Campbelltown City Council v WSN Environmental Solutions Pty Ltd
[2015] NSWCA 299
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2015-08-31
Before
Bathurst CJ, Meagher JA, Ward JA, Sackar J
Catchwords
- 221 CLR 522 York Air Conditioning & Refrigeration (Australasia) Pty Ltd v Commonwealth [1949] HCA 23
Source
Original judgment source is linked above.
Catchwords
Judgment (10 paragraphs)
Solicitors: Sparke Helmore Lawyers (Appellants) Maddocks Lawyers (Respondent) File Number(s): 2015/106025 Decision under appeal Court or tribunal: Supreme Court of New South Wales Jurisdiction: Equity Citation: [2015] NSWSC 155 Date of Decision: 6 March 2015 Before: Sackar J File Number(s): 2014/371801
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.] HEADNOTE [This headnote is not to be read as part of the judgment] By a Processing Contract dated 14 August 2006, the respondent, WSN Environmental Solutions Pty Ltd, processed waste on behalf of the appellant Councils. The Contract is for a term of 15 years and requires each Council to pay a fee calculated by reference to the tonnage of waste delivered to the respondent for processing. Provision is made for the variation of the payable fee in certain circumstances. Clause 24.3 defines two circumstances in which the respondent will be entitled to a variation. Clause 24.2 provides that, in those circumstances, the parties will negotiate as to "whether" and "how" the respondent should be compensated. In the event that the parties cannot agree, those questions may be referred to an expert for determination in accordance with cl 25. Clause 24.4 states that when the respondent incurs "a demonstrable material increase in costs, which are beyond [its] control … and which were reasonably unforeseeable as at the date of the Contract, the Parties agree to negotiate reasonably and in good faith as to whether a variation circumstance should apply". The mixed waste facility operated by the respondent under the Contract was decommissioned due to concerns as to its "odour footprint". From February 2011, waste was transported to and processed at an alternative facility. The respondent claimed this change constituted a variation circumstance within cl 24.4. The parties negotiated but could not agree as to whether the change in facility met the description in cl 24.4. The respondent sought to refer the dispute as to "whether a variation circumstance should apply" to an expert under cl 25. The Councils sought a declaration that the respondent was not entitled to refer the dispute for determination in that way. The primary judge disagreed with the Councils' construction of the Contract and made orders declaring that the respondent was so entitled. The issue before the Court was whether the primary judge erred in finding that, on the proper construction of the Contract, the parties' dispute as to "whether a variation circumstance should apply" under cl 24.4 was a dispute to be dealt with via the dispute resolution mechanism in cll 24.2(2) and 25. The Court held, allowing the appeal (per Meagher JA, Bathurst CJ and Ward JA agreeing): As provided by cl 24.2(4), a variation circumstance will exist "in accordance with the provisions of Clause 24.4", using the term "exist" in the same sense that it is used in cl 24.3, only if the parties have undertaken negotiations under cl 24.4 and reached an agreement that a variation circumstance should "apply" to the notified increase in costs: [8], [32], [34], [45]. The parties cannot be said to have intended that any increase in costs asserted to be within cl 24.4 would constitute an additional "variation circumstance" because it is likely that, as these circumstances were unforeseeable at the time of the Contract, the parties were unable to agree at that time as to who should bear the risk of such an event and so agreed in the event such a circumstance occurred to negotiate on that question reasonably and in good faith: [6], [9], [36], [45]. In the absence of agreement between the parties that a variation circumstance should apply to the increase in costs asserted to be within cl 24.4, there is no dispute falling within cl 24.2(2) and the respondent is not entitled to refer the present dispute to an expert: [9], [37], [45].