counsel for Excel, Mr Gleeson SC, submits that, to the extent that the Alternative Argument was put to the Arbitrator, it was rejected on the basis that the Arbitrator had concluded that notice was given as early as practicable (and hence, as I understand the submission, it was not necessary for the Arbitrator expressly to consider an argument predicated on a proposition antithetical to such a finding - namely, that there had been a delay in the giving of the notice) (as to which it says there was no manifest error of law) and, alternatively, to the extent that what Cargill is now seeking is to put an argument which was not in fact put (or put clearly) before the Arbitrator, there cannot be said to have been any denial of natural justice in the Arbitrator not having considered or expressly addressed the argument. It is submitted that Cargill was not deprived of a fair hearing of the case as put by it at the arbitration.
Issues
30 There are a number of jurisdictional and threshold issues which arise on the present application: