In Regata Developments Pty Ltd v Westpac Banking Corporation, unreported, FCA, 5 March 1993, Davies J said that indemnity costs may be awarded where an unsuccessful proceeding was brought and prosecuted "not for the bona fide purpose of protecting and enforcing a legal right, but to achieve an ulterior or extraneous purpose" (at 4).
In Colgate Palmolive Pty Ltd v Cussons Pty Ltd (1993) 46 FCR 225, Sheppard J noted that "an imprudent refusal of an offer to compromise" was one circumstance which had been thought sufficient to warrant the exercise of the discretion.
In John S Hayes, supra, Hill J declined to order indemnity costs in favour of a respondent, noting that the case was not one in which the applicant had had "no chance of success" (at 206). His Honour concluded that it was not "so unreasonable" (at 207) for the applicant to have brought and continued its case against the respondent that indemnity costs should be ordered. Similarly, in The Sanko Steamship Co Ltd and Grand Slam Enterprise Corporation v Sumitomo Australia Ltd, unreported, FCA, 7 February 1996 ("Sanko"), Sheppard J said that recovery of costs on the usual party and party basis
should "only be departed from where the conduct of the party against whom the order is sought is plainly unreasonable" (at 9 - emphasis supplied).
A different approach was taken by Rolfe J in Multicon Engineering Pty Ltd v Federal Airports Corporation, unreported, NSW/Sup Ct, 20 June 1996 and raises a question of principle. His Honour expressed disagreement with Hill J in John S Hayes and Sheppard J in Sanko, in so far as their Honours would require an applicant for indemnity costs to prove that the non-acceptance of its offer was unreasonable. Rather, Rolfe J took the view that the non-acceptance of an offer which the ultimate result established had favoured the offeree, itself prima facie demonstrated unreasonable conduct and an entitlement to indemnity costs with the result that the offeree bore the onus of showing why indemnity costs should not be ordered.
With respect, I would follow the two single judge decisions in this Court unless I thought that they were plainly wrong. I do not think that they were, and will therefore follow them. I will refer to certain considerations which lead me to think that they were not plainly wrong. Order 23 establishes a regime which, if utilised, gives rise to a presumptive entitlement to indemnity costs. Notwithstanding the policy of encouraging settlement of litigation, it should not be assumed that the mere writing of a Calderbank letter generates the same presumptive entitlement to indemnity costs that is provided for in O 23. In one respect, the present case illustrates why not. If O 23 had been complied with, MGICA's offer would have had to be open to be accepted not less than 14 days beginning on the day after the offer was made (O 23, sub-s 5 (3)). Accordingly, in view of the offer's expiry at 10.00 am on 7 August 1995, it would have had to be made no later than 23 July 1995. An offer made then would have been more protective of the position of the respondents as offerees than the Calderbank letter which was in fact written on 3 August 1995. Moreover, in a case of offers to pay a sum of money inclusive of interest, O 23 sub-r 4 (2) requires that the notice of offer specify the amount that is in respect of interest and how it is calculated. A Calderbank letter containing an offer to pay a sum of money which did not specify those matters would not be so protective of the offeree's interests.
The foregoing considerations merely show that there are elements of the regime established by O 23 which may be more protective of an offeree's position than the unregulated offer made in a Calderbank letter. It is difficult to accept, for example, that in the extreme case of an offer made in a Calderbank letter which contained only a minimal element of compromise and was open for acceptance for say only one day, should, in the event of total success of the offeror, give rise to a presumptive entitlement to indemnity costs generally similar to that provided for in O 23, even if, in such a case, the presumptive entitlement might be easily displaced by the offeree.
In many cases the different approaches of Hill J and Sheppard J on the one hand and Rolfe J on the other hand will not produce a different result. The present is such a case.
Clearly, the circumstances must take a case out of the "ordinary" or "usual" category if an order for indemnity costs is to be made, since, as noted earlier, the Rules evince an intention that in that category of case, an order for costs signifies an order for costs on a party and party basis. Perhaps the various "tests" which have been suggested are classifiable as "abuse of process", "ulterior or extraneous purpose" and "unreasonableness" tests. Be this as it may, I have concluded that none of the formulations to which I have referred encompass the present case.
MGICA points out that the respondents had themselves resorted to the use of a Calderbank letter in their solicitors' letter dated 31 July 1995. But the question whether the respondents would have been advantaged thereby on the issue of costs is an open one: it raises an issue of the same kind that MGICA's present application raises.
MGICA observes that at the time when its offer was made on 3 August 1995, it was too late to invoke the regime afforded by O 23 because the hearing was to commence on 7 August 1995 with an estimated duration of seven days. This is true, but it was open to either party to have resorted to O 23 by taking action earlier.
MGICA submits that the respondents could and should have appreciated the errors in his valuation which the second respondent ("Mr Kenny") conceded in cross examination he had made. With the benefit of hindsight, he could, and, in a perfect world I suppose should, have done so. But such matters are ordinary incidents of litigation which contribute to a party's failure in a proceeding and the making of the usual order for costs against it. It is not submitted that when the respondents were considering MGICA's offer, Mr Kenny was aware that his valuation contained errors, correction of which would necessitate the concessions that he made in cross examination and a reduction in the amount of his valuation to a figure substantially less than $5,500,000.
For their part, the respondents submit that the precise basis on which MGICA sought to establish, and succeeded in establishing, negligence had not been spelled out in the pleadings or particulars. The respondents refer to a letter dated 8 August 1994 from their solicitors to MGICA's solicitors seeking particulars of sub-para (l) of para 20 of the amended statement of claim which was as follows:
"(l)Ascribing to the buildings constructed on the land, a value greater than could reasonably be ascribed to them. The overestimate of the value of the buildings appears to be partly attributable to an incorrect calculation of the
floor area of the buildings and partly to the allocation of an excessive rate per square metre for the value of the buildings."